$31.32Avg low bid / LF
$21.99Avg of all bids
$35.13Avg engineer's estimate
15Jobs · 819,679 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2025 | 1 | 1,702 | $47.85 | $53.78 |
| 2024 | 1 | 12,455 | $48.05 | $35.43 |
| 2023 | 1 | 45,908 | $39.07 | $39.12 |
| 2021 | 3 | 495,902 | $34.92 | $24.93 |
| 2020 | 2 | 26,312 | $20.83 | $22.75 |
| 2019 | 1 | 390 | $51.40 | $44.13 |
| 2018 | 1 | 55,100 | $50.00 | $28.07 |
| 2017 | 5 | 181,910 | $14.05 | $16.87 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jan 7, 2025 | 0151-10-001 | WilliamsonAustin | 1,702 LF | $47.85 | WEBBER, LLC |
| Apr 4, 2024 | 0195-03-087 | DentonDallas | 12,455 LF | $48.05 | SEMA CONSTRUCTION, INC. |
| Oct 6, 2023 | 2452-02-130 | BexarSan Antonio | 45,908 LF | $39.07 | PULICE CONSTRUCTION, INC. |
| Dec 1, 2021 | 0113-13-166 | TravisAustin | 150,073 LF | $23.75 | COPASA INC |
| Jul 1, 2021 | 0113-07-075 | HaysAustin | 5,765 LF | $26.00 | RELMCO, INC. |
| Jun 3, 2021 | 2452-02-128 | BexarSan Antonio | 340,064 LF | $40.00 | ZACHRY CONSTRUCTION CORPORATION |
| Oct 1, 2020 | 0549-03-024 | CollinDallas | 20,787 LF | $20.25 | MARIO SINACOLA & SONS EXCAVATING, INC. |
| Oct 1, 2020 | 0902-90-141 | TarrantFort Worth | 5,525 LF | $23.00 | ZACHRY CONSTRUCTION CORPORATION |
| May 8, 2019 | 0836-02-073 | BellWaco | 390 LF | $51.40 | TEXAS MATERIALS GROUP, INC. |
| Jul 10, 2018 | 0253-04-138 | BexarSan Antonio | 55,100 LF | $50.00 | ZACHRY CONSTRUCTION CORPORATION |
| Aug 9, 2017 | 0015-13-382 | TravisAustin | 34,806 LF | $7.90 | J.D. ABRAMS, L.P. |
| Aug 8, 2017 | 0047-18-075 | GraysonParis | 2,321 LF | $17.57 | ED BELL CONSTRUCTION COMPANY |
| Aug 8, 2017 | 3136-01-015 | TravisAustin | 78,874 LF | $11.75 | WEBBER, LLC |
| Mar 8, 2017 | 0007-06-084 | EastlandBrownwood | 48,843 LF | $22.00 | ZACHRY CONSTRUCTION CORPORATION |
| Feb 2, 2017 | 0253-04-146 | BexarSan Antonio | 17,066 LF | $14.03 | WEBBER, LLC |