6485-71-001 Mill & Inlay
6485-71-001 · let Nov 6, 2025 · Ector, Odessa · Routine Maintenance Project - Sealed
$1,760,245Low bid: RAGLE CONSTRUCTION, INC.+11.1% vs estimate $1,584,269
$47,804Left on the table2.7% gap to the second bid
4BiddersSpread 23% low to high
29Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RAGLE CONSTRUCTION, INC. | $1,760,245 | 11.1% | $47,804 | 4+$225,095 | 1-$348,850 | |
| 2 | REECE ALBERT, INC. | $1,808,049 | +2.7% | 14.1% | $158,483 | 2+$218,570 | 1-$419,854 |
| 3 | RK HALL, LLC | $1,966,532 | +11.7% | 24.1% | $201,365 | 5+$407,125 | 1-$374,019 |
| 4 | JONES BROS. DIRT & PAVING CONTRACTORS, INC. | $2,167,897 | +23.2% | 36.8% | 8+$1,039,689 | 2-$420,805 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
RAGLE CONSTRUCTION, INC. vs REECE ALBERT, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 105-7023 RMV (3") TRT/UNTRT BASE & ASPH PAV | 27,925 SY | $3.40 | $8.08 | $3.93 | $130,689 |
| 500-7001 MOBILIZATION | 1 LS | $175,000.00 | $103,996.33 | $523,850.32 | -$71,004 |
| 341-7024 D-GR HMA TY-C SAC-B PG70-22 | 5,113 TON | $171.00 | $182.11 | $112.90 | $56,805 |
| 351-7002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(3") | 4,275 SY | $67.00 | $54.89 | $36.28 | -$51,770 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $18,000.00 | $26,291.40 | $600.85 | $33,166 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $18,000.00 | $11,502.97 | $11,585.04 | -$19,491 |
| 310-7001 PRIME COAT (AE-P) | 5,891 GAL | $5.50 | $4.01 | $5.11 | -$8,778 |
| 502-7004 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 EA | $3,000.00 | $1,574.09 | $3,068.24 | -$8,555 |
| 505-7001 TMA (STATIONARY) | 60 DAY | $350.00 | $252.15 | $217.57 | -$5,871 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 10,460 LF | $1.75 | $1.19 | $0.4986 | -$5,858 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 8,707 LF | $1.75 | $1.19 | $0.4757 | -$4,876 |
| 105-7026 RMV (6") TRT/UNTRT BASE & ASPH PAV | 1,530 SY | $7.90 | $10.63 | $5.12 | $4,177 |
| 342-7015 TACK COAT | 1,916 GAL | $6.50 | $4.57 | $3.37 | -$3,698 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 60 DAY | $133.00 | $72.98 | $87.82 | -$3,601 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 885 EA | $1.30 | $4.11 | $0.5715 | $2,487 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 925 EA | $1.30 | $3.96 | $1.03 | $2,461 |
| 216-7001 PROOF ROLLING | 20 HR | $128.20 | $245.63 | $127.71 | $2,349 |
| 672-7004 REFL PAV MRKR TY II-A-A | 620 EA | $9.00 | $5.68 | $3.97 | -$2,058 |
| 668-7091 PREFAB PM TY C (W)(ARROW) | 18 EA | $375.00 | $483.12 | $201.69 | $1,946 |
| 666-7420 REFL PAV MRK TY I (Y)6"(BRK)(100MIL) | 2,540 LF | $1.75 | $1.19 | $0.4829 | -$1,422 |
Positive: the low bidder was cheaper on that item. These 20 items account for $47,097 of the $47,804 gap.
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(3") | 4,275 SY | $67.00 | $36.28 | 1.85x | $131,313 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $18,000.00 | $600.85 | 29.96x | $69,597 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 10,460 LF | $1.75 | $0.4986 | 3.51x | $13,090 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 8,707 LF | $1.75 | $0.4757 | 3.68x | $11,095 |
| 500-7001 MOBILIZATION | 1 LS | $175,000.00 | $523,850.32 | 0.33x | -$348,850 |
REECE ALBERT, INC.: unbalanced items
Placed 2RK HALL, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(3") | 4,275 SY | $80.00 | $36.28 | 2.20x | $186,888 |
| 105-7023 RMV (3") TRT/UNTRT BASE & ASPH PAV | 27,925 SY | $8.90 | $3.93 | 2.26x | $138,706 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $10,000.00 | $600.85 | 16.64x | $37,597 |
| 105-7026 RMV (6") TRT/UNTRT BASE & ASPH PAV | 1,530 SY | $23.49 | $5.12 | 4.58x | $28,099 |
| 315-7004 FOG SEAL (CSS-1H) | 4,418 GAL | $7.60 | $4.02 | 1.89x | $15,836 |
| 500-7001 MOBILIZATION | 1 LS | $149,831.46 | $523,850.32 | 0.29x | -$374,019 |
JONES BROS. DIRT & PAVING CONTRACTORS, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7024 D-GR HMA TY-C SAC-B PG70-22 | 5,113 TON | $198.50 | $112.90 | 1.76x | $437,697 |
| 105-7023 RMV (3") TRT/UNTRT BASE & ASPH PAV | 27,925 SY | $12.95 | $3.93 | 3.29x | $251,803 |
| 351-7002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(3") | 4,275 SY | $65.00 | $36.28 | 1.79x | $122,763 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $30,550.00 | $600.85 | 50.84x | $119,797 |
| 505-7002 TMA (MOBILE OPERATION) | 48 HR | $1,105.00 | $64.00 | 17.27x | $49,968 |
| 105-7026 RMV (6") TRT/UNTRT BASE & ASPH PAV | 1,530 SY | $24.75 | $5.12 | 4.83x | $30,026 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 10,460 LF | $1.93 | $0.4986 | 3.87x | $14,972 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 8,707 LF | $1.93 | $0.4757 | 4.06x | $12,663 |
| 500-7001 MOBILIZATION | 1 LS | $114,000.00 | $523,850.32 | 0.22x | -$409,850 |
| 505-7001 TMA (STATIONARY) | 60 DAY | $35.00 | $217.57 | 0.16x | -$10,954 |