SH 36 Seal Coat: SS 10 to W of UA 90
0187-05-068 · let Sep 3, 2026 · Fort Bend, Houston · Seal Coat
$2,934,889Low bid: CLARK CONSTRUCTION OF TEXAS, INC.+44.7% vs estimate $2,028,830
$29,918Left on the table1.0% gap to the second bid
5BiddersSpread 18% low to high
114Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CLARK CONSTRUCTION OF TEXAS, INC. | $2,934,889 | 44.7% | $29,918 | 1+$96,888 | 0 | |
| 2 | HAYDEN PAVING, INC. | $2,964,808 | +1.0% | 46.1% | $204,313 | 0 | 1-$47,925 |
| 3 | CK NEWBERRY, LLC | $3,169,121 | +8.0% | 56.2% | $158,448 | 0 | 0 |
| 4 | FORDE CONSTRUCTION COMPANY, INC. | $3,327,569 | +13.4% | 64.0% | $125,592 | 1+$571,375 | 2-$471,776 |
| 5 | RONALD R. WAGNER & CO., LP | $3,453,161 | +17.7% | 70.2% | 0 | 1-$57,925 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
CLARK CONSTRUCTION OF TEXAS, INC. vs HAYDEN PAVING, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 316-7007 ASPH (AC-20-5TR) | 263,110 GAL | $3.24 | $2.30 | $3.27 | -$247,323 |
| 316-7211 AGGR (TY-PB, GR-4)(SAC-B) | 5,719 CY | $124.53 | $159.00 | $133.09 | $197,134 |
| 666-7441 RE PROFILE PM TY 1(W)6"(SLD)(125MIL) | 363,811 LF | $0.7500 | $0.9900 | $0.7577 | $87,315 |
| 500-7001 MOBILIZATION | 1 LS | $365,250.00 | $435,000.00 | $523,850.32 | $69,750 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $15,000.00 | $2,000.00 | $11,585.04 | -$65,000 |
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 43,998 LF | $5.00 | $3.65 | $2.80 | -$59,397 |
| 666-7501 RE PROFILE PM TY I(W)6"(SLD)(125MIL) | 199,456 LF | $0.7500 | $0.9900 | $0.7680 | $47,869 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 363,811 LF | $0.2500 | $0.2000 | $0.1701 | -$18,191 |
| 505-7001 TMA (STATIONARY) | 30 DAY | $10.00 | $400.00 | $217.57 | $11,700 |
| 505-7003 TMA (MOBILE OPERATION) | 30 DAY | $10.00 | $400.00 | $229.60 | $11,700 |
| 666-7213 RE PM TY II (Y) 6" (SLD) | 199,456 LF | $0.2500 | $0.2000 | $0.1749 | -$9,973 |
| 677-7002 ELIM EXT PM & MRKS (6") | 260,623 LF | $0.2000 | $0.1700 | $0.2755 | -$7,819 |
| 666-7505 RE PROFILE PM TY I(Y)6"(BRK)(125MIL) | 30,743.5 LF | $0.7500 | $0.9900 | $0.7500 | $7,378 |
| 672-7004 REFL PAV MRKR TY II-A-A | 5,736 EA | $5.00 | $3.83 | $3.97 | -$6,711 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 9,596 EA | $0.0100 | $0.5000 | $0.5715 | $4,702 |
| 668-7091 PREFAB PM TY C (W)(ARROW) | 33 EA | $175.00 | $261.00 | $201.69 | $2,838 |
| 668-7103 PREFAB PM TY C (W)(WORD) | 21 EA | $210.00 | $313.00 | $249.54 | $2,163 |
| 668-7089 PREFAB PM TY C (W)(24")(SLD) | 395 LF | $8.00 | $12.50 | $13.72 | $1,778 |
| 666-7451 REFL PAV MRK TY I (W)8"(SLD)(125MIL) | 3,779 LF | $0.7000 | $1.04 | $0.9392 | $1,285 |
| 666-7217 RE PM TY II (Y) 24" (SLD) | 836 LF | $5.00 | $4.17 | $3.73 | -$694 |
Positive: the low bidder was cheaper on that item. These 20 items account for $30,504 of the $29,918 gap.
CLARK CONSTRUCTION OF TEXAS, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 43,998 LF | $5.00 | $2.80 | 1.79x | $96,888 |
HAYDEN PAVING, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $2,000.00 | $11,585.04 | 0.17x | -$47,925 |
FORDE CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 4RONALD R. WAGNER & CO., LP: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $0.0100 | $11,585.04 | 0.00x | -$57,925 |