2027 Seal Coat-US 9O WB(W/FM 1009-EAST)
0028-05-057 · let Sep 3, 2026 · Liberty, Beaumont · Seal Coat
$11,067,539Low bid: SELECT MAINTENANCE, L.L.C.-11.0% vs estimate $12,430,021
$105,108Left on the table0.9% gap to the second bid
6BiddersSpread 30% low to high
396Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SELECT MAINTENANCE, L.L.C. | $11,067,539 | -11.0% | $105,108 | 2+$1,207,974 | 0 | |
| 2 | CLARK CONSTRUCTION OF TEXAS, INC. | $11,172,647 | +0.9% | -10.1% | $263,470 | 2+$1,218,224 | 0 |
| 3 | CK NEWBERRY, LLC | $11,436,118 | +3.3% | -8.0% | $1,051,152 | 2+$818,224 | 0 |
| 4 | HAYDEN PAVING, INC. | $12,487,270 | +12.8% | 0.5% | $859,421 | 1+$1,686,150 | 0 |
| 5 | RONALD R. WAGNER & CO., LP | $13,346,691 | +20.6% | 7.4% | $1,073,974 | 1+$2,106,310 | 0 |
| 6 | FORDE CONSTRUCTION COMPANY, INC. | $14,420,665 | +30.3% | 16.0% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
SELECT MAINTENANCE, L.L.C. vs CLARK CONSTRUCTION OF TEXAS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 316-7241 AGGR (TY-PB OR PL, GR-4)(SAC-A) | 24,997 CY | $185.00 | $196.86 | $180.75 | $296,464 |
| 500-7001 MOBILIZATION | 1 LS | $1,300,000.00 | $1,450,000.00 | $523,850.32 | $150,000 |
| 316-7023 ASPH (AC-20-5TR) | 4,965 TON | $780.00 | $751.00 | $696.11 | -$143,985 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $97,950.00 | $70,000.00 | $11,585.04 | -$139,750 |
| 505-7003 TMA (MOBILE OPERATION) | 102 DAY | $500.00 | $1.00 | $229.60 | -$50,898 |
| 505-7001 TMA (STATIONARY) | 27 DAY | $250.00 | $1.00 | $217.57 | -$6,723 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 6,876 EA | $0.0100 | $0.0100 | $1.03 | $0 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 66,171 EA | $0.0100 | $0.0100 | $0.5715 | $0 |
| 666-7186 RE PM TY II (W) (ARROW) | 281 EA | $45.00 | $45.00 | $86.49 | $0 |
| 666-7187 RE PM TY II (W) (DBL ARROW) | 4 EA | $55.00 | $55.00 | $128.26 | $0 |
| 666-7194 RE PM TY II (W) (WORD) | 70 EA | $55.00 | $55.00 | $104.92 | $0 |
| 666-7198 RE PM TY II (W) (RR XING) | 6 EA | $200.00 | $200.00 | $206.46 | $0 |
| 666-7201 RE PM TY II (W) 36" (YLD TRI) | 205 EA | $15.00 | $15.00 | $28.67 | $0 |
| 668-7136 PREFAB PM TY C (BLUE&WHITE)(EVAC SYM) | 6 EA | $500.00 | $500.00 | $255.12 | $0 |
| 672-7002 REFL PAV MRKR TY I-C | 1,407 EA | $5.00 | $5.00 | $4.04 | $0 |
| 672-7004 REFL PAV MRKR TY II-A-A | 15,460 EA | $5.00 | $5.00 | $3.97 | $0 |
| 672-7006 REFL PAV MRKR TY II-C-R | 169 EA | $5.00 | $5.00 | $4.19 | $0 |
| 666-7172 RE PM TY II (W) 6" (BRK) | 51,190 LF | $0.2500 | $0.2500 | $0.2347 | $0 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 1,149,001 LF | $0.2500 | $0.2500 | $0.1701 | $0 |
| 666-7177 RE PM TY II (W) 8" (DOT) | 1,171 LF | $0.3500 | $0.3500 | $0.5160 | $0 |
Positive: the low bidder was cheaper on that item. These 20 items account for $105,108 of the $105,108 gap.
SELECT MAINTENANCE, L.L.C.: unbalanced items
Placed 1CLARK CONSTRUCTION OF TEXAS, INC.: unbalanced items
Placed 2CK NEWBERRY, LLC: unbalanced items
Placed 3HAYDEN PAVING, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,210,000.00 | $523,850.32 | 4.22x | $1,686,150 |
RONALD R. WAGNER & CO., LP: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,630,159.97 | $523,850.32 | 5.02x | $2,106,310 |