AAO Modified 5 Aggregate
6507-60-001 · let Oct 14, 2026 · Brewster, El Paso · Material Maintenance Project
$82,235Low bid: GREEN DREAM INTERNATIONAL LLC-18.6% vs estimate $101,000
$2,437Left on the table3.0% gap to the second bid
3BiddersSpread 73% low to high
11Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | GREEN DREAM INTERNATIONAL LLC | $82,235 | -18.6% | $2,437 | 0 | 0 | |
| 2 | DIGG COMMERCIAL, LLC | $84,672 | +3.0% | -16.2% | $57,528 | 0 | 0 |
| 3 | JOBE MATERIALS, L.P. | $142,200 | +72.9% | 40.8% | 4+$29,578 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
GREEN DREAM INTERNATIONAL LLC vs DIGG COMMERCIAL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8000-7103 AGGR (TY B GR 4) (DEL) (ST5) | 100 TON | $86.56 | $93.03 | $78.65 | $647 |
| 8000-7117 AGGR (TY B GR 5) (DEL) (ST5) | 100 TON | $84.26 | $90.67 | $59.68 | $641 |
| 8000-7102 AGGR (TY B GR 4) (DEL) (ST4) | 100 TON | $75.07 | $78.41 | $75.77 | $334 |
| 8000-7116 AGGR (TY B GR 5) (DEL) (ST4) | 100 TON | $72.77 | $76.05 | $70.12 | $328 |
| 8032-7651 GRADE 5 AGGREGATE (DEL)(SITE 4) | 100 TON | $72.77 | $76.05 | $76.03 | $328 |
| 8032-7648 GRADE 5 AGGREGATE (DEL)(SITE 1) | 200 TON | $64.72 | $65.81 | $61.62 | $218 |
| 8000-7113 AGGR (TY B GR 5) (DEL) (ST1) | 100 TON | $64.72 | $65.81 | $67.38 | $109 |
| 8000-7115 AGGR (TY B GR 5) (DEL) (ST3) | 100 TON | $56.90 | $55.86 | $66.22 | -$104 |
| 8032-7650 GRADE 5 AGGREGATE (DEL)(SITE 3) | 100 TON | $56.90 | $55.86 | $61.43 | -$104 |
| 8000-7114 AGGR (TY B GR 5) (DEL) (ST2) | 100 TON | $61.48 | $61.68 | $67.10 | $20 |
| 8032-7649 GRADE 5 AGGREGATE (DEL)(SITE 2) | 100 TON | $61.48 | $61.68 | $66.09 | $20 |
Positive: the low bidder was cheaper on that item. These 11 items account for $2,437 of the $2,437 gap.
JOBE MATERIALS, L.P.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 8032-7648 GRADE 5 AGGREGATE (DEL)(SITE 1) | 200 TON | $116.50 | $61.62 | 1.89x | $10,975 |
| 8000-7117 AGGR (TY B GR 5) (DEL) (ST5) | 100 TON | $139.50 | $59.68 | 2.34x | $7,982 |
| 8000-7116 AGGR (TY B GR 5) (DEL) (ST4) | 100 TON | $123.50 | $70.12 | 1.76x | $5,338 |
| 8032-7650 GRADE 5 AGGREGATE (DEL)(SITE 3) | 100 TON | $114.25 | $61.43 | 1.86x | $5,282 |