BPM Denton Underseal FY 27
6485-46-001 · let Oct 14, 2026 · Denton, Dallas · Bridge Preventative Maintenance
$83,076Low bid: GARRET SHIELDS INFRASTRUCTURE+6.1% vs estimate $78,310
$9,571Left on the table11.5% gap to the second bid
6BiddersSpread 69% low to high
9Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | GARRET SHIELDS INFRASTRUCTURE | $83,076 | 6.1% | $9,571 | 0 | 2-$520,435 | |
| 2 | MACIAS SPECIALTY CONTRACTING LLC | $92,647 | +11.5% | 18.3% | $1,769 | 1+$4,474 | 2-$526,435 |
| 3 | ROAD DOCTORS LLC | $94,416 | +13.7% | 20.6% | $14,319 | 1+$5,424 | 3-$525,901 |
| 4 | STRUCTURAL INTEGRITY GROUP LLC | $108,735 | +30.9% | 38.9% | $26,830 | 2+$13,987 | 3-$524,201 |
| 5 | IBCTX, LLC | $135,565 | +63.2% | 73.1% | $4,875 | 3+$37,858 | 2-$517,935 |
| 6 | JACKSON EXCAVATION, LLC | $140,440 | +69.1% | 79.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
GARRET SHIELDS INFRASTRUCTURE vs MACIAS SPECIALTY CONTRACTING LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 143 CY | $200.00 | $295.00 | $190.61 | $13,585 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 MO | $5,000.00 | $1,000.00 | $11,585.04 | -$4,000 |
| 432-7002 RIPRAP (CONC)(5 IN) | 21 CY | $700.00 | $560.00 | $585.15 | -$2,940 |
| 3010-7001 RAIS AND UNDERSEAL CONC SLBS W FOAM SYS | 2,640 LB | $5.00 | $5.80 | $3.83 | $2,112 |
| 104-7006 REMOV CONC (RIPRAP) | 152 SY | $30.00 | $43.75 | $14.32 | $2,090 |
| 500-7001 MOBILIZATION | 1 LS | $10,000.00 | $8,000.00 | $523,850.32 | -$2,000 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 16 DAY | $1.00 | $110.00 | $87.82 | $1,744 |
| 505-7001 TMA (STATIONARY) | 16 DAY | $300.00 | $250.00 | $217.57 | -$800 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 11 SF | $200.00 | $180.00 | $150.68 | -$220 |
Positive: the low bidder was cheaper on that item. These 9 items account for $9,571 of the $9,571 gap.
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 1MACIAS SPECIALTY CONTRACTING LLC: unbalanced items
Placed 2ROAD DOCTORS LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 104-7006 REMOV CONC (RIPRAP) | 152 SY | $50.00 | $14.32 | 3.49x | $5,424 |
| 500-7001 MOBILIZATION | 1 LS | $8,000.00 | $523,850.32 | 0.02x | -$515,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 MO | $5,000.00 | $11,585.04 | 0.43x | -$6,585 |
| 505-7001 TMA (STATIONARY) | 16 DAY | $1.00 | $217.57 | 0.00x | -$3,465 |
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 11 SF | $791.00 | $150.68 | 5.25x | $7,044 |
| 104-7006 REMOV CONC (RIPRAP) | 152 SY | $60.00 | $14.32 | 4.19x | $6,944 |
| 500-7001 MOBILIZATION | 1 LS | $10,700.00 | $523,850.32 | 0.02x | -$513,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 MO | $4,000.00 | $11,585.04 | 0.35x | -$7,585 |
| 505-7001 TMA (STATIONARY) | 16 DAY | $1.00 | $217.57 | 0.00x | -$3,465 |
IBCTX, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 432-7002 RIPRAP (CONC)(5 IN) | 21 CY | $1,500.00 | $585.15 | 2.56x | $19,212 |
| 104-7006 REMOV CONC (RIPRAP) | 152 SY | $90.00 | $14.32 | 6.29x | $11,504 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 11 SF | $800.00 | $150.68 | 5.31x | $7,143 |
| 500-7001 MOBILIZATION | 1 LS | $13,500.00 | $523,850.32 | 0.03x | -$510,350 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 MO | $4,000.00 | $11,585.04 | 0.35x | -$7,585 |