Bridge Maintenance - Hopkins Co. FY27
6508-04-001 · let Oct 15, 2026 · Hopkins, Paris · Routine Maintenance Project - Sealed
$252,821Low bid: 12TWELVE ROAD AND BRIDGE LLC-33.7% vs estimate $381,350
$10,780Left on the table4.3% gap to the second bid
11BiddersSpread 35% low to high
11Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | 12TWELVE ROAD AND BRIDGE LLC | $252,821 | -33.7% | $10,780 | 3+$31,956 | 3-$534,484 | |
| 2 | GARRET SHIELDS INFRASTRUCTURE | $263,600 | +4.3% | -30.9% | $4,493 | 4+$28,582 | 2-$513,605 |
| 3 | PREMIER CONTRACTORS LLC | $268,093 | +6.0% | -29.7% | $3,927 | 4+$75,333 | 4-$563,113 |
| 4 | MACIAS SPECIALTY CONTRACTING LLC | $272,020 | +7.6% | -28.7% | $17,592 | 3+$16,656 | 1-$498,850 |
| 5 | INFRATEX CONSTRUCTION LLC | $289,612 | +14.6% | -24.1% | $2,680 | 4+$132,348 | 4-$573,264 |
| 6 | THE TRUESDELL CORPORATION | $292,292 | +15.6% | -23.4% | $15,058 | ||
| 7 | C & W SOUTHERN LLC | $307,350 | +21.6% | -19.4% | $7,400 | ||
| 8 | ROAD DOCTORS LLC | $314,750 | +24.5% | -17.5% | $5,801 | ||
| 9 | ICOS MANAGEMENT, LLC | $320,551 | +26.8% | -15.9% | $4,209 | ||
| 10 | GHB EQUIPMENT COMPANY, L.L.C. | $324,760 | +28.5% | -14.8% | $15,444 | ||
| 11 | STRUCTURAL INTEGRITY GROUP LLC | $340,204 | +34.6% | -10.8% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
12TWELVE ROAD AND BRIDGE LLC vs GARRET SHIELDS INFRASTRUCTURE, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 50 DAY | $0.0100 | $300.00 | $217.57 | $15,000 |
| 500-7001 MOBILIZATION | 1 LS | $20,000.00 | $30,000.00 | $523,850.32 | $10,000 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 238 SF | $240.00 | $200.00 | $150.68 | -$9,520 |
| 110-7003 EXCAV (SPECIAL) | 100 CY | $140.00 | $80.00 | $18.78 | -$6,000 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 85 CY | $240.00 | $200.00 | $184.74 | -$3,400 |
| 132-7013 EMBANK (VEH)(OC)(TY A) | 50 CY | $40.00 | $100.00 | $47.47 | $3,000 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 340 CY | $245.00 | $250.00 | $190.61 | $1,700 |
| 100-7002 PREPARING ROW | 1 STA | $15,000.00 | $15,000.00 | $6,072.92 | $0 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 320 LF | $50.00 | $50.00 | $15.92 | $0 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $5,000.00 | $5,000.00 | $11,585.04 | $0 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 100 DAY | $100.00 | $100.00 | $87.82 | $0 |
Positive: the low bidder was cheaper on that item. These 11 items account for $10,780 of the $10,780 gap.
12TWELVE ROAD AND BRIDGE LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7003 EXCAV (SPECIAL) | 100 CY | $140.00 | $18.78 | 7.46x | $12,122 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 320 LF | $50.00 | $15.92 | 3.14x | $10,906 |
| 100-7002 PREPARING ROW | 1 STA | $15,000.00 | $6,072.92 | 2.47x | $8,927 |
| 500-7001 MOBILIZATION | 1 LS | $20,000.00 | $523,850.32 | 0.04x | -$503,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $5,000.00 | $11,585.04 | 0.43x | -$19,755 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $0.0100 | $217.57 | 0.00x | -$10,878 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 320 LF | $50.00 | $15.92 | 3.14x | $10,906 |
| 100-7002 PREPARING ROW | 1 STA | $15,000.00 | $6,072.92 | 2.47x | $8,927 |
| 110-7003 EXCAV (SPECIAL) | 100 CY | $80.00 | $18.78 | 4.26x | $6,122 |
| 132-7013 EMBANK (VEH)(OC)(TY A) | 50 CY | $100.00 | $47.47 | 2.11x | $2,626 |
| 500-7001 MOBILIZATION | 1 LS | $30,000.00 | $523,850.32 | 0.06x | -$493,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $5,000.00 | $11,585.04 | 0.43x | -$19,755 |
PREMIER CONTRACTORS LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 238 SF | $330.00 | $150.68 | 2.19x | $42,678 |
| 110-7003 EXCAV (SPECIAL) | 100 CY | $200.00 | $18.78 | 10.65x | $18,122 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 320 LF | $50.00 | $15.92 | 3.14x | $10,906 |
| 132-7013 EMBANK (VEH)(OC)(TY A) | 50 CY | $120.00 | $47.47 | 2.53x | $3,626 |
| 500-7001 MOBILIZATION | 1 LS | $15,000.00 | $523,850.32 | 0.03x | -$508,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $1.00 | $11,585.04 | 0.00x | -$34,752 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $1.00 | $217.57 | 0.00x | -$10,829 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 100 DAY | $1.00 | $87.82 | 0.01x | -$8,682 |
MACIAS SPECIALTY CONTRACTING LLC: unbalanced items
Placed 4INFRATEX CONSTRUCTION LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 340 CY | $350.00 | $190.61 | 1.84x | $54,192 |
| 100-7002 PREPARING ROW | 1 STA | $50,000.00 | $6,072.92 | 8.23x | $43,927 |
| 110-7003 EXCAV (SPECIAL) | 100 CY | $300.00 | $18.78 | 15.98x | $28,122 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 320 LF | $35.00 | $15.92 | 2.20x | $6,106 |
| 500-7001 MOBILIZATION | 1 LS | $5,000.00 | $523,850.32 | 0.01x | -$518,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $0.0100 | $11,585.04 | 0.00x | -$34,755 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $0.0100 | $217.57 | 0.00x | -$10,878 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 100 DAY | $0.0100 | $87.82 | 0.00x | -$8,781 |