BS 6 NB AT SH 6 SB - BR
0050-11-027 · let Jan 6, 2026 · Grimes, Bryan · Bridge Maintenance
$2,838,056Low bid: GIBSON & ASSOCIATES, INC.+9.2% vs estimate $2,599,474
$206,850Left on the table7.3% gap to the second bid
8BiddersSpread 65% low to high
140Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | GIBSON & ASSOCIATES, INC. | $2,838,056 | 9.2% | $206,850 | 6+$264,170 | 3-$409,898 | |
| 2 | GARRET SHIELDS INFRASTRUCTURE | $3,044,907 | +7.3% | 17.1% | $110,089 | 3+$245,882 | 3-$385,276 |
| 3 | RAGLE CONSTRUCTION, INC. | $3,154,996 | +11.2% | 21.4% | $100,291 | 3+$251,145 | 2-$101,748 |
| 4 | STRUCTURAL INTEGRITY GROUP LLC | $3,255,287 | +14.7% | 25.2% | $171,208 | 6+$376,710 | 0 |
| 5 | MB WESTERN INDUSTRIAL CONTRACTING CO. | $3,426,495 | +20.7% | 31.8% | $795,416 | 12+$1,736,930 | 3-$1,154,758 |
| 6 | SOUTHERN ROAD & BRIDGE, LLC | $4,221,911 | +48.8% | 62.4% | $337,956 | ||
| 7 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $4,559,867 | +60.7% | 75.4% | $122,564 | ||
| 8 | BRAZOS PAVING, INC. | $4,682,431 | +65.0% | 80.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
GIBSON & ASSOCIATES, INC. vs GARRET SHIELDS INFRASTRUCTURE, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 1,165 SF | $20.00 | $150.00 | $85.28 | $151,450 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $19,400.00 | $5,000.00 | $11,585.04 | -$100,800 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 553 SF | $50.00 | $200.00 | $153.06 | $82,950 |
| 446-7001 CLEAN & PAINT EXIST STR (SYSTEM I) | 1 LS | $194,700.00 | $250,000.00 | $143,890.53 | $55,300 |
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 1,646 TON | $187.00 | $220.00 | $137.95 | $54,318 |
| 439-7015 POLYESTER POLYMER CONC OVERLAY (3/4") | 8,813 SY | $109.00 | $115.00 | $106.74 | $52,878 |
| 506-7021 CONSTRUCTION EXITS (INSTALL) (TY 2) | 468 SY | $113.19 | $10.00 | $26.75 | -$48,293 |
| 500-7001 MOBILIZATION | 1 LS | $247,000.00 | $200,000.00 | $523,850.32 | -$47,000 |
| 506-7024 CONSTRUCTION EXITS (REMOVE) | 468 SY | $60.50 | $1.00 | $8.93 | -$27,846 |
| 4010-7013 STEEL BRIDGE ZONE PAINTING | 1 LS | $249,700.00 | $275,000.00 | $126,860.25 | $25,300 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 365 SF | $1.00 | $60.00 | $28.47 | $21,535 |
| 354-7036 PLANE ASPH CONC PAV(0" TO 8") | 8,384 SY | $9.90 | $8.00 | $4.62 | -$15,930 |
| 104-7016 REMOV CONC (CURB) | 589 LF | $35.00 | $10.00 | $6.82 | -$14,725 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 197 DAY | $74.00 | $10.00 | $87.82 | -$12,608 |
| 451-7024 RETROFIT RAIL (TY SSTR) | 698 LF | $162.00 | $180.00 | $175.01 | $12,564 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 6,126 LF | $1.05 | $2.50 | $0.4757 | $8,883 |
| 316-7245 AGGR (TY-PB OR PL, GR-4)(SAC-B) | 12 CY | $990.00 | $320.00 | $165.18 | -$8,040 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 2,602 LF | $7.87 | $5.00 | $3.92 | -$7,468 |
| 506-7041 TEMP SEDMT CONT FENCE (REMOVE) | 2,602 LF | $3.85 | $1.00 | $1.02 | -$7,416 |
| 666-7172 RE PM TY II (W) 6" (BRK) | 520 LF | $1.10 | $15.00 | $0.2347 | $7,228 |
Positive: the low bidder was cheaper on that item. These 20 items account for $182,281 of the $206,850 gap.
GIBSON & ASSOCIATES, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 4010-7013 STEEL BRIDGE ZONE PAINTING | 1 LS | $249,700.00 | $126,860.25 | 1.97x | $122,840 |
| 354-7036 PLANE ASPH CONC PAV(0" TO 8") | 8,384 SY | $9.90 | $4.62 | 2.14x | $44,288 |
| 506-7021 CONSTRUCTION EXITS (INSTALL) (TY 2) | 468 SY | $113.19 | $26.75 | 4.23x | $40,454 |
| 506-7024 CONSTRUCTION EXITS (REMOVE) | 468 SY | $60.50 | $8.93 | 6.78x | $24,136 |
| 104-7016 REMOV CONC (CURB) | 589 LF | $35.00 | $6.82 | 5.14x | $16,601 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 928 LF | $33.00 | $15.92 | 2.07x | $15,853 |
| 500-7001 MOBILIZATION | 1 LS | $247,000.00 | $523,850.32 | 0.47x | -$276,850 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 1,165 SF | $20.00 | $85.28 | 0.23x | -$76,056 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 553 SF | $50.00 | $153.06 | 0.33x | -$56,992 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 4010-7013 STEEL BRIDGE ZONE PAINTING | 1 LS | $275,000.00 | $126,860.25 | 2.17x | $148,140 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 1,165 SF | $150.00 | $85.28 | 1.76x | $75,394 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 928 LF | $40.00 | $15.92 | 2.51x | $22,349 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $5,000.00 | $11,585.04 | 0.43x | -$46,095 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 197 DAY | $10.00 | $87.82 | 0.11x | -$15,330 |
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 446-7001 CLEAN & PAINT EXIST STR (SYSTEM I) | 1 LS | $325,000.00 | $143,890.53 | 2.26x | $181,109 |
| 100-7002 PREPARING ROW | 1 STA | $50,000.00 | $6,072.92 | 8.23x | $43,927 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 365 SF | $100.00 | $28.47 | 3.51x | $26,108 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 1,165 SF | $35.00 | $85.28 | 0.41x | -$58,581 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 553 SF | $75.00 | $153.06 | 0.49x | -$43,167 |
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 4010-7013 STEEL BRIDGE ZONE PAINTING | 1 LS | $247,680.00 | $126,860.25 | 1.95x | $120,820 |
| 446-7001 CLEAN & PAINT EXIST STR (SYSTEM I) | 1 LS | $261,120.00 | $143,890.53 | 1.81x | $117,229 |
| 354-7036 PLANE ASPH CONC PAV(0" TO 8") | 8,384 SY | $12.75 | $4.62 | 2.76x | $68,182 |
| 100-7002 PREPARING ROW | 1 STA | $32,750.00 | $6,072.92 | 5.39x | $26,677 |
| 354-7076 PLANE ASPH CONC PAV (1" TO 2") | 2,772 SY | $10.50 | $1.92 | 5.47x | $23,782 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 30 SF | $818.00 | $150.68 | 5.43x | $20,020 |
MB WESTERN INDUSTRIAL CONTRACTING CO.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 1,165 SF | $350.00 | $85.28 | 4.10x | $308,394 |
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 1,646 TON | $322.00 | $137.95 | 2.33x | $302,953 |
| 4010-7013 STEEL BRIDGE ZONE PAINTING | 1 LS | $354,350.00 | $126,860.25 | 2.79x | $227,490 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 553 SF | $550.00 | $153.06 | 3.59x | $219,508 |
| 446-7001 CLEAN & PAINT EXIST STR (SYSTEM I) | 1 LS | $338,500.00 | $143,890.53 | 2.35x | $194,609 |
| 100-7002 PREPARING ROW | 1 STA | $125,000.00 | $6,072.92 | 20.58x | $118,927 |
| 354-7036 PLANE ASPH CONC PAV(0" TO 8") | 8,384 SY | $18.00 | $4.62 | 3.90x | $112,198 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 365 SF | $286.00 | $28.47 | 10.05x | $93,998 |
| 784-7024 REP STL BRIDGE MEMBER(REPL RIVET/BOLT) | 18 EA | $3,500.00 | $305.16 | 11.47x | $57,507 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 197 DAY | $300.00 | $87.82 | 3.42x | $41,800 |
| 439-7015 POLYESTER POLYMER CONC OVERLAY (3/4") | 8,813 SY | $14.00 | $106.74 | 0.13x | -$817,312 |
| 500-7001 MOBILIZATION | 1 LS | $250,000.00 | $523,850.32 | 0.48x | -$273,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $2,500.00 | $11,585.04 | 0.22x | -$63,595 |