6509-23-001 Flex Base Refugio Maint
6509-23-001 · let Sep 29, 2026 · Refugio, Corpus Christi · Material Maintenance Project
$350,830Low bid: MARTIN MARIETTA MATERIALS, INC.+17.7% vs estimate $298,000
$14,170Left on the table4.0% gap to the second bid
4BiddersSpread 11% low to high
2Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | MARTIN MARIETTA MATERIALS, INC. | $350,830 | 17.7% | $14,170 | 0 | 0 | |
| 2 | ANDERSON COLUMBIA CO., INC. | $365,000 | +4.0% | 22.5% | $10,000 | 0 | 0 |
| 3 | VULCAN CONSTRUCTION MATERIALS, LLC | $375,000 | +6.9% | 25.8% | $14,040 | 0 | 0 |
| 4 | SOUTHERN SOURCING SOLUTIONS, LLC | $389,040 | +10.9% | 30.6% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
MARTIN MARIETTA MATERIALS, INC. vs ANDERSON COLUMBIA CO., INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8010-7022 FL BS(TY A GR 1-2)(DEL)(ST2) | 5,000 TON | $59.57 | $62.00 | $42.69 | $12,150 |
| 8010-7021 FL BS(TY A GR 1-2)(DEL)(ST1) | 1,000 TON | $52.98 | $55.00 | $39.77 | $2,020 |
Positive: the low bidder was cheaper on that item. These 2 items account for $14,170 of the $14,170 gap.