$16.15Avg low bid / SY
$16.21Avg of all bids
$14.26Avg engineer's estimate
12Jobs · 1,230,338.6 SY
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2023 | 3 | 285,395.6 | $22.55 | $21.92 |
| 2022 | 1 | 209,181 | $14.00 | $17.25 |
| 2021 | 1 | 14,109 | $25.00 | $22.13 |
| 2020 | 1 | 35,810 | $7.00 | $9.52 |
| 2019 | 2 | 159,940 | $14.08 | $14.18 |
| 2018 | 2 | 370,667 | $14.28 | $14.27 |
| 2017 | 2 | 155,236 | $15.16 | $15.48 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Nov 1, 2023 | 1880-01-008 | FanninParis | 3,615 SY | $28.00 | HIGHWAY 19 CONSTRUCTION LLC |
| Aug 2, 2023 | 0579-02-014 | HuntParis | 143,281.6 SY | $25.35 | D. L. LENNON INCORPORATED - CONTRACTOR |
| Feb 1, 2023 | 0174-04-040 | FanninParis | 138,499 SY | $19.51 | A. K. GILLIS & SONS, LLC |
| Nov 2, 2022 | 2906-01-006 | MidlandOdessa | 209,181 SY | $14.00 | JONES BROS. DIRT & PAVING CONTRACTORS, INC. |
| Jun 4, 2021 | 1502-01-029 | LubbockLubbock | 14,109 SY | $25.00 | SACYR CONSTRUCTION USA LLC |
| Oct 1, 2020 | 2224-01-099 | EctorOdessa | 35,810 SY | $7.00 | RAGLE CONSTRUCTION, INC. |
| Mar 6, 2019 | 0313-02-059 | ParkerFort Worth | 8,600 SY | $19.00 | BLYTHE CONSTRUCTION, INC. |
| Jan 9, 2019 | 0139-05-043 | ReevesOdessa | 151,340 SY | $13.80 | FNF CONSTRUCTION, INC. |
| May 1, 2018 | 0139-04-045 | ReevesOdessa | 207,478 SY | $14.50 | JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY |
| Apr 4, 2018 | 0139-02-025 | ReevesOdessa | 163,189 SY | $14.00 | FNF CONSTRUCTION, INC. |
| Nov 2, 2017 | 1493-01-017 | HuntParis | 42,880 SY | $12.56 | A. K. GILLIS & SONS, INC. |
| Aug 8, 2017 | 0139-03-039 | ReevesOdessa | 112,356 SY | $16.15 | FNF CONSTRUCTION, INC. |