$93.62Avg low bid / HR
$107.00Avg of all bids
$130.39Avg engineer's estimate
37Jobs · 27,574 HR
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 4 | 2,012 | $84.69 | $88.34 |
| 2023 | 3 | 1,960 | $136.63 | $89.61 |
| 2022 | 7 | 4,172 | $100.48 | $109.69 |
| 2021 | 4 | 3,000 | $92.00 | $107.77 |
| 2020 | 8 | 7,080 | $110.73 | $107.02 |
| 2019 | 2 | 2,400 | $68.48 | $104.87 |
| 2018 | 6 | 4,980 | $66.44 | $130.91 |
| 2017 | 3 | 1,970 | $85.70 | $85.35 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Aug 2, 2024 | 6467-71-001 | HarrisHouston | 72 HR | $250.00 | ROY JORGENSEN ASSOCIATES, INC. |
| May 2, 2024 | 6464-32-001 | NavarroDallas | 800 HR | $72.00 | AWP SAFETY |
| Apr 5, 2024 | 6462-52-001 | DallasDallas | 900 HR | $80.00 | AWP SAFETY |
| Jan 5, 2024 | 6448-75-001 | DentonDallas | 240 HR | $95.00 | SUPERIOR TRAFFIC CONTROL, LLC |
| Dec 5, 2023 | 6450-09-001 | DallasDallas | 900 HR | $113.00 | AWP SAFETY |
| Aug 3, 2023 | 6436-90-001 | KaufmanDallas | 1,000 HR | $155.00 | AWP SAFETY |
| Jun 7, 2023 | 6437-81-001 | DentonDallas | 60 HR | $185.00 | BARRICADES UNLIMITED |
| Dec 2, 2022 | 6416-34-001 | DallasDallas | 900 HR | $30.00 | FC TRAFFIC CONTROL, INC. |
| Dec 1, 2022 | 6416-32-001 | DallasDallas | 900 HR | $100.00 | FC TRAFFIC CONTROL, INC. |
| Nov 3, 2022 | 6420-99-001 | BosqueWaco | 700 HR | $75.00 | STATEWIDE SAFETY SYSTEMS |
| Sep 7, 2022 | 6399-15-001 | LibertyBeaumont | 100 HR | $100.00 | ROY JORGENSEN ASSOCIATES, INC. |
| May 4, 2022 | 6391-55-001 | HarrisHouston | 72 HR | $100.00 | ROY JORGENSEN ASSOCIATES, INC. |
| Apr 7, 2022 | 6394-46-001 | EllisDallas | 500 HR | $155.00 | TOTAL HIGHWAY MAINTENANCE, LLC |
| Jan 6, 2022 | 6390-44-001 | KaufmanDallas | 1,000 HR | $155.00 | STATEWIDE SAFETY SYSTEMS |
| Dec 2, 2021 | 6389-97-001 | DallasDallas | 900 HR | $125.00 | STATEWIDE SAFETY SYSTEMS |
| Dec 1, 2021 | 6389-96-001 | DallasDallas | 900 HR | $115.00 | SELECT MAINTENANCE, L.L.C. |
| Nov 3, 2021 | 6389-00-001 | BosqueWaco | 700 HR | $50.00 | ELITE CASTLE RESOURCES LLC |
| Oct 26, 2021 | 6388-01-001 | EllisDallas | 500 HR | $50.00 | ELITE CASTLE RESOURCES LLC |
| Dec 3, 2020 | 6373-84-001 | DallasDallas | 900 HR | $170.00 | BARRICADES UNLIMITED |
| Dec 2, 2020 | 6373-83-001 | DallasDallas | 900 HR | $110.00 | STATEWIDE SAFETY SYSTEMS |
| Oct 1, 2020 | 6366-76-001 | DallasDallas | 1,200 HR | $115.00 | STATEWIDE SAFETY SYSTEMS |
| Oct 1, 2020 | 6366-75-001 | DallasDallas | 1,200 HR | $110.00 | STATEWIDE SAFETY SYSTEMS |
| May 8, 2020 | 6351-58-001 | McLennanWaco | 1,000 HR | $75.00 | CROSS PLUS CONSTRUCTION, LLC |
| Mar 5, 2020 | 6354-27-001 | KaufmanDallas | 500 HR | $99.00 | ALTUS TRAFFIC MANAGEMENT LLC |
| Feb 6, 2020 | 6354-40-001 | EllisDallas | 1,080 HR | $100.00 | TOTAL HIGHWAY MAINTENANCE, LLC |
| Jan 9, 2020 | 6352-29-001 | BosqueWaco | 300 HR | $98.33 | AREA WIDE PROTECTIVE, INC. |
| Sep 6, 2019 | 6344-77-001 | DallasDallas | 1,200 HR | $72.50 | TOTAL HIGHWAY MAINTENANCE, LLC |
| Sep 5, 2019 | 6344-76-001 | DallasDallas | 1,200 HR | $64.46 | TOTAL HIGHWAY MAINTENANCE, LLC |
| Dec 6, 2018 | 6332-83-001 | BosqueWaco | 500 HR | $84.00 | AREA WIDE PROTECTIVE, INC. |
| Nov 6, 2018 | 6328-19-001 | EllisDallas | 1,080 HR | $50.00 | NIXON ENGINEERING |
| Sep 7, 2018 | 6332-53-001 | DallasDallas | 1,200 HR | $75.40 | ALTUS TRAFFIC MANAGEMENT LLC |
| Sep 7, 2018 | 6332-83-001 | BosqueWaco | 500 HR | $0.1000 | NIXON ENGINEERING |
| Sep 6, 2018 | 6331-56-001 | DallasDallas | 1,200 HR | $93.00 | AREA WIDE PROTECTIVE, INC. |
| Jan 4, 2018 | 6322-33-001 | KaufmanDallas | 500 HR | $65.45 | ALTUS TRAFFIC MANAGEMENT LLC |
| Nov 7, 2017 | 6319-58-001 | CollinDallas | 50 HR | $87.18 | ALTUS TRAFFIC MANAGEMENT LLC |
| Nov 3, 2017 | 6315-22-001 | DallasDallas | 960 HR | $86.28 | ALTUS TRAFFIC MANAGEMENT LLC |
| Nov 2, 2017 | 6315-21-001 | DallasDallas | 960 HR | $85.04 | ALTUS TRAFFIC MANAGEMENT LLC |