FY26 - Burleson Mowing - 03
- Let date
- Wednesday, March 11, 2026
- CCSJ
- 6498-18-001
- District
- Bryan
- County
- Burleson
- Highway
- FM0060
- Limits
- Various to Various
- Classification
- Routine Maintenance Project · Maintenance
- Project number
- RMC - A00219938
- Working days
- 365
- DBE goal
- 0%
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $236,924 | ||
| 1 | CEDAR HILL SERVICES, LLC Low bidder | $274,801 | +16.0% | |
| 2 | P-VILLE, INCORPORATED | $290,903 | +22.8% | +5.9% |
| 3 | ABESCAPE GROUP LLC | $322,029 | +35.9% | +17.2% |
| 4 | SKYLINE CONSTRUCTION PAVING & STRIPING | $325,415 | +37.3% | +18.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 CEDAR HILL SERV… | #2 P-VILLE, INCORP… | #3 ABESCAPE GROUP … | #4 SKYLINE CONSTRU… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-7002 | MOBILIZATION (CALLOUT) | 4 | EA | $250.00 | $1.00 | $1.00 | $1.00 | $700.00 |
| 2 | 730-7022 | FULL - WIDTH MOWING | 7,284.3 | AC | $30.00 | $34.65 | $36.95 | $39.83 | $40.11 |
| 3 | 734-7004 | LITTER REMOVAL - TRACT (1) | 804 | AC | $12.00 | $15.45 | $15.00 | $22.00 | $21.00 |
| 4 | 734-7005 | LITTER REMOVAL - TRACT (2) | 89.4 | AC | $12.00 | $15.45 | $15.00 | $22.00 | $21.00 |
| 5 | 734-7006 | LITTER REMOVAL - TRACT (3) | 556.2 | AC | $12.00 | $15.45 | $15.00 | $22.00 | $21.00 |