FM 604 AT JIM NED CREEK
0974-03-014 · let Dec 3, 2025 · Taylor, Abilene · Bridge Replacement
$2,697,516Low bid: J. H. STRAIN & SONS, INC.-16.2% vs estimate $3,220,743
$571,683Left on the table21.2% gap to the second bid
9BiddersSpread 85% low to high
77Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | J. H. STRAIN & SONS, INC. | $2,697,516 | -16.2% | $571,683 | 5+$109,143 | 5-$1,105,763 | |
| 2 | STX CIVIL | $3,269,199 | +21.2% | 1.5% | $360,042 | 7+$387,439 | 6-$1,089,436 |
| 3 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $3,629,241 | +34.5% | 12.7% | $196,690 | 9+$490,584 | 3-$534,261 |
| 4 | JAMES CONSTRUCTION GROUP, LLC | $3,825,931 | +41.8% | 18.8% | $270,600 | 9+$848,611 | 2-$507,260 |
| 5 | EARTH BUILDERS, L.P. | $4,096,531 | +51.9% | 27.2% | $119,166 | 11+$718,330 | 2-$568,966 |
| 6 | THK CONSTRUCTION LLC | $4,215,697 | +56.3% | 30.9% | $250,418 | ||
| 7 | GILVIN-TERRILL, LTD. | $4,466,115 | +65.6% | 38.7% | $211,105 | ||
| 8 | COPPELL CONSTRUCTION CO., INC. | $4,677,220 | +73.4% | 45.2% | $308,545 | ||
| 9 | C. E. BARKER, LTD. | $4,985,765 | +84.8% | 54.8% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
J. H. STRAIN & SONS, INC. vs STX CIVIL, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 508-7001 CONSTRUCTING DETOURS | 1,620 SY | $66.00 | $180.00 | $83.58 | $184,680 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $240,000.00 | $523,850.32 | $140,000 |
| 403-7001 TEMPORARY SPL SHORING | 3,665 SF | $28.00 | $5.00 | $25.56 | -$84,295 |
| 432-7024 RIPRAP (STONE TY R)(DRY)(18 IN) | 620 CY | $100.00 | $225.00 | $235.33 | $77,500 |
| 247-7104 FL BS (CMP IN PLC)(TY D GR 4) (10") | 5,554 SY | $26.55 | $40.00 | $26.55 | $74,701 |
| 512-7013 PORT CTB (DES SOURCE)(SGL SLP)(TY 1) | 1,650 LF | $27.14 | $65.00 | $15.26 | $62,469 |
| 132-7002 EMBANK (FNL)(DC)(TY A) | 7,928 CY | $18.00 | $25.00 | $15.82 | $55,496 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $99,500.00 | $45,000.00 | $136,676.66 | -$54,500 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $5,000.00 | $1,400.00 | $11,585.04 | -$46,800 |
| 344-7053 SP MIXES SP-D SAC-B PG70-22 | 439 TON | $139.66 | $240.00 | $139.66 | $44,049 |
| 316-7208 AGGR (TY-PB, GR-3)(SAC-B) | 52 CY | $175.00 | $800.00 | $110.18 | $32,500 |
| 422-7002 REINF CONC SLAB (HPC) | 6,762 SF | $32.00 | $27.50 | $26.91 | -$30,429 |
| 316-7263 ASPH (MULTI OPTION) | 2,950 GAL | $10.00 | $20.00 | $3.89 | $29,500 |
| 110-7001 EXCAV (ROADWAY) | 3,093 CY | $12.00 | $20.00 | $11.68 | $24,744 |
| 400-7010 CEM STABIL BKFL | 333 CY | $250.00 | $180.00 | $138.14 | -$23,310 |
| 247-7058 FL BS (CMP IN PLC)(TY D GR 4) (6") | 923 SY | $15.85 | $40.00 | $27.39 | $22,290 |
| 344-7002 SP MIXES SP-B SAC-B PG64-22 | 895 TON | $137.66 | $160.00 | $110.21 | $19,994 |
| 450-7008 RAIL (TY T223) | 369 LF | $115.00 | $160.00 | $141.07 | $16,605 |
| 420-7023 CL C CONC (CAP)(HPC) | 43.8 CY | $1,325.00 | $1,700.00 | $1,420.15 | $16,425 |
| 496-7036 REMOV STR (SMALL) | 3,171 EA | $5.00 | $10.00 | $143.01 | $15,855 |
Positive: the low bidder was cheaper on that item. These 20 items account for $577,475 of the $571,683 gap.
J. H. STRAIN & SONS, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7010 CEM STABIL BKFL | 333 CY | $250.00 | $138.14 | 1.81x | $37,248 |
| 512-7013 PORT CTB (DES SOURCE)(SGL SLP)(TY 1) | 1,650 LF | $27.14 | $15.26 | 1.78x | $19,600 |
| 316-7263 ASPH (MULTI OPTION) | 2,950 GAL | $10.00 | $3.89 | 2.57x | $18,015 |
| 512-7037 PORT CTB (STKPL)(SGL SLP)(TY 1) | 1,620 LF | $23.40 | $12.38 | 1.89x | $17,855 |
| 540-7005 MTL BEAM GD FEN TRANS (THRIE-BEAM) | 4 EA | $6,325.00 | $2,218.70 | 2.85x | $16,425 |
| 496-7036 REMOV STR (SMALL) | 3,171 EA | $5.00 | $143.01 | 0.03x | -$437,637 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $5,000.00 | $11,585.04 | 0.43x | -$85,606 |
| 432-7024 RIPRAP (STONE TY R)(DRY)(18 IN) | 620 CY | $100.00 | $235.33 | 0.42x | -$83,903 |
| 100-7002 PREPARING ROW | 16 STA | $1,400.00 | $6,072.92 | 0.23x | -$74,767 |
STX CIVIL: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 508-7001 CONSTRUCTING DETOURS | 1,620 SY | $180.00 | $83.58 | 2.15x | $156,192 |
| 512-7013 PORT CTB (DES SOURCE)(SGL SLP)(TY 1) | 1,650 LF | $65.00 | $15.26 | 4.26x | $82,069 |
| 316-7263 ASPH (MULTI OPTION) | 2,950 GAL | $20.00 | $3.89 | 5.14x | $47,515 |
| 316-7208 AGGR (TY-PB, GR-3)(SAC-B) | 52 CY | $800.00 | $110.18 | 7.26x | $35,871 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 14,843 SY | $3.00 | $1.43 | 2.10x | $23,314 |
| 169-7009 SOIL RET BLKT(SL_MOD_CLAY_SHORT_ROLL) | 14,843 SY | $3.00 | $1.52 | 1.98x | $22,031 |
| 512-7037 PORT CTB (STKPL)(SGL SLP)(TY 1) | 1,620 LF | $25.00 | $12.38 | 2.02x | $20,447 |
| 496-7036 REMOV STR (SMALL) | 3,171 EA | $10.00 | $143.01 | 0.07x | -$421,782 |
| 500-7001 MOBILIZATION | 1 LS | $240,000.00 | $523,850.32 | 0.46x | -$283,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $1,400.00 | $11,585.04 | 0.12x | -$132,406 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $45,000.00 | $136,676.66 | 0.33x | -$91,677 |
| 100-7002 PREPARING ROW | 16 STA | $800.00 | $6,072.92 | 0.13x | -$84,367 |
| 403-7001 TEMPORARY SPL SHORING | 3,665 SF | $5.00 | $25.56 | 0.20x | -$75,355 |
HODGES AND SON CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 344-7002 SP MIXES SP-B SAC-B PG64-22 | 895 TON | $220.00 | $110.21 | 2.00x | $98,266 |
| 344-7053 SP MIXES SP-D SAC-B PG70-22 | 439 TON | $300.00 | $139.66 | 2.15x | $70,389 |
| 512-7037 PORT CTB (STKPL)(SGL SLP)(TY 1) | 1,620 LF | $55.00 | $12.38 | 4.44x | $69,047 |
| 512-7013 PORT CTB (DES SOURCE)(SGL SLP)(TY 1) | 1,650 LF | $55.00 | $15.26 | 3.60x | $65,569 |
| 400-7010 CEM STABIL BKFL | 333 CY | $300.00 | $138.14 | 2.17x | $53,898 |
| 110-7001 EXCAV (ROADWAY) | 3,093 CY | $25.00 | $11.68 | 2.14x | $41,192 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 14,843 SY | $4.00 | $1.43 | 2.80x | $38,157 |
| 316-7208 AGGR (TY-PB, GR-3)(SAC-B) | 52 CY | $690.00 | $110.18 | 6.26x | $30,151 |
| 316-7263 ASPH (MULTI OPTION) | 2,950 GAL | $12.00 | $3.89 | 3.08x | $23,915 |
| 496-7036 REMOV STR (SMALL) | 3,171 EA | $2.50 | $143.01 | 0.02x | -$445,565 |
| 100-7002 PREPARING ROW | 16 STA | $2,500.00 | $6,072.92 | 0.41x | -$57,167 |
| 506-7001 ROCK FILTER DAMS (INSTALL) (TY 1) | 870 LF | $1.00 | $37.24 | 0.03x | -$31,529 |
JAMES CONSTRUCTION GROUP, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 16 STA | $22,750.00 | $6,072.92 | 3.75x | $266,833 |
| 422-7002 REINF CONC SLAB (HPC) | 6,762 SF | $47.46 | $26.91 | 1.76x | $138,967 |
| 132-7002 EMBANK (FNL)(DC)(TY A) | 7,928 CY | $31.91 | $15.82 | 2.02x | $127,550 |
| 403-7001 TEMPORARY SPL SHORING | 3,665 SF | $58.56 | $25.56 | 2.29x | $120,943 |
| 344-7002 SP MIXES SP-B SAC-B PG64-22 | 895 TON | $193.00 | $110.21 | 1.75x | $74,101 |
| 400-7010 CEM STABIL BKFL | 333 CY | $262.97 | $138.14 | 1.90x | $41,567 |
| 420-7039 CL C CONC (COLUMN)(HPC) | 16.8 CY | $3,242.81 | $1,492.16 | 2.17x | $29,411 |
| 316-7208 AGGR (TY-PB, GR-3)(SAC-B) | 52 CY | $660.00 | $110.18 | 5.99x | $28,591 |
| 164-7017 HYDRO MULCH SEED (PERM_RURAL_SANDY) | 14,843 SY | $1.92 | $0.5289 | 3.63x | $20,648 |
| 496-7036 REMOV STR (SMALL) | 3,171 EA | $6.79 | $143.01 | 0.05x | -$431,961 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $61,378.36 | $136,676.66 | 0.45x | -$75,298 |
EARTH BUILDERS, L.P.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7002 EMBANK (FNL)(DC)(TY A) | 7,928 CY | $32.00 | $15.82 | 2.02x | $128,264 |
| 508-7001 CONSTRUCTING DETOURS | 1,620 SY | $150.00 | $83.58 | 1.79x | $107,592 |
| 344-7002 SP MIXES SP-B SAC-B PG64-22 | 895 TON | $215.00 | $110.21 | 1.95x | $93,791 |
| 400-7010 CEM STABIL BKFL | 333 CY | $400.00 | $138.14 | 2.90x | $87,198 |
| 344-7053 SP MIXES SP-D SAC-B PG70-22 | 439 TON | $295.00 | $139.66 | 2.11x | $68,194 |
| 512-7013 PORT CTB (DES SOURCE)(SGL SLP)(TY 1) | 1,650 LF | $55.00 | $15.26 | 3.60x | $65,569 |
| 316-7208 AGGR (TY-PB, GR-3)(SAC-B) | 52 CY | $900.00 | $110.18 | 8.17x | $41,071 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 14,843 SY | $4.00 | $1.43 | 2.80x | $38,157 |
| 512-7037 PORT CTB (STKPL)(SGL SLP)(TY 1) | 1,620 LF | $35.00 | $12.38 | 2.83x | $36,647 |
| 316-7263 ASPH (MULTI OPTION) | 2,950 GAL | $14.00 | $3.89 | 3.60x | $29,815 |
| 496-7036 REMOV STR (SMALL) | 3,171 EA | $0.0100 | $143.01 | 0.00x | -$453,461 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $2,700.00 | $11,585.04 | 0.23x | -$115,506 |