Set your company to personalize scores

FY27 Crosby/Floyd ROW Mowing

6510-24-001 · let Sep 29, 2026 · Crosby, Lubbock · Routine Maintenance Project - Sealed

$595,302Low bid: KENNETH THOMASON-13.7% vs estimate $689,620
$43,986Left on the table7.4% gap to the second bid
5BiddersSpread 23% low to high
3Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1KENNETH THOMASON $595,302-13.7% $43,986 0 0
2TEXAS BLACKTOPS LLC $639,288+7.4%-7.3% $49,046 0 0
3K2 PRIME LLC $688,334+15.6%-0.2% $1,329 2+$15,760 0
4BOEN LANDSCAPING & IRRIGATION, LLC $689,663+15.9%0.0% $43,192 0 0
5ABESCAPE LANDSCAPING, LLC $732,855+23.1%6.3% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

KENNETH THOMASON vs TEXAS BLACKTOPS LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
730-7022 FULL - WIDTH MOWING19,372 AC $30.73$33.00$38.53 $43,974
505-7003 TMA (MOBILE OPERATION)8 DAY $0.0010$1.00$229.60 $8
500-7002 MOBILIZATION (CALLOUT)4 EA $0.0010$1.00$600.85 $4

Positive: the low bidder was cheaper on that item. These 3 items account for $43,986 of the $43,986 gap.

K2 PRIME LLC: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
505-7003 TMA (MOBILE OPERATION)8 DAY $1,250.00$229.605.44x$8,163
500-7002 MOBILIZATION (CALLOUT)4 EA $2,500.00$600.854.16x$7,597