Bid Tab X-ray: 6502-06-001

Sep 9, 2026 · Navarro Sign up free
Set your company to personalize scores

Limestone Rock Asphalt 01 0926

6502-06-001 · let Sep 9, 2026 · Navarro, Dallas · Material Maintenance Project

$77,710Low bid: VULCAN CONSTRUCTION MATERIALS, LLC+11.0% vs estimate $70,000
$1,375Left on the table1.8% gap to the second bid
2BiddersSpread 2% low to high
2Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1VULCAN CONSTRUCTION MATERIALS, LLC $77,71011.0% $1,375 0 0
2MARTIN MARIETTA MATERIALS, INC. $79,085+1.8%13.0% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.

Where the job was won

VULCAN CONSTRUCTION MATERIALS, LLC vs MARTIN MARIETTA MATERIALS, INC., biggest item swings
ItemQtyLow2ndMarket2nd minus low
8001-7065 LRA (TY I GR CC) (DEL) (ST1)300 TON $155.82$158.63$117.99 $843
8001-7009 LRA (TY I GR AA) (DEL) (ST1)200 TON $154.82$157.48$112.79 $532

Positive: the low bidder was cheaper on that item. These 2 items account for $1,375 of the $1,375 gap.