Bid Tab X-ray: 6498-18-001

Mar 11, 2026 · Burleson Sign up free
Set your company to personalize scores

FY26 - Burleson Mowing - 03

6498-18-001 · let Mar 11, 2026 · Burleson, Bryan · Routine Maintenance Project

$274,801Low bid: CEDAR HILL SERVICES, LLC+16.0% vs estimate $236,924
$16,102Left on the table5.9% gap to the second bid
4BiddersSpread 18% low to high
5Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1CEDAR HILL SERVICES, LLC $274,80116.0% $16,102 0 1-$20,321
2P-VILLE, INCORPORATED $290,903+5.9%22.8% $31,126 0 1-$20,683
3ABESCAPE GROUP LLC $322,029+17.2%35.9% $3,386 0 0
4SKYLINE CONSTRUCTION PAVING & STRIPING $325,415+18.4%37.3% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.

Where the job was won

CEDAR HILL SERVICES, LLC vs P-VILLE, INCORPORATED, biggest item swings
ItemQtyLow2ndMarket2nd minus low
730-7022 FULL - WIDTH MOWING7,284.3 AC $34.65$36.95$38.53 $16,754
734-7004 LITTER REMOVAL - TRACT (1)804 AC $15.45$15.00$40.72 -$362
734-7006 LITTER REMOVAL - TRACT (3)556.2 AC $15.45$15.00$14.49 -$250
734-7005 LITTER REMOVAL - TRACT (2)89.4 AC $15.45$15.00$14.81 -$40
500-7002 MOBILIZATION (CALLOUT)4 EA $1.00$1.00$600.85 $0

Positive: the low bidder was cheaper on that item. These 5 items account for $16,102 of the $16,102 gap.

CEDAR HILL SERVICES, LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
734-7004 LITTER REMOVAL - TRACT (1)804 AC $15.45$40.720.38x-$20,321

P-VILLE, INCORPORATED: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
734-7004 LITTER REMOVAL - TRACT (1)804 AC $15.00$40.720.37x-$20,683