CR 234 (C Meyer Rd) at Bee Creek
0912-34-213 · let Feb 5, 2026 · Fort Bend, Houston · Bridge Replacement
$1,818,854Low bid: TREVWAY, INC.-26.7% vs estimate $2,482,945
$209,601Left on the table11.5% gap to the second bid
9BiddersSpread 47% low to high
144Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TREVWAY, INC. | $1,818,854 | -26.7% | $209,601 | 3+$107,787 | 8-$795,801 | |
| 2 | JFO SERVICES, LLC | $2,028,455 | +11.5% | -18.3% | $68,475 | 4+$176,650 | 5-$537,132 |
| 3 | R CONSTRUCTION CIVIL, LLC | $2,096,930 | +15.3% | -15.5% | $213,550 | 5+$247,510 | 4-$720,506 |
| 4 | CASTILLO ARANDA LLC | $2,310,480 | +27.0% | -6.9% | $10,199 | 3+$122,603 | 2-$496,871 |
| 5 | SKYLINE BRIDGE LLC | $2,320,680 | +27.6% | -6.5% | $16,549 | 5+$233,945 | 4-$488,879 |
| 6 | MC2 CIVIL, LLC | $2,337,229 | +28.5% | -5.9% | $41,031 | ||
| 7 | TALBERT COMPANIES LLC | $2,378,260 | +30.8% | -4.2% | $179,237 | ||
| 8 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $2,557,497 | +40.6% | 3.0% | $108,138 | ||
| 9 | STX CIVIL | $2,665,634 | +46.6% | 7.4% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
TREVWAY, INC. vs JFO SERVICES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 422-7001 REINF CONC SLAB | 4,264 SF | $22.49 | $51.26 | $24.45 | $122,675 |
| 292-7006 ASPHALT TRT BASE (GR 2)(PG 64) | 1,334 TON | $189.47 | $125.58 | $154.72 | -$85,229 |
| 420-7012 CL C CONC (ABUT) | 119 CY | $510.69 | $1,070.82 | $1,307.98 | $66,655 |
| 450-7008 RAIL (TY T223) | 456.7 LF | $98.99 | $197.50 | $141.07 | $44,990 |
| 400-7010 CEM STABIL BKFL | 340 CY | $148.76 | $44.62 | $138.14 | -$35,408 |
| 403-7001 TEMPORARY SPL SHORING | 266 SF | $1.00 | $111.26 | $25.56 | $29,329 |
| 341-7050 D-GR HMA TY-D SAC-B PG70-22 | 485 TON | $233.68 | $180.55 | $116.75 | -$25,768 |
| 100-7002 PREPARING ROW | 11.6 STA | $500.00 | $2,288.60 | $6,072.92 | $20,748 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 58.5 CY | $303.00 | $643.14 | $616.83 | $19,898 |
| 506-7003 ROCK FILTER DAMS (INSTALL) (TY 3) | 228 LF | $5.00 | $77.88 | $71.34 | $16,617 |
| 500-7001 MOBILIZATION | 1 LS | $180,000.00 | $194,986.77 | $523,850.32 | $14,987 |
| 416-7006 DRILL SHAFT (36 IN) | 536 LF | $360.10 | $334.97 | $280.58 | -$13,470 |
| 105-7052 RMV (0"-12") TRT/UNTRT BASE & ASPH PAV | 2,655 SY | $6.31 | $10.73 | $7.43 | $11,735 |
| 432-7002 RIPRAP (CONC)(5 IN) | 447 CY | $287.00 | $311.09 | $585.15 | $10,768 |
| 454-7004 SEALED EXPANSION JOINT (4 IN) (SEJ - M) | 126 LF | $180.00 | $265.01 | $221.89 | $10,711 |
| 422-7013 APPROACH SLAB | 53.4 CY | $400.00 | $591.44 | $738.51 | $10,223 |
| 110-7001 EXCAV (ROADWAY) | 2,574 CY | $8.00 | $4.54 | $11.68 | -$8,906 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 12 EA | $2,986.53 | $3,626.90 | $3,190.07 | $7,684 |
| 425-7001 PRESTR CONC GIRDER (TX28) | 435.65 LF | $266.69 | $283.16 | $217.69 | $7,175 |
| 168-7001 VEGETATIVE WATERING | 199 TGL | $7.73 | $43.19 | $8.43 | $7,057 |
Positive: the low bidder was cheaper on that item. These 20 items account for $232,472 of the $209,601 gap.
TREVWAY, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7050 D-GR HMA TY-D SAC-B PG70-22 | 485 TON | $233.68 | $116.75 | 2.00x | $56,711 |
| 260-7007 LIME TRT (EXIST MATL)(8") | 3,031 SY | $14.00 | $4.35 | 3.22x | $29,260 |
| 530-7010 DRIVEWAYS (ACP) | 114 SY | $246.32 | $54.96 | 4.48x | $21,816 |
| 500-7001 MOBILIZATION | 1 LS | $180,000.00 | $523,850.32 | 0.34x | -$343,850 |
| 432-7002 RIPRAP (CONC)(5 IN) | 447 CY | $287.00 | $585.15 | 0.49x | -$133,273 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $1,989.47 | $11,585.04 | 0.17x | -$115,147 |
| 420-7012 CL C CONC (ABUT) | 119 CY | $510.69 | $1,307.98 | 0.39x | -$94,878 |
| 100-7002 PREPARING ROW | 11.6 STA | $500.00 | $6,072.92 | 0.08x | -$64,646 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 58.5 CY | $303.00 | $616.83 | 0.49x | -$18,359 |
| 506-7003 ROCK FILTER DAMS (INSTALL) (TY 3) | 228 LF | $5.00 | $71.34 | 0.07x | -$15,127 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 1,463 CY | $6.00 | $13.19 | 0.45x | -$10,522 |
JFO SERVICES, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 422-7001 REINF CONC SLAB | 4,264 SF | $51.26 | $24.45 | 2.10x | $114,303 |
| 260-7007 LIME TRT (EXIST MATL)(8") | 3,031 SY | $12.51 | $4.35 | 2.88x | $24,744 |
| 403-7001 TEMPORARY SPL SHORING | 266 SF | $111.26 | $25.56 | 4.35x | $22,796 |
| 530-7010 DRIVEWAYS (ACP) | 114 SY | $184.84 | $54.96 | 3.36x | $14,807 |
| 500-7001 MOBILIZATION | 1 LS | $194,986.77 | $523,850.32 | 0.37x | -$328,864 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $2,069.33 | $11,585.04 | 0.18x | -$114,189 |
| 100-7002 PREPARING ROW | 11.6 STA | $2,288.60 | $6,072.92 | 0.38x | -$43,898 |
| 400-7010 CEM STABIL BKFL | 340 CY | $44.62 | $138.14 | 0.32x | -$31,798 |
| 110-7001 EXCAV (ROADWAY) | 2,574 CY | $4.54 | $11.68 | 0.39x | -$18,384 |
R CONSTRUCTION CIVIL, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 416-7006 DRILL SHAFT (36 IN) | 536 LF | $581.00 | $280.58 | 2.07x | $161,025 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 98 DAY | $400.00 | $87.82 | 4.55x | $30,594 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 4,022 SY | $7.00 | $1.43 | 4.90x | $22,405 |
| 403-7001 TEMPORARY SPL SHORING | 266 SF | $91.00 | $25.56 | 3.56x | $17,407 |
| 530-7010 DRIVEWAYS (ACP) | 114 SY | $196.00 | $54.96 | 3.57x | $16,079 |
| 500-7001 MOBILIZATION | 1 LS | $40,000.00 | $523,850.32 | 0.08x | -$483,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $3,600.00 | $11,585.04 | 0.31x | -$95,821 |
| 420-7012 CL C CONC (ABUT) | 119 CY | $580.00 | $1,307.98 | 0.44x | -$86,630 |
| 100-7002 PREPARING ROW | 11.6 STA | $1,400.00 | $6,072.92 | 0.23x | -$54,206 |
CASTILLO ARANDA LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7050 D-GR HMA TY-D SAC-B PG70-22 | 485 TON | $250.00 | $116.75 | 2.14x | $64,626 |
| 105-7052 RMV (0"-12") TRT/UNTRT BASE & ASPH PAV | 2,655 SY | $20.00 | $7.43 | 2.69x | $33,386 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 1,463 CY | $30.00 | $13.19 | 2.27x | $24,590 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $5,500.00 | $11,585.04 | 0.47x | -$73,021 |
SKYLINE BRIDGE LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7050 D-GR HMA TY-D SAC-B PG70-22 | 485 TON | $300.00 | $116.75 | 2.57x | $88,876 |
| 400-7010 CEM STABIL BKFL | 340 CY | $300.00 | $138.14 | 2.17x | $55,031 |
| 260-7007 LIME TRT (EXIST MATL)(8") | 3,031 SY | $20.00 | $4.35 | 4.60x | $47,446 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 1,463 CY | $32.00 | $13.19 | 2.43x | $27,516 |
| 310-7001 PRIME COAT (AE-P) | 758 GAL | $25.00 | $5.11 | 4.89x | $15,075 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $4,000.00 | $11,585.04 | 0.35x | -$91,021 |
| 100-7002 PREPARING ROW | 11.6 STA | $2,800.00 | $6,072.92 | 0.46x | -$37,966 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 2 EA | $10,000.00 | $28,021.15 | 0.36x | -$36,042 |