SH115__FM874_3MI_S_ANDREWS_C/L
0354-04-041 · let Nov 6, 2025 · Winkler, Odessa · Super-2 Highway
$28,204,481Low bid: JONES BROS. DIRT & PAVING CONTRACTORS, INC.-21.5% vs estimate $35,916,484
$2,261,902Left on the table8.0% gap to the second bid
6BiddersSpread 45% low to high
115Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | JONES BROS. DIRT & PAVING CONTRACTORS, INC. | $28,204,481 | -21.5% | $2,261,902 | 1+$976,150 | 1-$258,239 | |
| 2 | RAGLE CONSTRUCTION, INC. | $30,466,383 | +8.0% | -15.2% | $326,891 | 2+$3,065,294 | 1-$258,239 |
| 3 | FNF CONSTRUCTION, INC. | $30,793,274 | +9.2% | -14.3% | $1,496,021 | 2+$2,841,694 | 0 |
| 4 | CK NEWBERRY, LLC | $32,289,295 | +14.5% | -10.1% | $2,333,273 | 2+$2,694,510 | 0 |
| 5 | A. L. HELMCAMP, INC. | $34,622,568 | +22.8% | -3.6% | $6,280,911 | 2+$2,457,342 | 0 |
| 6 | JAMES HAMILTON CONSTRUCTION CO. | $40,903,479 | +45.0% | 13.9% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
JONES BROS. DIRT & PAVING CONTRACTORS, INC. vs RAGLE CONSTRUCTION, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,500,000.00 | $3,000,000.00 | $523,850.32 | $1,500,000 |
| 110-7001 EXCAV (ROADWAY) | 145,380 CY | $9.50 | $18.00 | $11.68 | $1,235,730 |
| 344-7005 SP MIXES SP-B SAC-B PG70-22 | 116,326 TON | $90.00 | $100.00 | $94.47 | $1,163,260 |
| 346-7009 STONE-MTRX-ASPH SMA-D SAC-A PG76-22 | 32,488 TON | $132.00 | $105.00 | $152.44 | -$877,176 |
| 432-7002 RIPRAP (CONC)(5 IN) | 2,523.5 CY | $714.00 | $500.00 | $585.15 | -$540,029 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 23 MO | $15,000.00 | $37,200.00 | $11,585.04 | $510,600 |
| 105-7027 RMV (7") TRT/UNTRT BASE & ASPH PAV | 167,570 SY | $5.55 | $3.30 | $6.13 | -$377,033 |
| 505-7001 TMA (STATIONARY) | 650 DAY | $27.50 | $346.00 | $217.57 | $207,025 |
| 462-7010 CONC BOX CULV (6 FT X 2 FT) | 837 LF | $673.20 | $480.00 | $558.64 | -$161,708 |
| 247-7023 FL BS (CMP IN PLC)(TY A GR 4) (4") | 133,054 SY | $7.77 | $6.60 | $8.41 | -$155,673 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 22,185 CY | $17.13 | $11.00 | $12.93 | -$135,994 |
| 467-7126 SET (TY I)(S= 6 FT)(HW= 3 FT)(6:1)(C) | 15 EA | $10,269.00 | $18,510.00 | $10,420.54 | $123,615 |
| 666-7270 RE PROFILE PM TY I(Y)6"(SLD)(100MIL) | 322,584 LF | $0.9200 | $0.5500 | $0.6629 | -$119,356 |
| 316-7099 AGGR (TY-B, GR-4)(SAC-A) | 1,345 CY | $97.00 | $175.00 | $114.53 | $104,910 |
| 400-7006 CUT & RESTORING PAV | 431 SY | $347.26 | $120.00 | $171.81 | -$97,949 |
| 545-7002 CRASH CUSH ATTEN (MOVE & RESET) | 36 EA | $3,675.00 | $1,100.00 | $1,471.00 | -$92,700 |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 231,656 LF | $0.9200 | $0.5500 | $0.6515 | -$85,713 |
| 662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) | 262,700 LF | $0.1800 | $0.5000 | $0.2770 | $84,064 |
| 510-7003 ONE-WAY TRAF CONT (PORT TRAF SIG) | 20 MO | $8,000.00 | $3,800.00 | $4,980.23 | -$84,000 |
| 316-7007 ASPH (AC-20-5TR) | 55,761 GAL | $3.57 | $5.00 | $3.27 | $79,738 |
Positive: the low bidder was cheaper on that item. These 20 items account for $2,281,611 of the $2,261,902 gap.