SH115_Super2_3MI_S_AndrewsCL_AndrewsCL
0354-04-044 · let Dec 2, 2025 · Winkler, Odessa · Super-2 Highway
$24,397,885Low bid: JONES BROS. DIRT & PAVING CONTRACTORS, INC.-8.2% vs estimate $26,580,487
$4,196,200Left on the table17.2% gap to the second bid
5BiddersSpread 33% low to high
226Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | JONES BROS. DIRT & PAVING CONTRACTORS, INC. | $24,397,885 | -8.2% | $4,196,200 | 1+$851,150 | 0 | |
| 2 | FNF CONSTRUCTION, INC. | $28,594,085 | +17.2% | 7.6% | $1,292,392 | 3+$4,425,610 | 0 |
| 3 | RAGLE CONSTRUCTION, INC. | $29,886,476 | +22.5% | 12.4% | $35,135 | 3+$5,115,475 | 0 |
| 4 | A. L. HELMCAMP, INC. | $29,921,612 | +22.6% | 12.6% | $2,559,735 | 1+$2,026,150 | 0 |
| 5 | JAMES HAMILTON CONSTRUCTION CO. | $32,481,346 | +33.1% | 22.2% | 3+$3,244,703 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
JONES BROS. DIRT & PAVING CONTRACTORS, INC. vs FNF CONSTRUCTION, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 346-7009 STONE-MTRX-ASPH SMA-D SAC-A PG76-22 | 28,531 TON | $132.00 | $0.00 | $152.44 | -$3,766,092 |
| 110-7001 EXCAV (ROADWAY) | 112,795 CY | $9.47 | $25.00 | $11.68 | $1,751,706 |
| 500-7001 MOBILIZATION | 1 LS | $1,375,000.00 | $2,859,000.00 | $523,850.32 | $1,484,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 22 MO | $15,000.00 | $38,325.00 | $11,585.04 | $513,150 |
| 462-7010 CONC BOX CULV (6 FT X 2 FT) | 868 LF | $506.76 | $710.00 | $558.64 | $176,412 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 18,903 CY | $16.70 | $8.00 | $12.93 | -$164,456 |
| 105-7027 RMV (7") TRT/UNTRT BASE & ASPH PAV | 157,362 SY | $5.51 | $6.50 | $6.13 | $155,788 |
| 344-7005 SP MIXES SP-B SAC-B PG70-22 | 102,327 TON | $87.50 | $89.00 | $94.47 | $153,491 |
| 505-7001 TMA (STATIONARY) | 640 DAY | $27.50 | $220.00 | $217.57 | $123,200 |
| 403-7001 TEMPORARY SPL SHORING | 5,324 SF | $35.83 | $15.00 | $25.56 | -$110,899 |
| 432-7002 RIPRAP (CONC)(5 IN) | 2,218.6 CY | $793.41 | $747.00 | $585.15 | -$102,965 |
| 247-7023 FL BS (CMP IN PLC)(TY A GR 4) (4") | 111,003 SY | $8.04 | $7.25 | $8.41 | -$87,692 |
| 462-7004 CONC BOX CULV (4 FT X 3 FT) | 369 LF | $378.79 | $565.00 | $404.43 | $68,711 |
| 530-7022 INTRSCT, DRVWAYS, & TURNOUT (ACP) | 2,763 SY | $58.30 | $80.00 | $42.62 | $59,957 |
| 316-7099 AGGR (TY-B, GR-4)(SAC-A) | 1,427 CY | $89.50 | $131.00 | $114.53 | $59,221 |
| 510-7003 ONE-WAY TRAF CONT (PORT TRAF SIG) | 10 MO | $9,350.00 | $3,750.00 | $4,980.23 | -$56,000 |
| 508-7001 CONSTRUCTING DETOURS | 2,900 SY | $57.00 | $76.00 | $83.58 | $55,100 |
| 310-7001 PRIME COAT (AE-P) | 54,171 GAL | $4.55 | $5.50 | $5.11 | $51,462 |
| 468-7002 THERMOPLASTIC PIPE (PP) (24") | 408 LF | $112.61 | $0.00 | $108.87 | -$45,945 |
| 467-7125 SET (TY I)(S= 6 FT)(HW= 3 FT)(4:1)(C) | 9 EA | $12,285.00 | $7,500.00 | $10,817.63 | -$43,065 |
Positive: the low bidder was cheaper on that item. These 20 items account for $275,085 of the $4,196,200 gap.
JONES BROS. DIRT & PAVING CONTRACTORS, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,375,000.00 | $523,850.32 | 2.62x | $851,150 |
FNF CONSTRUCTION, INC.: unbalanced items
Placed 2RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 3A. L. HELMCAMP, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,550,000.00 | $523,850.32 | 4.87x | $2,026,150 |