RipRap 07 09.26
6504-32-001 · let Sep 9, 2026 · Collin, Dallas · Material Maintenance Project
$104,965Low bid: DIGG COMMERCIAL, LLC-6.7% vs estimate $112,500
$5,035Left on the table4.8% gap to the second bid
5BiddersSpread 22% low to high
3Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | DIGG COMMERCIAL, LLC | $104,965 | -6.7% | $5,035 | 0 | 0 | |
| 2 | GARRET SHIELDS INFRASTRUCTURE | $110,000 | +4.8% | -2.2% | $2,005 | 0 | 0 |
| 3 | SOUTHERN SOURCING SOLUTIONS, LLC | $112,005 | +6.7% | -0.4% | $580 | 0 | 0 |
| 4 | A. L. HELMCAMP, INC. | $112,585 | +7.3% | 0.1% | $15,715 | 0 | 0 |
| 5 | RK HALL, LLC | $128,300 | +22.2% | 14.0% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
DIGG COMMERCIAL, LLC vs GARRET SHIELDS INFRASTRUCTURE, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8004-7188 RIPRAP(STONE PROT)(8 IN)(DEL)(ST1) | 500 TON | $58.32 | $75.00 | $78.13 | $8,340 |
| 8004-7254 RIPRAP(STN CMN)(DRY)(8"X16")(DEL)(ST1) | 500 TON | $73.91 | $70.00 | $74.64 | -$1,955 |
| 8004-7210 RIPRAP(STONE PROT)(18 IN)(DEL)(ST1) | 500 TON | $77.70 | $75.00 | $81.45 | -$1,350 |
Positive: the low bidder was cheaper on that item. These 3 items account for $5,035 of the $5,035 gap.