Debris Removal - Grayson Co FY27
6507-51-001 · let Oct 15, 2026 · Grayson, Paris · Routine Maintenance Project - Sealed
$553,846Low bid: SWEEPING CORPORATION OF AMERICA, LLC-12.2% vs estimate $631,000
$15,674Left on the table2.8% gap to the second bid
7BiddersSpread 60% low to high
5Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SWEEPING CORPORATION OF AMERICA, LLC | $553,846 | -12.2% | $15,674 | 0 | 3-$652,087 | |
| 2 | ADVANCED BARRICADES OF AMERICA, LLC | $569,520 | +2.8% | -9.7% | $17,000 | 0 | 1-$513,850 |
| 3 | BOEN LANDSCAPING & IRRIGATION, LLC | $586,520 | +5.9% | -7.0% | $70,080 | 1+$400,610 | 4-$874,834 |
| 4 | ROAD SOLUTIONS L.L.C. | $656,600 | +18.6% | 4.1% | $54,400 | 1+$127,610 | 1-$493,850 |
| 5 | XIT PAVING AND CONSTRUCTION INC. | $711,000 | +28.4% | 12.7% | $90,696 | 1+$244,610 | 1-$488,850 |
| 6 | GROD CONSTRUCTION LLC | $801,696 | +44.8% | 27.1% | $82,064 | ||
| 7 | ANTHONY SERVICES | $883,760 | +59.6% | 40.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
SWEEPING CORPORATION OF AMERICA, LLC vs ADVANCED BARRICADES OF AMERICA, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 520 DAY | $249.00 | $115.00 | $229.60 | -$69,680 |
| 735-7026 DEBRIS REMOVAL (FRONTAGE ROADS) | 52 CYC | $249.00 | $1,000.00 | $1,988.40 | $39,052 |
| 735-7038 DEBRIS REMOVAL (ENTRANCE/EXIT RAMPS) | 52 CYC | $249.00 | $922.00 | $1,278.58 | $34,996 |
| 735-7015 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (1) | 208 CYC | $1,840.00 | $1,922.00 | $1,190.48 | $17,056 |
| 500-7001 MOBILIZATION | 1 LS | $15,750.00 | $10,000.00 | $523,850.32 | -$5,750 |
Positive: the low bidder was cheaper on that item. These 5 items account for $15,674 of the $15,674 gap.
SWEEPING CORPORATION OF AMERICA, LLC: unbalanced items
Placed 1ADVANCED BARRICADES OF AMERICA, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $10,000.00 | $523,850.32 | 0.02x | -$513,850 |
BOEN LANDSCAPING & IRRIGATION, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 520 DAY | $1,000.00 | $229.60 | 4.36x | $400,610 |
| 500-7001 MOBILIZATION | 1 LS | $1,000.00 | $523,850.32 | 0.00x | -$522,850 |
| 735-7015 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (1) | 208 CYC | $210.00 | $1,190.48 | 0.18x | -$203,941 |
| 735-7026 DEBRIS REMOVAL (FRONTAGE ROADS) | 52 CYC | $210.00 | $1,988.40 | 0.11x | -$92,477 |
| 735-7038 DEBRIS REMOVAL (ENTRANCE/EXIT RAMPS) | 52 CYC | $210.00 | $1,278.58 | 0.16x | -$55,566 |