FY27 - Brenham AO LRA - 10
6508-78-001 · let Oct 13, 2026 · Washington, Bryan · Material Maintenance Project
$312,536Low bid: VULCAN CONSTRUCTION MATERIALS, LLC+9.7% vs estimate $284,900
$36,475Left on the table11.7% gap to the second bid
2BiddersSpread 12% low to high
4Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | VULCAN CONSTRUCTION MATERIALS, LLC | $312,536 | 9.7% | $36,475 | 0 | 0 | |
| 2 | MARTIN MARIETTA MATERIALS, INC. | $349,011 | +11.7% | 22.5% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
VULCAN CONSTRUCTION MATERIALS, LLC vs MARTIN MARIETTA MATERIALS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8001-7109 LRA (TY II GR DS) (DEL) (ST3) | 700 TON | $142.88 | $159.33 | $132.08 | $11,515 |
| 8001-7107 LRA (TY II GR DS) (DEL) (ST1) | 500 TON | $141.20 | $158.82 | $125.06 | $8,810 |
| 8001-7024 LRA (TY I GR A) (DEL) (ST2) | 500 TON | $141.92 | $158.07 | $129.21 | $8,075 |
| 8001-7094 LRA (TY II GR CS) (DEL) (ST2) | 500 TON | $141.92 | $158.07 | $127.06 | $8,075 |
Positive: the low bidder was cheaper on that item. These 4 items account for $36,475 of the $36,475 gap.