Bid Tab X-ray: 6496-56-001

Oct 6, 2026 · Brown Sign up free
Set your company to personalize scores

THERMOPLASTIC STRIPING AND PAV

6496-56-001 · let Oct 6, 2026 · Brown, Brownwood · Routine Maintenance Project

$3,276,697Low bid: DOUBLE A CONTRACTING, L.P.-25.8% vs estimate $4,414,901
$320,110Left on the table9.8% gap to the second bid
7BiddersSpread 92% low to high
38Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1DOUBLE A CONTRACTING, L.P. $3,276,697-25.8% $320,110 0 1-$51,663
2STRIPE LINES, INC. $3,596,807+9.8%-18.5% $231,078 0 1-$49,629
3CENTERLINE TECHNOLOGIES, LLC $3,827,885+16.8%-13.3% $53,329 0 1-$51,663
4TRP INFRASTRUCTURE SERVICES, LLC $3,881,214+18.4%-12.1% $165,740 0 1-$51,663
5FLAT LINE, INC. $4,046,954+23.5%-8.3% $897,856 1+$43,197 1-$29,289
6STRIPE-A-ZONE, LLC $4,944,811+50.9%12.0% $1,350,390
7L&L COMPANY $6,295,201+92.1%42.6%

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

DOUBLE A CONTRACTING, L.P. vs STRIPE LINES, INC., biggest item swings
ItemQtyLow2ndMarket2nd minus low
666-7409 REFL PAV MRK TY I (W)6"(SLD)(060MIL)4,569,903 LF $0.2800$0.3200$0.3171 $182,796
666-7421 REFL PAV MRK TY I (Y)6"(SLD)(060MIL)4,542,906 LF $0.3000$0.3200$0.3278 $90,858
668-7089 PREFAB PM TY C (W)(24")(SLD)10,642 LF $11.50$13.41$13.72 $20,326
668-7111 PREFAB PM TY C (W)(36")(YLD TRI)234 EA $16.00$79.33$38.96 $14,819
666-7418 REFL PAV MRK TY I (Y)6"(BRK)(060MIL)482,483 LF $0.3000$0.3200$0.3503 $9,650
500-7002 MOBILIZATION (CALLOUT)3 EA $5,500.00$3,500.00$600.85 -$6,000
668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE)5,500 LF $4.50$3.50$2.80 -$5,500
666-7022 REFL PAV MRK TY I (W)8"(SLD)(060MIL)30,416 LF $0.4800$0.6500$0.6127 $5,171
668-7127 PREFAB PM TY C (Y)(24")(SLD)1,353 LF $10.00$13.53$11.82 $4,776
668-7091 PREFAB PM TY C (W)(ARROW)148 EA $180.00$208.85$201.69 $4,270
668-7100 PREFAB PM TY C (W)(LN REDUCT ARROW)37 EA $550.00$435.00$467.68 -$4,255
505-7003 TMA (MOBILE OPERATION)226 DAY $1.00$10.00$229.60 $2,034
666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL)50,000 LF $0.7500$0.7900$0.6515 $2,000
666-7270 RE PROFILE PM TY I(Y)6"(SLD)(100MIL)50,000 LF $0.7500$0.7900$0.6629 $2,000
666-7274 RE PROFILE PM TY I(Y)6"(BRK)(100MIL)50,000 LF $0.7500$0.7900$0.6738 $2,000
668-7093 PREFAB PM TY C (W)(DBL ARROW)7 EA $550.00$294.97$314.80 -$1,785
666-7007 REFL PAV MRK TY I (W)6"(DOT)(060MIL)8,085 LF $0.3800$0.5300$0.7227 $1,213
666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL)9,299 LF $0.6500$0.5200$0.4986 -$1,209
666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL)4,158 LF $0.7500$0.5200$0.4757 -$956
668-7108 PREFAB PM TY C (W)(RR XING)28 EA $550.00$517.08$602.94 -$922

Positive: the low bidder was cheaper on that item. These 20 items account for $321,286 of the $320,110 gap.

DOUBLE A CONTRACTING, L.P.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
505-7003 TMA (MOBILE OPERATION)226 DAY $1.00$229.600.00x-$51,663

STRIPE LINES, INC.: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
505-7003 TMA (MOBILE OPERATION)226 DAY $10.00$229.600.04x-$49,629

CENTERLINE TECHNOLOGIES, LLC: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
505-7003 TMA (MOBILE OPERATION)226 DAY $1.00$229.600.00x-$51,663

TRP INFRASTRUCTURE SERVICES, LLC: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
505-7003 TMA (MOBILE OPERATION)226 DAY $1.00$229.600.00x-$51,663

FLAT LINE, INC.: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
500-7002 MOBILIZATION (CALLOUT)3 EA $15,000.00$600.8524.96x$43,197
505-7003 TMA (MOBILE OPERATION)226 DAY $100.00$229.600.44x-$29,289