Repair/Replace Conc Barrier Denton FY 27
6503-16-001 · let Oct 14, 2026 · Denton, Dallas · Routine Maintenance Project - Sealed
$166,500Low bid: GARRET SHIELDS INFRASTRUCTURE-13.0% vs estimate $191,275
$33,250Left on the table20.0% gap to the second bid
3BiddersSpread 64% low to high
5Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | GARRET SHIELDS INFRASTRUCTURE | $166,500 | -13.0% | $33,250 | 2+$27,837 | 0 | |
| 2 | IBCTX, LLC | $199,750 | +20.0% | 4.4% | $72,750 | 1+$26,500 | 0 |
| 3 | JACKSON EXCAVATION, LLC | $272,500 | +63.7% | 42.5% | 3+$175,074 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
GARRET SHIELDS INFRASTRUCTURE vs IBCTX, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 429-7008 CONC STR REPR(RAPID VERT AND OVERHEAD) | 500 SF | $200.00 | $275.00 | $198.67 | $37,500 |
| 514-7014 PERM CTB (F-SHAPE) (TY 2) | 100 LF | $200.00 | $375.00 | $110.00 | $17,500 |
| 512-7108 PORT CTB (ALIGNING) | 900 LF | $30.00 | $15.00 | $9.07 | -$13,500 |
| 500-7002 MOBILIZATION (CALLOUT) | 15 EA | $1,000.00 | $600.00 | $600.85 | -$6,000 |
| 505-7001 TMA (STATIONARY) | 15 DAY | $300.00 | $150.00 | $217.57 | -$2,250 |
Positive: the low bidder was cheaper on that item. These 5 items account for $33,250 of the $33,250 gap.
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 1IBCTX, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 514-7014 PERM CTB (F-SHAPE) (TY 2) | 100 LF | $375.00 | $110.00 | 3.41x | $26,500 |