SH 19 Lake Creek BRG MNT
0136-04-052 · let Jan 6, 2026 · Delta, Paris · Bridge Maintenance
$2,541,166Low bid: GIBSON & ASSOCIATES, INC.-34.6% vs estimate $3,883,588
$547,977Left on the table21.6% gap to the second bid
10BiddersSpread 75% low to high
123Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | GIBSON & ASSOCIATES, INC. | $2,541,166 | -34.6% | $547,977 | 3+$63,276 | 5-$486,556 | |
| 2 | THK CONSTRUCTION LLC | $3,089,143 | +21.6% | -20.5% | $34,754 | 4+$347,943 | 1-$282,288 |
| 3 | GARRET SHIELDS INFRASTRUCTURE | $3,123,897 | +22.9% | -19.6% | $15,861 | 3+$152,823 | 1-$79,021 |
| 4 | RAGLE CONSTRUCTION, INC. | $3,139,758 | +23.6% | -19.2% | $331,449 | 3+$510,249 | 3-$693,383 |
| 5 | STRUCTURAL INTEGRITY GROUP LLC | $3,471,207 | +36.6% | -10.6% | $44,902 | 4+$300,855 | 2-$55,665 |
| 6 | HIGHWAY 19 CONSTRUCTION LLC | $3,516,108 | +38.4% | -9.5% | $157,583 | ||
| 7 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | $3,673,691 | +44.6% | -5.4% | $359,020 | ||
| 8 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $4,032,711 | +58.7% | 3.8% | $7,340 | ||
| 9 | RISE UP CONSTRUCTION LLC | $4,040,051 | +59.0% | 4.0% | $398,628 | ||
| 10 | GREY SKY CONSTRUCTION LLC | $4,438,679 | +74.7% | 14.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
GIBSON & ASSOCIATES, INC. vs THK CONSTRUCTION LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 3,551 SF | $5.00 | $170.00 | $95.74 | $585,915 |
| 735-7060 DRIFTWOOD REMOVAL | 5,948 CY | $72.60 | $25.00 | $72.46 | -$283,125 |
| 439-7015 POLYESTER POLYMER CONC OVERLAY (3/4") | 5,372 SY | $110.00 | $142.00 | $106.74 | $171,904 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 2,130 LF | $10.00 | $90.00 | $52.29 | $170,400 |
| 439-7002 CONCRETE OVERLAY (2 IN) | 2,520 SY | $94.00 | $45.00 | $80.95 | -$123,480 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $14,250.00 | $7,000.00 | $11,585.04 | -$87,000 |
| 483-7010 HYDRO-DEMOLITION (2 IN) | 2,520 SY | $115.00 | $88.50 | $113.92 | -$66,780 |
| 788-7001 CONCRETE BEAM REPAIR | 7 EA | $1,200.00 | $10,000.00 | $4,623.25 | $61,600 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 2,130 LF | $5.00 | $25.00 | $12.08 | $42,600 |
| 545-7016 CRASH CUSH ATTEN (INSTL)(S)(W)(TL3) | 5 EA | $3,000.00 | $9,180.00 | $10,040.20 | $30,900 |
| 442-7008 STR STEEL (MISCELLANEOUS BRIDGE) | 4,530 LB | $12.50 | $7.00 | $6.21 | -$24,915 |
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7) | 1,059 LF | $33.00 | $51.84 | $38.57 | $19,952 |
| 788-7004 CONCRETE BEAM REP (STRAND SPLICE) | 1 EA | $5,600.00 | $25,000.00 | $5,892.50 | $19,400 |
| 420-7010 CL B CONC (FLUME) | 19 CY | $1,820.00 | $850.00 | $756.63 | -$18,430 |
| 500-7001 MOBILIZATION | 1 LS | $272,000.00 | $285,000.00 | $523,850.32 | $13,000 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 386.9 CY | $231.00 | $200.00 | $184.74 | -$11,994 |
| 428-7001 PENETRATING CONCRETE SURFACE TREATMENT | 534 SY | $37.40 | $15.00 | $10.07 | -$11,962 |
| 429-7010 CONC STR REPAIR (PAN GIRDER HOLE REPR) | 110 EA | $150.00 | $250.00 | $131.64 | $11,000 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 2,130 LF | $5.00 | $10.00 | $7.54 | $10,650 |
| 104-7007 REMOV CONC (RIPRAP) | 32.3 CY | $370.00 | $50.00 | $26.91 | -$10,336 |
Positive: the low bidder was cheaper on that item. These 20 items account for $499,299 of the $547,977 gap.
GIBSON & ASSOCIATES, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 442-7008 STR STEEL (MISCELLANEOUS BRIDGE) | 4,530 LB | $12.50 | $6.21 | 2.01x | $28,479 |
| 420-7010 CL B CONC (FLUME) | 19 CY | $1,820.00 | $756.63 | 2.41x | $20,204 |
| 428-7001 PENETRATING CONCRETE SURFACE TREATMENT | 534 SY | $37.40 | $10.07 | 3.71x | $14,593 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 3,551 SF | $5.00 | $95.74 | 0.05x | -$322,229 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 2,130 LF | $10.00 | $52.29 | 0.19x | -$90,075 |
| 545-7016 CRASH CUSH ATTEN (INSTL)(S)(W)(TL3) | 5 EA | $3,000.00 | $10,040.20 | 0.30x | -$35,201 |
| 788-7001 CONCRETE BEAM REPAIR | 7 EA | $1,200.00 | $4,623.25 | 0.26x | -$23,963 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 2,130 LF | $5.00 | $12.08 | 0.41x | -$15,088 |
THK CONSTRUCTION LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 3,551 SF | $170.00 | $95.74 | 1.78x | $263,686 |
| 788-7001 CONCRETE BEAM REPAIR | 7 EA | $10,000.00 | $4,623.25 | 2.16x | $37,637 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 2,130 LF | $25.00 | $12.08 | 2.07x | $27,512 |
| 788-7004 CONCRETE BEAM REP (STRAND SPLICE) | 1 EA | $25,000.00 | $5,892.50 | 4.24x | $19,108 |
| 735-7060 DRIFTWOOD REMOVAL | 5,948 CY | $25.00 | $72.46 | 0.35x | -$282,288 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 442-7008 STR STEEL (MISCELLANEOUS BRIDGE) | 4,530 LB | $30.00 | $6.21 | 4.83x | $107,754 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 2,130 LF | $20.00 | $7.54 | 2.65x | $26,550 |
| 429-7010 CONC STR REPAIR (PAN GIRDER HOLE REPR) | 110 EA | $300.00 | $131.64 | 2.28x | $18,519 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $5,000.00 | $11,585.04 | 0.43x | -$79,021 |
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 439-7002 CONCRETE OVERLAY (2 IN) | 2,520 SY | $185.00 | $80.95 | 2.29x | $262,210 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $25,000.00 | $11,585.04 | 2.16x | $160,979 |
| 510-7001 ONE-WAY TRAF CONT (FLAGGER CONT) | 216 HR | $450.00 | $46.94 | 9.59x | $87,060 |
| 735-7060 DRIFTWOOD REMOVAL | 5,948 CY | $10.00 | $72.46 | 0.14x | -$371,508 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 3,551 SF | $10.00 | $95.74 | 0.10x | -$304,474 |
| 505-7001 TMA (STATIONARY) | 148 DAY | $100.00 | $217.57 | 0.46x | -$17,401 |
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 2,130 LF | $110.00 | $12.08 | 9.10x | $208,562 |
| 442-7008 STR STEEL (MISCELLANEOUS BRIDGE) | 4,530 LB | $16.00 | $6.21 | 2.58x | $44,334 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 2,130 LF | $19.50 | $7.54 | 2.59x | $25,485 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 98 SF | $380.00 | $150.68 | 2.52x | $22,473 |
| 505-7001 TMA (STATIONARY) | 148 DAY | $1.00 | $217.57 | 0.00x | -$32,053 |
| 788-7001 CONCRETE BEAM REPAIR | 7 EA | $1,250.00 | $4,623.25 | 0.27x | -$23,613 |