Loring Creek Relief
1097-01-018 · let Mar 5, 2026 · Hunt, Paris · Bridge Replacement
$2,085,509Low bid: HODGES AND SON CONSTRUCTION COMPANY, INC.-23.5% vs estimate $2,724,592
$40,055Left on the table1.9% gap to the second bid
12BiddersSpread 46% low to high
111Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $2,085,509 | -23.5% | $40,055 | 0 | 3-$448,210 | |
| 2 | TUCAN CONTRACTING, LLC | $2,125,564 | +1.9% | -22.0% | $121,373 | 2+$29,491 | 3-$581,137 |
| 3 | SKYLINE BRIDGE LLC | $2,246,938 | +7.7% | -17.5% | $22,929 | 3+$125,259 | 4-$521,567 |
| 4 | TEXAS STEEL INDUSTRIAL PLACING, LLC | $2,269,867 | +8.8% | -16.7% | $144,557 | 3+$75,190 | 3-$466,915 |
| 5 | EAST TEXAS BRIDGE, INC. | $2,414,424 | +15.8% | -11.4% | $41,649 | 2+$49,013 | 3-$441,697 |
| 6 | THK CONSTRUCTION LLC | $2,456,073 | +17.8% | -9.9% | $11,239 | ||
| 7 | TALBERT COMPANIES LLC | $2,467,312 | +18.3% | -9.4% | $34,420 | ||
| 8 | HIGHWAY 19 CONSTRUCTION LLC | $2,501,732 | +20.0% | -8.2% | $62,333 | ||
| 9 | R CONSTRUCTION CIVIL, LLC | $2,564,064 | +22.9% | -5.9% | $24,255 | ||
| 10 | GARRET SHIELDS INFRASTRUCTURE | $2,588,319 | +24.1% | -5.0% | $36,899 | ||
| 11 | RB CONTRACTING, LLC | $2,625,218 | +25.9% | -3.6% | $413,272 | ||
| 12 | COPPELL CONSTRUCTION CO., INC. | $3,038,489 | +45.7% | 11.5% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
HODGES AND SON CONSTRUCTION COMPANY, INC. vs TUCAN CONTRACTING, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $170,000.00 | $100,000.00 | $523,850.32 | -$70,000 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 1,641 CY | $175.00 | $148.50 | $190.61 | -$43,487 |
| 425-7001 PRESTR CONC GIRDER (TX28) | 1,040 LF | $230.00 | $191.32 | $217.69 | -$40,227 |
| 450-7008 RAIL (TY T223) | 516 LF | $120.00 | $187.00 | $141.07 | $34,572 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 4,786 CY | $15.00 | $22.00 | $13.19 | $33,502 |
| 416-7006 DRILL SHAFT (36 IN) | 800 LF | $195.00 | $154.00 | $280.58 | -$32,800 |
| 100-7002 PREPARING ROW | 16 STA | $3,250.00 | $1,210.00 | $6,072.92 | -$32,640 |
| 420-7012 CL C CONC (ABUT) | 89.2 CY | $900.00 | $1,210.00 | $1,307.98 | $27,652 |
| 341-7034 D-GR HMA TY-C SAC-A PG64-22(EXEMPT) | 741 TON | $145.00 | $177.43 | $136.91 | $24,031 |
| 422-7013 APPROACH SLAB | 108 CY | $795.00 | $990.00 | $738.51 | $21,060 |
| 422-7001 REINF CONC SLAB | 7,560 SF | $26.00 | $28.60 | $24.45 | $19,656 |
| 110-7002 EXCAV (CHANNEL) | 1,031 CY | $15.00 | $33.00 | $16.69 | $18,558 |
| 341-7003 D-GR HMA TY-B PG64-22 (EXEMPT) | 1,006 TON | $140.00 | $155.98 | $127.48 | $16,076 |
| 420-7022 CL C CONC (CAP) | 31.4 CY | $900.00 | $1,320.00 | $1,543.38 | $13,188 |
| 132-7001 EMBANK (FNL)(OC)(TY A) | 166 CY | $20.00 | $99.00 | $22.62 | $13,114 |
| 506-7020 CONSTRUCTION EXITS (INSTALL) (TY 1) | 600 SY | $1.00 | $22.00 | $30.47 | $12,600 |
| 5011-7002 REMOVE LEAD-CONTAINING COATING (OTHER) | 2 LS | $15,000.00 | $10,900.00 | $15,780.56 | -$8,200 |
| 506-7002 ROCK FILTER DAMS (INSTALL) (TY 2) | 160 LF | $1.00 | $44.00 | $44.91 | $6,880 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $10,500.00 | $8,800.00 | $9,253.78 | -$6,800 |
| 454-7003 ARMOR JOINT (SEALED) | 204 LF | $120.00 | $88.00 | $154.25 | -$6,528 |
Positive: the low bidder was cheaper on that item. These 20 items account for $207 of the $40,055 gap.
HODGES AND SON CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 1TUCAN CONTRACTING, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7002 EXCAV (CHANNEL) | 1,031 CY | $33.00 | $16.69 | 1.98x | $16,812 |
| 132-7001 EMBANK (FNL)(OC)(TY A) | 166 CY | $99.00 | $22.62 | 4.38x | $12,680 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $1,650.00 | $11,585.04 | 0.14x | -$79,480 |
| 100-7002 PREPARING ROW | 16 STA | $1,210.00 | $6,072.92 | 0.20x | -$77,807 |
SKYLINE BRIDGE LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7006 EMBANK (FNL)(DC)(TY C) | 4,786 CY | $29.25 | $13.19 | 2.22x | $76,854 |
| 251-7051 REWORK BS MTL (TY C)(8")(ORD COMP) | 3,706 SY | $10.57 | $2.89 | 3.66x | $28,465 |
| 400-7010 CEM STABIL BKFL | 140 CY | $280.57 | $138.14 | 2.03x | $19,940 |
| 500-7001 MOBILIZATION | 1 LS | $180,000.00 | $523,850.32 | 0.34x | -$343,850 |
| 100-7002 PREPARING ROW | 16 STA | $775.00 | $6,072.92 | 0.13x | -$84,767 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $2,176.17 | $11,585.04 | 0.19x | -$75,271 |
| 506-7020 CONSTRUCTION EXITS (INSTALL) (TY 1) | 600 SY | $1.00 | $30.47 | 0.03x | -$17,679 |
TEXAS STEEL INDUSTRIAL PLACING, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $17,000.00 | $9,253.78 | 1.84x | $30,985 |
| 530-7015 DRIVEWAYS (BASE) | 680 SY | $65.00 | $27.85 | 2.33x | $25,264 |
| 251-7051 REWORK BS MTL (TY C)(8")(ORD COMP) | 3,706 SY | $8.00 | $2.89 | 2.77x | $18,941 |
| 500-7001 MOBILIZATION | 1 LS | $226,782.03 | $523,850.32 | 0.43x | -$297,068 |
| 100-7002 PREPARING ROW | 16 STA | $500.00 | $6,072.92 | 0.08x | -$89,167 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $1,500.00 | $11,585.04 | 0.13x | -$80,680 |
EAST TEXAS BRIDGE, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 251-7051 REWORK BS MTL (TY C)(8")(ORD COMP) | 3,706 SY | $10.00 | $2.89 | 3.46x | $26,353 |
| 400-7010 CEM STABIL BKFL | 140 CY | $300.00 | $138.14 | 2.17x | $22,660 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $4,000.00 | $11,585.04 | 0.35x | -$60,680 |
| 100-7002 PREPARING ROW | 16 STA | $2,500.00 | $6,072.92 | 0.41x | -$57,167 |