FM 3405 from Ronald Reagan to GT Heights
1755-03-010 · let Feb 5, 2026 · Williamson, Austin · Safety Improvement Projects
$2,760,448Low bid: AARON CONCRETE CONTRACTORS, LLC-10.7% vs estimate $3,092,708
$43,146Left on the table1.6% gap to the second bid
9BiddersSpread 26% low to high
266Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | AARON CONCRETE CONTRACTORS, LLC | $2,760,448 | -10.7% | $43,146 | 2+$32,346 | 4-$739,995 | |
| 2 | LONE STAR SITEWORK, LLC | $2,803,594 | +1.6% | -9.3% | $117,092 | 5+$300,880 | 5-$954,946 |
| 3 | DAN WILLIAMS COMPANY | $2,920,687 | +5.8% | -5.6% | $46,499 | 1+$16,931 | 1-$42,344 |
| 4 | TEXAS MATERIALS GROUP, INC. | $2,967,185 | +7.5% | -4.1% | $115,061 | 4+$170,142 | 5-$797,213 |
| 5 | POSILLICO CIVIL, INC. | $3,082,246 | +11.7% | -0.3% | $200,276 | 5+$118,728 | 4-$425,125 |
| 6 | GARRET SHIELDS INFRASTRUCTURE | $3,282,522 | +18.9% | 6.1% | $4,873 | ||
| 7 | PATIN CONSTRUCTION LLC | $3,287,395 | +19.1% | 6.3% | $191,264 | ||
| 8 | HUNTER INDUSTRIES, LTD. | $3,478,659 | +26.0% | 12.5% | $8,816 | ||
| 9 | CHASCO CONSTRUCTORS | $3,487,475 | +26.3% | 12.8% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
AARON CONCRETE CONTRACTORS, LLC vs LONE STAR SITEWORK, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 132-7003 EMBANK (FNL)(OC)(TY B) | 7,509 CY | $9.00 | $29.50 | $16.96 | $153,935 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 25,832 SY | $1.00 | $6.25 | $1.43 | $135,618 |
| 500-7001 MOBILIZATION | 1 LS | $193,000.00 | $100,000.00 | $523,850.32 | -$93,000 |
| 100-7002 PREPARING ROW | 63 STA | $1,300.00 | $200.00 | $6,072.92 | -$69,300 |
| 505-7001 TMA (STATIONARY) | 297 DAY | $180.00 | $400.00 | $217.57 | $65,340 |
| 341-7059 D-GR HMA TY-D PG76-22 (LEVEL-UP) | 2,645.4 TON | $118.00 | $100.00 | $115.04 | -$47,617 |
| 168-7001 VEGETATIVE WATERING | 433.98 TGL | $25.00 | $130.00 | $8.43 | $45,568 |
| 347-7002 TOM-C PG76-22 SAC-B | 1,814 TON | $145.00 | $124.00 | $130.62 | -$38,094 |
| 505-7003 TMA (MOBILE OPERATION) | 15 DAY | $860.00 | $3,140.00 | $229.60 | $34,200 |
| 466-7192 WINGWALL (PW - 2) (HW=8 FT) | 1 EA | $37,000.00 | $5,800.00 | $33,376.42 | -$31,200 |
| 466-7194 WINGWALL (PW - 2) (HW=10 FT) | 1 EA | $38,000.00 | $7,500.00 | $54,085.10 | -$30,500 |
| 247-7179 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | 5,210 CY | $45.00 | $50.00 | $63.96 | $26,050 |
| 540-7039 TL-3 31" SHORT RADIUS (COMPLETE) | 1 EA | $4,600.00 | $26,250.00 | $13,068.91 | $21,650 |
| 110-7001 EXCAV (ROADWAY) | 9,368 CY | $9.00 | $11.10 | $11.68 | $19,673 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 80 CY | $780.00 | $560.00 | $616.83 | -$17,600 |
| 341-7003 D-GR HMA TY-B PG64-22 (EXEMPT) | 3,441 TON | $92.00 | $87.00 | $127.48 | -$17,205 |
| 464-7040 RC PIPE (ARCH)(CL III)(DES 1) | 287 LF | $170.00 | $112.00 | $201.47 | -$16,646 |
| 467-7129 SET (TY I)(S= 6 FT)(HW= 4 FT)(4:1)(C) | 2 EA | $14,600.00 | $6,300.00 | $10,383.10 | -$16,600 |
| 467-7012 SET (TY I) (30 IN) (4: 1) (C) | 4 EA | $6,800.00 | $2,700.00 | $6,031.77 | -$16,400 |
| 169-7002 SOIL RET BLKT(SL_MOD_CLAY_LONG) | 22,832 SY | $1.90 | $1.45 | $1.49 | -$10,274 |
Positive: the low bidder was cheaper on that item. These 20 items account for $97,597 of the $43,146 gap.
AARON CONCRETE CONTRACTORS, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 134-7001 BACKFILL (TY A) | 10 STA | $2,000.00 | $224.26 | 8.92x | $17,757 |
| 506-7011 ROCK FILTER DAMS (REMOVE) | 620 LF | $36.00 | $12.47 | 2.89x | $14,589 |
| 500-7001 MOBILIZATION | 1 LS | $193,000.00 | $523,850.32 | 0.37x | -$330,850 |
| 100-7002 PREPARING ROW | 63 STA | $1,300.00 | $6,072.92 | 0.21x | -$300,694 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $1,100.00 | $11,585.04 | 0.09x | -$94,365 |
| 105-7008 RMV (8"-12") TRT/UNTRT BASE & ASPH PAV | 2,883 SY | $4.00 | $8.89 | 0.45x | -$14,085 |
LONE STAR SITEWORK, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 160-7002 FURN & PLACE TOPSOIL (4") | 25,832 SY | $6.25 | $1.43 | 4.37x | $124,528 |
| 505-7001 TMA (STATIONARY) | 297 DAY | $400.00 | $217.57 | 1.84x | $54,181 |
| 168-7001 VEGETATIVE WATERING | 433.98 TGL | $130.00 | $8.43 | 15.41x | $52,757 |
| 505-7003 TMA (MOBILE OPERATION) | 15 DAY | $3,140.00 | $229.60 | 13.68x | $43,656 |
| 134-7001 BACKFILL (TY A) | 10 STA | $2,800.00 | $224.26 | 12.49x | $25,757 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 100-7002 PREPARING ROW | 63 STA | $200.00 | $6,072.92 | 0.03x | -$369,994 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $1,925.00 | $11,585.04 | 0.17x | -$86,940 |
| 466-7194 WINGWALL (PW - 2) (HW=10 FT) | 1 EA | $7,500.00 | $54,085.10 | 0.14x | -$46,585 |
| 466-7192 WINGWALL (PW - 2) (HW=8 FT) | 1 EA | $5,800.00 | $33,376.42 | 0.17x | -$27,576 |
DAN WILLIAMS COMPANY: unbalanced items
Placed 3TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 530-7022 INTRSCT, DRVWAYS, & TURNOUT (ACP) | 1,324 SY | $102.00 | $42.62 | 2.39x | $78,618 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 25,832 SY | $3.60 | $1.43 | 2.52x | $56,074 |
| 168-7001 VEGETATIVE WATERING | 433.98 TGL | $50.00 | $8.43 | 5.93x | $18,039 |
| 400-7008 CUT & RESTORE ASPH PAVING | 27 SY | $785.00 | $140.13 | 5.60x | $17,411 |
| 100-7002 PREPARING ROW | 63 STA | $955.00 | $6,072.92 | 0.16x | -$322,429 |
| 500-7001 MOBILIZATION | 1 LS | $203,000.00 | $523,850.32 | 0.39x | -$320,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $873.00 | $11,585.04 | 0.08x | -$96,408 |
| 505-7001 TMA (STATIONARY) | 297 DAY | $93.00 | $217.57 | 0.43x | -$36,998 |
| 467-7012 SET (TY I) (30 IN) (4: 1) (C) | 4 EA | $900.00 | $6,031.77 | 0.15x | -$20,527 |
POSILLICO CIVIL, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 5061-7001 SUBSURFACE UTIL LOCATE (NON-PAVED AREA) | 10 EA | $4,500.00 | $920.62 | 4.89x | $35,794 |
| 464-7005 RC PIPE (CL III)(24 IN) | 200 LF | $250.00 | $108.34 | 2.31x | $28,333 |
| 464-7007 RC PIPE (CL III)(30 IN) | 106 LF | $325.00 | $140.03 | 2.32x | $19,607 |
| 464-7019 RC PIPE (CL IV)(18 IN) | 125 LF | $250.00 | $107.92 | 2.32x | $17,761 |
| 467-7129 SET (TY I)(S= 6 FT)(HW= 4 FT)(4:1)(C) | 2 EA | $19,000.00 | $10,383.10 | 1.83x | $17,234 |
| 500-7001 MOBILIZATION | 1 LS | $250,000.00 | $523,850.32 | 0.48x | -$273,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $800.00 | $11,585.04 | 0.07x | -$97,065 |
| 505-7001 TMA (STATIONARY) | 297 DAY | $100.00 | $217.57 | 0.46x | -$34,919 |
| 169-7002 SOIL RET BLKT(SL_MOD_CLAY_LONG) | 22,832 SY | $0.6500 | $1.49 | 0.43x | -$19,291 |