SH204,RUSKC/CHEROKEEC/L,WDN
0450-02-014 · let Feb 5, 2026 · Rusk, Tyler · Super-2 Highway
$10,286,588Low bid: PINTO CONSTRUCTION CO., INC.-18.7% vs estimate $12,659,927
$301,318Left on the table2.9% gap to the second bid
8BiddersSpread 24% low to high
219Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | PINTO CONSTRUCTION CO., INC. | $10,286,588 | -18.7% | $301,318 | 3+$246,297 | 4-$283,439 | |
| 2 | BIG CREEK CONSTRUCTION, LTD. | $10,587,906 | +2.9% | -16.4% | $392,232 | 2+$557,548 | 1-$240,381 |
| 3 | A. L. HELMCAMP, INC. | $10,980,138 | +6.7% | -13.3% | $268,267 | 1+$71,194 | 1-$89,731 |
| 4 | MADDEN CONTRACTING COMPANY, LLC. | $11,248,405 | +9.4% | -11.1% | $717,266 | 3+$789,263 | 4-$370,989 |
| 5 | REYNOLDS & KAY, LTD. | $11,965,671 | +16.3% | -5.5% | $149,134 | 6+$1,119,606 | 1-$173,181 |
| 6 | EAST TEXAS BRIDGE, INC. | $12,114,805 | +17.8% | -4.3% | $164,350 | ||
| 7 | DREWERY CONSTRUCTION COMPANY, INCORPORATED | $12,279,155 | +19.4% | -3.0% | $480,435 | ||
| 8 | LONGVIEW BRIDGE AND ROAD, LTD. | $12,759,590 | +24.0% | 0.8% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
PINTO CONSTRUCTION CO., INC. vs BIG CREEK CONSTRUCTION, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $500,000.00 | $1,000,000.00 | $523,850.32 | $500,000 |
| 132-7001 EMBANK (FNL)(OC)(TY A) | 15,897 CY | $18.00 | $30.00 | $22.62 | $190,764 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 28 MO | $9,150.00 | $3,000.00 | $11,585.04 | -$172,200 |
| 100-7001 PREPARING ROW | 61.99 AC | $6,876.60 | $5,000.00 | $3,995.94 | -$116,330 |
| 342-7001 PFC-C PG76-22 SAC-A | 7,405 TON | $157.07 | $170.00 | $170.34 | $95,747 |
| 545-7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) | 4 EA | $29,400.00 | $10,000.00 | $8,780.51 | -$77,600 |
| 403-7001 TEMPORARY SPL SHORING | 7,837 SF | $40.43 | $31.00 | $25.56 | -$73,903 |
| 110-7001 EXCAV (ROADWAY) | 5,314 CY | $15.00 | $27.00 | $11.68 | $63,768 |
| 275-7003 CEMENT TRT (EXIST MATL)(8") | 25,036 SY | $7.50 | $5.00 | $3.04 | -$62,590 |
| 275-7001 CEMENT | 514 TON | $392.00 | $275.00 | $224.93 | -$60,138 |
| 316-7068 ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR) | 36,320 GAL | $5.00 | $3.40 | $5.18 | -$58,112 |
| 260-7001 LIME (COM OR QK)(SLURRY) OR QK(DRY) | 514 TON | $168.00 | $275.00 | $345.77 | $54,998 |
| 316-7258 AGGR (TY-PD OR PL, GR-4) | 748 CY | $231.00 | $165.00 | $194.90 | -$49,368 |
| 344-7077 TACK COAT | 9,235 GAL | $0.0100 | $5.00 | $3.25 | $46,083 |
| 344-7001 SP MIXES SP-B PG64-22 | 23,364 TON | $113.92 | $112.00 | $124.45 | -$44,859 |
| 260-7007 LIME TRT (EXIST MATL)(8") | 25,036 SY | $3.26 | $5.00 | $4.35 | $43,563 |
| 168-7001 VEGETATIVE WATERING | 1,918 TGL | $0.0100 | $20.00 | $8.43 | $38,341 |
| 354-7004 PLANE & TEXT ASPH CONC PAV(0" TO 4") | 25,025 SY | $1.77 | $3.00 | $4.74 | $30,781 |
| 530-7002 INTERSECTIONS (ACP) | 340 SY | $132.71 | $45.00 | $50.74 | -$29,821 |
| 662-7068 WK ZN PAV MRK REMOV (W)6"(SLD) | 72,771 LF | $0.0100 | $0.4000 | $0.8015 | $28,381 |
Positive: the low bidder was cheaper on that item. These 20 items account for $347,503 of the $301,318 gap.
PINTO CONSTRUCTION CO., INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 275-7003 CEMENT TRT (EXIST MATL)(8") | 25,036 SY | $7.50 | $3.04 | 2.47x | $111,693 |
| 545-7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) | 4 EA | $29,400.00 | $8,780.51 | 3.35x | $82,478 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 810 LF | $105.00 | $40.65 | 2.58x | $52,125 |
| 260-7001 LIME (COM OR QK)(SLURRY) OR QK(DRY) | 514 TON | $168.00 | $345.77 | 0.49x | -$91,373 |
| 354-7004 PLANE & TEXT ASPH CONC PAV(0" TO 4") | 25,025 SY | $1.77 | $4.74 | 0.37x | -$74,279 |
| 662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD) | 72,771 LF | $0.0100 | $0.8371 | 0.01x | -$60,189 |
| 662-7068 WK ZN PAV MRK REMOV (W)6"(SLD) | 72,771 LF | $0.0100 | $0.8015 | 0.01x | -$57,598 |
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 2A. L. HELMCAMP, INC.: unbalanced items
Placed 3MADDEN CONTRACTING COMPANY, LLC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,100,000.00 | $523,850.32 | 2.10x | $576,150 |
| 275-7003 CEMENT TRT (EXIST MATL)(8") | 25,036 SY | $8.68 | $3.04 | 2.86x | $141,236 |
| 545-7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) | 4 EA | $26,750.00 | $8,780.51 | 3.05x | $71,878 |
| 132-7001 EMBANK (FNL)(OC)(TY A) | 15,897 CY | $11.00 | $22.62 | 0.49x | -$184,679 |
| 354-7004 PLANE & TEXT ASPH CONC PAV(0" TO 4") | 25,025 SY | $2.00 | $4.74 | 0.42x | -$68,523 |
| 662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD) | 72,771 LF | $0.0100 | $0.8371 | 0.01x | -$60,189 |
| 662-7068 WK ZN PAV MRK REMOV (W)6"(SLD) | 72,771 LF | $0.0100 | $0.8015 | 0.01x | -$57,598 |
REYNOLDS & KAY, LTD.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,000,000.00 | $523,850.32 | 1.91x | $476,150 |
| 403-7001 TEMPORARY SPL SHORING | 7,837 SF | $62.50 | $25.56 | 2.45x | $289,494 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 87,177 SY | $3.00 | $1.43 | 2.10x | $136,929 |
| 545-7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) | 4 EA | $30,000.00 | $8,780.51 | 3.42x | $84,878 |
| 275-7003 CEMENT TRT (EXIST MATL)(8") | 25,036 SY | $5.75 | $3.04 | 1.89x | $67,880 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 810 LF | $120.00 | $40.65 | 2.95x | $64,275 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 28 MO | $5,400.00 | $11,585.04 | 0.47x | -$173,181 |