FM 1300 BRIDGE REPLACEMENT 2305
0420-10-018 · let Dec 2, 2025 · Wharton, Yoakum · Bridge Replacement
$2,667,278Low bid: SCOUT 5 CONSTRUCTION LLC-9.1% vs estimate $2,933,267
$49,706Left on the table1.9% gap to the second bid
10BiddersSpread 54% low to high
66Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SCOUT 5 CONSTRUCTION LLC | $2,667,278 | -9.1% | $49,706 | 5+$459,629 | 7-$884,054 | |
| 2 | HUNTER INDUSTRIES, LTD. | $2,716,984 | +1.9% | -7.4% | $47,053 | 2+$37,049 | 3-$166,154 |
| 3 | STX CIVIL | $2,764,036 | +3.6% | -5.8% | $96,807 | 2+$71,046 | 3-$519,471 |
| 4 | E-Z BEL CONSTRUCTION, LLC | $2,860,844 | +7.3% | -2.5% | $384 | 2+$94,102 | 3-$418,380 |
| 5 | FORDE CONSTRUCTION COMPANY, INC. | $2,861,227 | +7.3% | -2.5% | $36,434 | 3+$65,793 | 2-$372,686 |
| 6 | LUCANIA CONTRACTORS LLC | $2,897,662 | +8.6% | -1.2% | $166,299 | ||
| 7 | TEXAS STEEL INDUSTRIAL PLACING, LLC | $3,063,960 | +14.9% | 4.5% | $63,580 | ||
| 8 | R CONSTRUCTION CIVIL, LLC | $3,127,540 | +17.3% | 6.6% | $337,593 | ||
| 9 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $3,465,133 | +29.9% | 18.1% | $629,605 | ||
| 10 | C. E. BARKER, LTD. | $4,094,738 | +53.5% | 39.6% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
SCOUT 5 CONSTRUCTION LLC vs HUNTER INDUSTRIES, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 1,145 LF | $166.40 | $3.35 | $3.92 | -$186,692 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $266,047.22 | $523,850.32 | $166,047 |
| 316-7264 ASPH (AC 20-5TR OR AC-20XP OR CRS-2P) | 6,654 GAL | $27.00 | $4.14 | $4.17 | -$152,110 |
| 247-7193 FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS) | 2,205.4 CY | $25.00 | $87.85 | $91.27 | $138,609 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 811 CY | $60.37 | $200.00 | $184.74 | $113,238 |
| 416-7004 DRILL SHAFT (24 IN) | 1,538 LF | $300.00 | $230.00 | $234.98 | -$107,660 |
| 100-7002 PREPARING ROW | 19 STA | $6,500.00 | $1,761.00 | $6,072.92 | -$90,041 |
| 420-7022 CL C CONC (CAP) | 41.6 CY | $467.00 | $2,200.00 | $1,543.38 | $72,093 |
| 422-7007 REINF CONC SLAB (SLAB BEAM) | 9,276 SF | $20.00 | $26.00 | $23.90 | $55,656 |
| 496-7036 REMOV STR (SMALL) | 2 EA | $30,000.00 | $3,200.00 | $143.01 | -$53,600 |
| 425-7018 PRESTR CONC SLAB BEAM (4SB15) | 1,740 LF | $218.73 | $190.00 | $233.81 | -$49,982 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 MO | $1,050.52 | $5,500.00 | $11,585.04 | $48,944 |
| 420-7012 CL C CONC (ABUT) | 29 CY | $394.00 | $2,000.00 | $1,307.98 | $46,574 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $2,000.00 | $45,000.00 | $28,021.15 | $43,000 |
| 316-7016 ASPH (RC-250) | 1,958 GAL | $27.00 | $6.08 | $5.28 | -$40,961 |
| 110-7001 EXCAV (ROADWAY) | 5,815 CY | $14.00 | $18.60 | $11.68 | $26,749 |
| 467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P) | 8 EA | $664.30 | $3,600.00 | $1,883.43 | $23,486 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $15,730.00 | $5,000.00 | $9,253.78 | -$21,460 |
| 450-7024 RAIL (TY SSTR) | 464 LF | $66.35 | $110.00 | $69.92 | $20,253 |
| 251-7050 REWORK BS MTL (TY C)(6")(DENS CONT) | 2,158 SY | $12.00 | $2.75 | $10.76 | -$19,962 |
Positive: the low bidder was cheaper on that item. These 20 items account for $32,181 of the $49,706 gap.
SCOUT 5 CONSTRUCTION LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 1,145 LF | $166.40 | $3.92 | 42.49x | $186,044 |
| 316-7264 ASPH (AC 20-5TR OR AC-20XP OR CRS-2P) | 6,654 GAL | $27.00 | $4.17 | 6.47x | $151,894 |
| 496-7036 REMOV STR (SMALL) | 2 EA | $30,000.00 | $143.01 | 209.77x | $59,714 |
| 316-7016 ASPH (RC-250) | 1,958 GAL | $27.00 | $5.28 | 5.12x | $42,535 |
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 151.6 CY | $240.00 | $111.76 | 2.15x | $19,442 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 247-7193 FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS) | 2,205.4 CY | $25.00 | $91.27 | 0.27x | -$146,159 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 MO | $1,050.52 | $11,585.04 | 0.09x | -$115,880 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 811 CY | $60.37 | $184.74 | 0.33x | -$100,862 |
| 420-7022 CL C CONC (CAP) | 41.6 CY | $467.00 | $1,543.38 | 0.30x | -$44,777 |
| 420-7012 CL C CONC (ABUT) | 29 CY | $394.00 | $1,307.98 | 0.30x | -$26,505 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $2,000.00 | $28,021.15 | 0.07x | -$26,021 |
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 151.6 CY | $265.56 | $111.76 | 2.38x | $23,317 |
| 467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P) | 8 EA | $3,600.00 | $1,883.43 | 1.91x | $13,733 |
| 100-7002 PREPARING ROW | 19 STA | $1,761.00 | $6,072.92 | 0.29x | -$81,927 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 MO | $5,500.00 | $11,585.04 | 0.47x | -$66,935 |
| 251-7050 REWORK BS MTL (TY C)(6")(DENS CONT) | 2,158 SY | $2.75 | $10.76 | 0.26x | -$17,292 |
STX CIVIL: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 151.6 CY | $430.00 | $111.76 | 3.85x | $48,246 |
| 316-7194 AGGR (TY-E, GR-5)(SAC-B) | 70.4 CY | $480.00 | $156.13 | 3.07x | $22,800 |
| 500-7001 MOBILIZATION | 1 LS | $215,000.00 | $523,850.32 | 0.41x | -$308,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 MO | $1,200.00 | $11,585.04 | 0.10x | -$114,235 |
| 100-7002 PREPARING ROW | 19 STA | $1,000.00 | $6,072.92 | 0.16x | -$96,386 |
E-Z BEL CONSTRUCTION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7001 EXCAV (ROADWAY) | 5,815 CY | $24.00 | $11.68 | 2.05x | $71,628 |
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 151.6 CY | $260.00 | $111.76 | 2.33x | $22,474 |
| 500-7001 MOBILIZATION | 1 LS | $220,000.00 | $523,850.32 | 0.42x | -$303,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 MO | $2,500.00 | $11,585.04 | 0.22x | -$99,935 |
| 251-7050 REWORK BS MTL (TY C)(6")(DENS CONT) | 2,158 SY | $4.00 | $10.76 | 0.37x | -$14,594 |
FORDE CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 151.6 CY | $300.00 | $111.76 | 2.68x | $28,538 |
| 316-7194 AGGR (TY-E, GR-5)(SAC-B) | 70.4 CY | $475.00 | $156.13 | 3.04x | $22,448 |
| 420-7038 CL C CONC (COLUMN) | 10.2 CY | $3,000.00 | $1,548.37 | 1.94x | $14,807 |
| 500-7001 MOBILIZATION | 1 LS | $250,000.00 | $523,850.32 | 0.48x | -$273,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 MO | $2,600.00 | $11,585.04 | 0.22x | -$98,835 |