6496-25-001 Aggregate CCAO
6496-25-001 · let Jan 13, 2026 · Nueces, Corpus Christi · Material Maintenance Project
$188,870Low bid: VULCAN CONSTRUCTION MATERIALS, LLC+1.5% vs estimate $186,000
$6,130Left on the table3.2% gap to the second bid
4BiddersSpread 39% low to high
3Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | VULCAN CONSTRUCTION MATERIALS, LLC | $188,870 | 1.5% | $6,130 | 0 | 0 | |
| 2 | BRAUNTEX MATERIALS, INC. | $195,000 | +3.2% | 4.8% | $9,300 | 1+$16,250 | 0 |
| 3 | MARTIN MARIETTA MATERIALS, INC. | $204,300 | +8.2% | 9.8% | $58,200 | 0 | 0 |
| 4 | TOUCHSTONE RESOURCES, LLC | $262,500 | +39.0% | 41.1% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
VULCAN CONSTRUCTION MATERIALS, LLC vs BRAUNTEX MATERIALS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8000-7056 AGGR (TY PB GR 4) (PICKUP) | 500 TON | $38.00 | $72.00 | $39.50 | $17,000 |
| 8000-7296 AGGR (TY PB GR 4) (DEL) (ST2) | 1,000 TON | $84.83 | $77.00 | $92.46 | -$7,830 |
| 8000-7295 AGGR (TY PB GR 4) (DEL) (ST1) | 1,000 TON | $85.04 | $82.00 | $92.77 | -$3,040 |
Positive: the low bidder was cheaper on that item. These 3 items account for $6,130 of the $6,130 gap.
BRAUNTEX MATERIALS, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 8000-7056 AGGR (TY PB GR 4) (PICKUP) | 500 TON | $72.00 | $39.50 | 1.82x | $16,250 |