0542-01, US59 OV
0542-01-100 · let Jan 6, 2026 · Webb, Laredo · Overlay
$16,415,512Low bid: ANDERSON COLUMBIA CO., INC.-20.4% vs estimate $20,635,134
$283,953Left on the table1.7% gap to the second bid
4BiddersSpread 9% low to high
206Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ANDERSON COLUMBIA CO., INC. | $16,415,512 | -20.4% | $283,953 | 0 | 1-$94,435 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $16,699,465 | +1.7% | -19.1% | $721,889 | 0 | 2-$491,219 |
| 3 | HUNTER INDUSTRIES, LTD. | $17,421,355 | +6.1% | -15.6% | $437,757 | 2+$798,661 | 0 |
| 4 | CK NEWBERRY, LLC | $17,859,111 | +8.8% | -13.5% | 1+$976,150 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
ANDERSON COLUMBIA CO., INC. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 341-7031 D-GR HMA TY-C SAC-A PG76-22 | 43,630 TON | $111.00 | $123.50 | $122.50 | $545,375 |
| 347-7001 TOM-C PG76-22 SAC-A | 5,391 TON | $111.00 | $161.00 | $169.86 | $269,550 |
| 3007-7001 BONDING COURSE | 122,641 GAL | $2.00 | $0.0500 | $3.32 | -$239,150 |
| 500-7001 MOBILIZATION | 1 LS | $842,000.00 | $643,000.00 | $523,850.32 | -$199,000 |
| 510-7001 ONE-WAY TRAF CONT (FLAGGER CONT) | 4,340 HR | $25.00 | $60.00 | $46.94 | $151,900 |
| 341-7051 D-GR HMA TY-D PG70-22 (LEVEL-UP) | 16,647 TON | $100.00 | $107.00 | $120.73 | $116,529 |
| 351-7004 FLEXIBLE PAVEMENT STRUCTURE REPAIR(5") | 66,681 SY | $36.00 | $34.40 | $35.89 | -$106,690 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $18,000.00 | $6,000.00 | $9,253.78 | -$48,000 |
| 505-7001 TMA (STATIONARY) | 217 DAY | $300.00 | $100.00 | $217.57 | -$43,400 |
| 346-7001 STONE-MTRX-ASPH SMA-C SAC-A PG76-22 | 19,335 TON | $144.00 | $142.00 | $156.93 | -$38,670 |
| 354-7032 PLANE ASPH CONC PAV(0" TO 2") | 4,718 SY | $8.00 | $2.00 | $2.13 | -$28,308 |
| 351-7031 FLEXIBLE PAVEMENT STRUCTURE REPAIR 2.5" | 5,490 SY | $24.00 | $20.30 | $26.93 | -$20,313 |
| 134-7001 BACKFILL (TY A) | 634 STA | $194.00 | $175.00 | $224.26 | -$12,046 |
| 505-7002 TMA (MOBILE OPERATION) | 475 HR | $75.00 | $50.00 | $64.00 | -$11,875 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 235,684 LF | $0.5600 | $0.5200 | $0.4757 | -$9,427 |
| 354-7050 PLANE ASPH CONC PAV(1") | 2,590 SY | $4.30 | $1.90 | $1.11 | -$6,216 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 152,894 LF | $0.5700 | $0.5300 | $0.4986 | -$6,116 |
| 668-7051 PREFAB PM TY B (Y)(6")(SLD) | 5,500 LF | $11.00 | $10.00 | $9.10 | -$5,500 |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE) | 135,820 LF | $0.1200 | $0.1600 | $0.2394 | $5,433 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 13,443 EA | $2.00 | $1.60 | $0.5715 | -$5,377 |
Positive: the low bidder was cheaper on that item. These 20 items account for $308,699 of the $283,953 gap.
ANDERSON COLUMBIA CO., INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 MO | $3,000.00 | $11,585.04 | 0.26x | -$94,435 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 2HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 3CK NEWBERRY, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,500,000.00 | $523,850.32 | 2.86x | $976,150 |