Bid Tab X-ray: 6496-25-001

Jan 13, 2026 · Nueces Sign up free
Set your company to personalize scores

6496-25-001 Aggregate CCAO

6496-25-001 · let Jan 13, 2026 · Nueces, Corpus Christi · Material Maintenance Project

$188,870Low bid: VULCAN CONSTRUCTION MATERIALS, LLC+1.5% vs estimate $186,000
$6,130Left on the table3.2% gap to the second bid
4BiddersSpread 39% low to high
3Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1VULCAN CONSTRUCTION MATERIALS, LLC $188,8701.5% $6,130 0 0
2BRAUNTEX MATERIALS, INC. $195,000+3.2%4.8% $9,300 1+$16,250 0
3MARTIN MARIETTA MATERIALS, INC. $204,300+8.2%9.8% $58,200 0 0
4TOUCHSTONE RESOURCES, LLC $262,500+39.0%41.1% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.

Where the job was won

VULCAN CONSTRUCTION MATERIALS, LLC vs BRAUNTEX MATERIALS, INC., biggest item swings
ItemQtyLow2ndMarket2nd minus low
8000-7056 AGGR (TY PB GR 4) (PICKUP)500 TON $38.00$72.00$39.50 $17,000
8000-7296 AGGR (TY PB GR 4) (DEL) (ST2)1,000 TON $84.83$77.00$92.46 -$7,830
8000-7295 AGGR (TY PB GR 4) (DEL) (ST1)1,000 TON $85.04$82.00$92.77 -$3,040

Positive: the low bidder was cheaper on that item. These 3 items account for $6,130 of the $6,130 gap.

BRAUNTEX MATERIALS, INC.: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
8000-7056 AGGR (TY PB GR 4) (PICKUP)500 TON $72.00$39.501.82x$16,250