FY26 Freestone/Leon RipRap - 01
6494-53-001 · let Jan 13, 2026 · Freestone, Bryan · Material Maintenance Project
$80,600Low bid: TOUCHSTONE RESOURCES, LLC-25.4% vs estimate $108,000
$10,455Left on the table13.0% gap to the second bid
4BiddersSpread 39% low to high
8Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TOUCHSTONE RESOURCES, LLC | $80,600 | -25.4% | $10,455 | 0 | 0 | |
| 2 | KNIFE RIVER CORPORATION - SOUTH | $91,055 | +13.0% | -15.7% | $15,081 | 0 | 0 |
| 3 | SOUTHERN SOURCING SOLUTIONS, LLC | $106,136 | +31.7% | -1.7% | $6,065 | 0 | 0 |
| 4 | RENEGADE SITE SOLUTIONS, LLC | $112,200 | +39.2% | 3.9% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
TOUCHSTONE RESOURCES, LLC vs KNIFE RIVER CORPORATION - SOUTH, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8004-7035 RIPRAP(STONE PROT)(18 IN)(DEL)(ST2) | 300 CY | $65.00 | $74.00 | $80.61 | $2,700 |
| 8004-7034 RIPRAP(STONE PROT)(18 IN)(DEL)(ST1) | 300 CY | $65.00 | $70.00 | $88.85 | $1,500 |
| 8004-7002 RIPRAP(STN CMN DRY)(3"-5")(DEL)(ST 2) | 200 CY | $43.00 | $50.00 | $62.44 | $1,400 |
| 8004-7024 RIPRAP(STONE PROT)(12 IN)(DEL)(ST2) | 100 CY | $60.00 | $73.80 | $82.66 | $1,380 |
| 8004-7001 RIPRAP(STN CMN DRY)(3"-5")(DEL)(ST 1) | 200 CY | $40.00 | $45.50 | $60.08 | $1,100 |
| 8004-7023 RIPRAP(STONE PROT)(12 IN)(DEL)(ST1) | 100 CY | $60.00 | $69.75 | $96.59 | $975 |
| 8004-7046 RIPRAP(STONE PROT)(24 IN)(DEL)(ST2) | 100 CY | $65.00 | $74.00 | $85.85 | $900 |
| 8004-7045 RIPRAP(STONE PROT)(24 IN)(DEL)(ST1) | 100 CY | $65.00 | $70.00 | $101.00 | $500 |
Positive: the low bidder was cheaper on that item. These 8 items account for $10,455 of the $10,455 gap.