SH 37, CR 2460-CR 2302
0190-03-089 · let Jan 6, 2026 · Wood, Tyler · Safety Improvement Projects
$4,058,410Low bid: BAKER & COMPANY CONSTRUCTION, LLC-1.0% vs estimate $4,100,162
$440,588Left on the table10.9% gap to the second bid
8BiddersSpread 67% low to high
90Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BAKER & COMPANY CONSTRUCTION, LLC | $4,058,410 | -1.0% | $440,588 | 3+$169,287 | 5-$779,262 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $4,498,998 | +10.9% | 9.7% | $17,187 | 3+$272,637 | 4-$654,935 |
| 3 | LONGVIEW BRIDGE AND ROAD, LTD. | $4,516,185 | +11.3% | 10.1% | $82,822 | 0 | 2-$230,715 |
| 4 | DRAKE COMPANIES LLC | $4,599,007 | +13.3% | 12.2% | $134,390 | 4+$193,009 | 2-$280,418 |
| 5 | ROMAN EMPERORS ROAD, LLC | $4,733,397 | +16.6% | 15.4% | $25,177 | 4+$426,892 | 1-$107,552 |
| 6 | EAST TEXAS BRIDGE, INC. | $4,758,574 | +17.3% | 16.1% | $245,987 | ||
| 7 | CDM HOLDINGS | $5,004,561 | +23.3% | 22.1% | $1,757,755 | ||
| 8 | HIGHWAY 19 CONSTRUCTION LLC | $6,762,316 | +66.6% | 64.9% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
BAKER & COMPANY CONSTRUCTION, LLC vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 132-7005 EMBANK (FNL)(OC)(TY C) | 9,863 CY | $5.40 | $28.95 | $18.71 | $232,274 |
| 110-7001 EXCAV (ROADWAY) | 9,325 CY | $5.75 | $27.26 | $11.68 | $200,581 |
| 348-7002 TBPFC-C PG76-22 SAC-A | 3,492 TON | $225.00 | $247.74 | $206.53 | $79,408 |
| 344-7001 SP MIXES SP-B PG64-22 | 6,262 TON | $157.00 | $148.35 | $124.45 | -$54,166 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 51,521 SY | $1.50 | $2.53 | $1.43 | $53,067 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $4,470.00 | $1,023.19 | $11,585.04 | -$48,255 |
| 464-7005 RC PIPE (CL III)(24 IN) | 984 LF | $70.00 | $109.14 | $108.34 | $38,514 |
| 505-7001 TMA (STATIONARY) | 225 DAY | $363.00 | $198.63 | $217.57 | -$36,983 |
| 506-7002 ROCK FILTER DAMS (INSTALL) (TY 2) | 180 LF | $227.00 | $44.95 | $44.91 | -$32,769 |
| 530-7007 DRIVEWAYS (CONC) (HES) | 292 SY | $275.00 | $169.06 | $122.10 | -$30,934 |
| 464-7003 RC PIPE (CL III)(18 IN) | 940 LF | $52.00 | $80.25 | $83.08 | $26,555 |
| 500-7001 MOBILIZATION | 1 LS | $190,000.00 | $215,261.36 | $523,850.32 | $25,261 |
| 275-7005 CEMENT TRT (EXIST MATL)(12") | 14,520 SY | $9.00 | $7.54 | $2.67 | -$21,199 |
| 164-7076 BOND FBR MTRX SEED (PERM)(RURAL)(SAND) | 51,521 SY | $0.9000 | $0.5700 | $0.5910 | -$17,002 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 46 CY | $655.00 | $1,016.50 | $616.83 | $16,629 |
| 432-7001 RIPRAP (CONC)(4 IN) | 177 CY | $850.00 | $760.77 | $573.24 | -$15,794 |
| 310-7010 PRIME COAT & BLOTTER (MC-30) | 1,452 GAL | $7.65 | $17.97 | $6.16 | $14,985 |
| 403-7001 TEMPORARY SPL SHORING | 528 SF | $27.00 | $52.43 | $25.56 | $13,427 |
| 344-7012 SP MIXES SP-C PG64-22 (LEVEL-UP) | 1,031 TON | $158.00 | $170.42 | $134.06 | $12,805 |
| 348-7001 TBPFC (MEMBRANE) | 9,313 GAL | $5.10 | $3.75 | $4.22 | -$12,573 |
Positive: the low bidder was cheaper on that item. These 20 items account for $443,829 of the $440,588 gap.
BAKER & COMPANY CONSTRUCTION, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 275-7005 CEMENT TRT (EXIST MATL)(12") | 14,520 SY | $9.00 | $2.67 | 3.37x | $91,864 |
| 530-7007 DRIVEWAYS (CONC) (HES) | 292 SY | $275.00 | $122.10 | 2.25x | $44,647 |
| 506-7002 ROCK FILTER DAMS (INSTALL) (TY 2) | 180 LF | $227.00 | $44.91 | 5.05x | $32,776 |
| 500-7001 MOBILIZATION | 1 LS | $190,000.00 | $523,850.32 | 0.36x | -$333,850 |
| 100-7002 PREPARING ROW | 35 STA | $1,525.00 | $6,072.92 | 0.25x | -$159,177 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 9,863 CY | $5.40 | $18.71 | 0.29x | -$131,306 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $4,470.00 | $11,585.04 | 0.39x | -$99,611 |
| 110-7001 EXCAV (ROADWAY) | 9,325 CY | $5.75 | $11.68 | 0.49x | -$55,318 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7001 EXCAV (ROADWAY) | 9,325 CY | $27.26 | $11.68 | 2.33x | $145,263 |
| 275-7005 CEMENT TRT (EXIST MATL)(12") | 14,520 SY | $7.54 | $2.67 | 2.82x | $70,664 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 51,521 SY | $2.53 | $1.43 | 1.77x | $56,709 |
| 500-7001 MOBILIZATION | 1 LS | $215,261.36 | $523,850.32 | 0.41x | -$308,589 |
| 100-7002 PREPARING ROW | 35 STA | $1,255.11 | $6,072.92 | 0.21x | -$168,623 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $1,023.19 | $11,585.04 | 0.09x | -$147,866 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 450 DAY | $21.47 | $87.82 | 0.24x | -$29,856 |
LONGVIEW BRIDGE AND ROAD, LTD.: unbalanced items
Placed 3DRAKE COMPANIES LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 105-7023 RMV (3") TRT/UNTRT BASE & ASPH PAV | 4,365 SY | $22.00 | $3.93 | 5.59x | $78,863 |
| 275-7005 CEMENT TRT (EXIST MATL)(12") | 14,520 SY | $6.00 | $2.67 | 2.24x | $48,304 |
| 403-7001 TEMPORARY SPL SHORING | 528 SF | $100.00 | $25.56 | 3.91x | $39,304 |
| 354-7032 PLANE ASPH CONC PAV(0" TO 2") | 8,645 SY | $5.20 | $2.13 | 2.44x | $26,538 |
| 100-7002 PREPARING ROW | 35 STA | $1,375.00 | $6,072.92 | 0.23x | -$164,427 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $3,300.00 | $11,585.04 | 0.28x | -$115,991 |
ROMAN EMPERORS ROAD, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7001 EXCAV (ROADWAY) | 9,325 CY | $30.00 | $11.68 | 2.57x | $170,813 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 9,863 CY | $35.00 | $18.71 | 1.87x | $160,639 |
| 275-7005 CEMENT TRT (EXIST MATL)(12") | 14,520 SY | $6.00 | $2.67 | 2.24x | $48,304 |
| 168-7001 VEGETATIVE WATERING | 1,134 TGL | $50.00 | $8.43 | 5.93x | $47,136 |
| 100-7002 PREPARING ROW | 35 STA | $3,000.00 | $6,072.92 | 0.49x | -$107,552 |