FM 1160 BRIDGE REPLACEMENT 2305
1302-01-025 · let Jan 7, 2026 · Wharton, Yoakum · Bridge Replacement
$2,791,031Low bid: TEXAS STEEL INDUSTRIAL PLACING, LLC-10.8% vs estimate $3,130,081
$8,716Left on the table0.3% gap to the second bid
10BiddersSpread 50% low to high
65Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TEXAS STEEL INDUSTRIAL PLACING, LLC | $2,791,031 | -10.8% | $8,716 | 1+$41,492 | 2-$244,867 | |
| 2 | R CONSTRUCTION CIVIL, LLC | $2,799,747 | +0.3% | -10.6% | $37,350 | 4+$68,119 | 4-$798,993 |
| 3 | HUNTER INDUSTRIES, LTD. | $2,837,097 | +1.7% | -9.4% | -$25,129 | 0 | 4-$261,210 |
| 4 | STX CIVIL | $2,811,968 | +0.8% | -10.2% | $107,069 | 0 | 4-$596,401 |
| 5 | E-Z BEL CONSTRUCTION, LLC | $2,919,038 | +4.6% | -6.7% | $93,440 | 0 | 3-$530,933 |
| 6 | TREVWAY, INC. | $3,012,477 | +7.9% | -3.8% | $244,290 | ||
| 7 | FORDE CONSTRUCTION COMPANY, INC. | $3,256,768 | +16.7% | 4.0% | $74,119 | ||
| 8 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $3,330,887 | +19.3% | 6.4% | $518,294 | ||
| 9 | C. E. BARKER, LTD. | $3,849,180 | +37.9% | 23.0% | $346,746 | ||
| 10 | RAGLE CONSTRUCTION, INC. | $4,195,926 | +50.3% | 34.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
TEXAS STEEL INDUSTRIAL PLACING, LLC vs R CONSTRUCTION CIVIL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $278,851.92 | $23,000.00 | $523,850.32 | -$255,852 |
| 800-7002 NO. OF DAYS MILESTONE 1 | 7,171 $/D | $100.00 | $126.00 | $155.44 | $186,446 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 2,080 CY | $170.00 | $238.00 | $184.74 | $141,440 |
| 247-7193 FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS) | 2,137.1 CY | $98.00 | $156.00 | $91.27 | $123,952 |
| 416-7004 DRILL SHAFT (24 IN) | 1,640 LF | $210.00 | $230.00 | $234.98 | $32,800 |
| 420-7012 CL C CONC (ABUT) | 66.1 CY | $1,100.00 | $620.00 | $1,307.98 | -$31,728 |
| 420-7022 CL C CONC (CAP) | 45.4 CY | $1,500.00 | $830.00 | $1,543.38 | -$30,418 |
| 450-7008 RAIL (TY T223) | 572 LF | $160.00 | $210.00 | $141.07 | $28,600 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $30,000.00 | $19,000.00 | $9,253.78 | -$22,000 |
| 422-7007 REINF CONC SLAB (SLAB BEAM) | 10,964 SF | $20.00 | $18.00 | $23.90 | -$21,928 |
| 425-7018 PRESTR CONC SLAB BEAM (4SB15) | 2,055.26 LF | $185.00 | $175.00 | $233.81 | -$20,553 |
| 316-7016 ASPH (RC-250) | 1,855 GAL | $4.15 | $14.00 | $5.28 | $18,272 |
| 316-7264 ASPH (AC 20-5TR OR AC-20XP OR CRS-2P) | 6,286 GAL | $4.35 | $7.00 | $4.17 | $16,658 |
| 168-7001 VEGETATIVE WATERING | 61 TGL | $1.00 | $260.00 | $8.43 | $15,799 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $40,000.00 | $27,000.00 | $28,021.15 | -$13,000 |
| 425-7019 PRESTR CONC SLAB BEAM (5SB15) | 513.8 LF | $185.00 | $210.00 | $261.75 | $12,845 |
| 506-7001 ROCK FILTER DAMS (INSTALL) (TY 1) | 502 LF | $40.00 | $60.00 | $37.24 | $10,040 |
| 400-7010 CEM STABIL BKFL | 87 CY | $200.00 | $86.00 | $138.14 | -$9,918 |
| 420-7038 CL C CONC (COLUMN) | 17.5 CY | $1,500.00 | $990.00 | $1,548.37 | -$8,925 |
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 144.6 CY | $170.00 | $230.00 | $111.76 | $8,676 |
Positive: the low bidder was cheaper on that item. These 20 items account for $181,206 of the $8,716 gap.
TEXAS STEEL INDUSTRIAL PLACING, LLC: unbalanced items
Placed 1R CONSTRUCTION CIVIL, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $19,000.00 | $9,253.78 | 2.05x | $19,492 |
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 144.6 CY | $230.00 | $111.76 | 2.06x | $17,098 |
| 316-7016 ASPH (RC-250) | 1,855 GAL | $14.00 | $5.28 | 2.65x | $16,182 |
| 168-7001 VEGETATIVE WATERING | 61 TGL | $260.00 | $8.43 | 30.83x | $15,346 |
| 500-7001 MOBILIZATION | 1 LS | $23,000.00 | $523,850.32 | 0.04x | -$500,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $800.00 | $11,585.04 | 0.07x | -$150,991 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $35,000.00 | $136,676.66 | 0.26x | -$101,677 |
| 420-7012 CL C CONC (ABUT) | 66.1 CY | $620.00 | $1,307.98 | 0.47x | -$45,475 |
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $1,875.26 | $11,585.04 | 0.16x | -$135,937 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $56,877.97 | $136,676.66 | 0.42x | -$79,799 |
| 100-7002 PREPARING ROW | 8 STA | $2,181.15 | $6,072.92 | 0.36x | -$31,134 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $2,083.48 | $9,253.78 | 0.23x | -$14,341 |
STX CIVIL: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $220,000.00 | $523,850.32 | 0.42x | -$303,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $1,100.00 | $11,585.04 | 0.09x | -$146,791 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $27,500.00 | $136,676.66 | 0.20x | -$109,177 |
| 100-7002 PREPARING ROW | 8 STA | $1,500.00 | $6,072.92 | 0.25x | -$36,583 |