Katy Trail Phase Two
0901-19-229 · let Mar 5, 2026 · Grayson, Paris · Pedestrian, Sidewalks & Curb Ramps
$2,744,602Low bid: SCOUT 5 CONSTRUCTION LLC-7.5% vs estimate $2,967,039
$19,202Left on the table0.7% gap to the second bid
11BiddersSpread 100% low to high
68Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SCOUT 5 CONSTRUCTION LLC | $2,744,602 | -7.5% | $19,202 | 5+$189,289 | 6-$567,910 | |
| 2 | STX CIVIL | $2,763,804 | +0.7% | -6.8% | $63,207 | 4+$135,286 | 4-$791,579 |
| 3 | TEXAS STEEL INDUSTRIAL PLACING, LLC | $2,827,011 | +3.0% | -4.7% | $50,661 | 4+$230,025 | 2-$393,761 |
| 4 | GARRET SHIELDS INFRASTRUCTURE | $2,877,672 | +4.8% | -3.0% | $19,040 | 5+$323,999 | 4-$761,965 |
| 5 | SKYLINE BRIDGE LLC | $2,896,712 | +5.5% | -2.4% | $68,869 | 4+$544,446 | 4-$753,461 |
| 6 | HIGHWAY 19 CONSTRUCTION LLC | $2,965,581 | +8.1% | 0.0% | $118,445 | ||
| 7 | PACE CONSTRUCTION SERVICES LLC | $3,084,026 | +12.4% | 3.9% | $75,663 | ||
| 8 | TALBERT COMPANIES LLC | $3,159,690 | +15.1% | 6.5% | $40,865 | ||
| 9 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $3,200,555 | +16.6% | 7.9% | $1,083,981 | ||
| 10 | ED BELL CONSTRUCTION COMPANY | $4,284,536 | +56.1% | 44.4% | $1,214,192 | ||
| 11 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | $5,498,727 | +100.3% | 85.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
SCOUT 5 CONSTRUCTION LLC vs STX CIVIL, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 531-7003 CONC SIDEWALKS (6") | 8,977 SY | $44.00 | $90.00 | $88.84 | $412,942 |
| 100-7002 PREPARING ROW | 67.2 STA | $5,000.00 | $350.00 | $6,072.92 | -$312,480 |
| 500-7001 MOBILIZATION | 1 LS | $300,000.00 | $216,000.00 | $523,850.32 | -$84,000 |
| 446-7002 CLEAN & PAINT EXIST STR (SYSTEM II) | 1 LS | $352,000.00 | $280,000.00 | $301,243.48 | -$72,000 |
| 685-7004 INSTL RDSD FLSH BCN ASSM (SOLAR PWRD) | 6 EA | $616.25 | $9,500.00 | $5,710.21 | $53,303 |
| 506-7041 TEMP SEDMT CONT FENCE (REMOVE) | 13,270 LF | $4.00 | $0.1000 | $1.02 | -$51,753 |
| 260-7010 LIME TRT (EXIST MATL & NEW BASE)(6") | 10,562 SY | $3.25 | $8.00 | $4.40 | $50,170 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 13,270 LF | $7.00 | $4.00 | $3.92 | -$39,810 |
| 450-7063 RAIL (HANDRAIL)(TY F) | 1,926 LF | $135.00 | $155.00 | $152.24 | $38,520 |
| 110-7001 EXCAV (ROADWAY) | 2,870 CY | $33.00 | $20.00 | $11.68 | -$37,310 |
| 420-7012 CL C CONC (ABUT) | 36.4 CY | $465.00 | $1,300.00 | $1,307.98 | $30,394 |
| 491-7001 TREAT TIMBER | 10 MBF | $3,500.00 | $500.00 | $4,543.86 | -$30,000 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 19,528 LF | $1.50 | $0.1500 | $0.0662 | -$26,363 |
| 4005-7001 RELOCATE EXISTING TRUSS BRIDGE | 1 LS | $25,000.00 | $50,000.00 | $24,000.00 | $25,000 |
| 666-7346 PAVEMENT SLER 4" | 19,528 LF | $1.50 | $0.2500 | $0.4948 | -$24,410 |
| 132-7001 EMBANK (FNL)(OC)(TY A) | 2,890 CY | $33.00 | $40.00 | $22.62 | $20,230 |
| 4064-7001 SHADE STRUCTURE | 1 EA | $50,000.00 | $30,000.00 | $50,000.00 | -$20,000 |
| 168-7001 VEGETATIVE WATERING | 505 TGL | $11.50 | $50.00 | $8.43 | $19,443 |
| 162-7002 BLOCK SODDING | 14,467 SY | $6.00 | $4.75 | $4.39 | -$18,084 |
| 465-7126 INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT) | 6 EA | $3,042.00 | $6,000.00 | $7,339.80 | $17,748 |
Positive: the low bidder was cheaper on that item. These 20 items account for -$48,461 of the $19,202 gap.
SCOUT 5 CONSTRUCTION LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7001 EXCAV (ROADWAY) | 2,870 CY | $33.00 | $11.68 | 2.82x | $61,182 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 13,270 LF | $7.00 | $3.92 | 1.79x | $40,926 |
| 506-7041 TEMP SEDMT CONT FENCE (REMOVE) | 13,270 LF | $4.00 | $1.02 | 3.92x | $39,553 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 19,528 LF | $1.50 | $0.0662 | 22.66x | $27,999 |
| 666-7346 PAVEMENT SLER 4" | 19,528 LF | $1.50 | $0.4948 | 3.03x | $19,630 |
| 531-7003 CONC SIDEWALKS (6") | 8,977 SY | $44.00 | $88.84 | 0.50x | -$402,544 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1,200.00 | $11,585.04 | 0.10x | -$62,310 |
| 420-7012 CL C CONC (ABUT) | 36.4 CY | $465.00 | $1,307.98 | 0.36x | -$30,684 |
| 685-7004 INSTL RDSD FLSH BCN ASSM (SOLAR PWRD) | 6 EA | $616.25 | $5,710.21 | 0.11x | -$30,564 |
| 465-7126 INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT) | 6 EA | $3,042.00 | $7,339.80 | 0.41x | -$25,787 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $12,000.00 | $28,021.15 | 0.43x | -$16,021 |
STX CIVIL: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7001 EMBANK (FNL)(OC)(TY A) | 2,890 CY | $40.00 | $22.62 | 1.77x | $50,236 |
| 260-7010 LIME TRT (EXIST MATL & NEW BASE)(6") | 10,562 SY | $8.00 | $4.40 | 1.82x | $38,059 |
| 4005-7001 RELOCATE EXISTING TRUSS BRIDGE | 1 LS | $50,000.00 | $24,000.00 | 2.08x | $26,000 |
| 168-7001 VEGETATIVE WATERING | 505 TGL | $50.00 | $8.43 | 5.93x | $20,991 |
| 100-7002 PREPARING ROW | 67.2 STA | $350.00 | $6,072.92 | 0.06x | -$384,580 |
| 500-7001 MOBILIZATION | 1 LS | $216,000.00 | $523,850.32 | 0.41x | -$307,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1,800.00 | $11,585.04 | 0.16x | -$58,710 |
| 491-7001 TREAT TIMBER | 10 MBF | $500.00 | $4,543.86 | 0.11x | -$40,439 |
TEXAS STEEL INDUSTRIAL PLACING, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 4005-7001 RELOCATE EXISTING TRUSS BRIDGE | 1 LS | $150,000.00 | $24,000.00 | 6.25x | $126,000 |
| 260-7010 LIME TRT (EXIST MATL & NEW BASE)(6") | 10,562 SY | $10.00 | $4.40 | 2.27x | $59,183 |
| 110-7001 EXCAV (ROADWAY) | 2,870 CY | $21.00 | $11.68 | 1.80x | $26,742 |
| 434-7002 ELASTOMERIC BEARING (LAMINATED) | 4 EA | $6,400.00 | $1,875.10 | 3.41x | $18,100 |
| 100-7002 PREPARING ROW | 67.2 STA | $1,000.00 | $6,072.92 | 0.16x | -$340,900 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $2,775.00 | $11,585.04 | 0.24x | -$52,860 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 4005-7001 RELOCATE EXISTING TRUSS BRIDGE | 1 LS | $160,000.00 | $24,000.00 | 6.67x | $136,000 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $90,000.00 | $28,021.15 | 3.21x | $61,979 |
| 685-7004 INSTL RDSD FLSH BCN ASSM (SOLAR PWRD) | 6 EA | $14,000.00 | $5,710.21 | 2.45x | $49,739 |
| 110-7001 EXCAV (ROADWAY) | 2,870 CY | $25.00 | $11.68 | 2.14x | $38,222 |
| 260-7010 LIME TRT (EXIST MATL & NEW BASE)(6") | 10,562 SY | $8.00 | $4.40 | 1.82x | $38,059 |
| 100-7002 PREPARING ROW | 67.2 STA | $600.00 | $6,072.92 | 0.10x | -$367,780 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $4,000.00 | $11,585.04 | 0.35x | -$45,510 |
| 784-7024 REP STL BRIDGE MEMBER(REPL RIVET/BOLT) | 121 EA | $100.00 | $305.16 | 0.33x | -$24,824 |
SKYLINE BRIDGE LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 422-7001 REINF CONC SLAB | 2,002 SF | $242.16 | $24.45 | 9.90x | $435,849 |
| 4005-7001 RELOCATE EXISTING TRUSS BRIDGE | 1 LS | $70,000.00 | $24,000.00 | 2.92x | $46,000 |
| 260-7010 LIME TRT (EXIST MATL & NEW BASE)(6") | 10,562 SY | $7.75 | $4.40 | 1.76x | $35,419 |
| 685-7004 INSTL RDSD FLSH BCN ASSM (SOLAR PWRD) | 6 EA | $10,240.00 | $5,710.21 | 1.79x | $27,179 |
| 100-7002 PREPARING ROW | 67.2 STA | $500.00 | $6,072.92 | 0.08x | -$374,500 |
| 500-7001 MOBILIZATION | 1 LS | $225,000.00 | $523,850.32 | 0.43x | -$298,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $2,400.00 | $11,585.04 | 0.21x | -$55,110 |
| 4064-7001 SHADE STRUCTURE | 1 EA | $25,000.00 | $50,000.00 | 0.50x | -$25,000 |