FM 2790:2883-01-004; RER
2883-01-004 · let Mar 4, 2026 · Medina, San Antonio · Rehabilitation of Existing Road
$11,778,114Low bid: DEAN WORD COMPANY, LTD.-27.3% vs estimate $16,198,822
$126,020Left on the table1.1% gap to the second bid
9BiddersSpread 46% low to high
196Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | DEAN WORD COMPANY, LTD. | $11,778,114 | -27.3% | $126,020 | 3+$195,316 | 7-$2,707,569 | |
| 2 | HUNTER INDUSTRIES, LTD. | $11,904,134 | +1.1% | -26.5% | $95,481 | 2+$199,478 | 1-$1,750,931 |
| 3 | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. | $11,999,615 | +1.9% | -25.9% | $1,272,494 | 2+$200,146 | 2-$1,910,983 |
| 4 | D & D CONTRACTORS, INC. | $13,272,109 | +12.7% | -18.1% | $88,303 | 3+$335,338 | 4-$2,306,449 |
| 5 | TEXAS MATERIALS GROUP, INC. | $13,360,412 | +13.4% | -17.5% | $626,069 | 4+$960,310 | 1-$1,827,340 |
| 6 | E-Z BEL CONSTRUCTION, LLC | $13,986,481 | +18.7% | -13.7% | $293,717 | ||
| 7 | 3LW CIVIL LLC | $14,280,198 | +21.2% | -11.8% | $262,462 | ||
| 8 | J3 COMPANY, LLC | $14,542,659 | +23.5% | -10.2% | $2,655,019 | ||
| 9 | ANDERSON COLUMBIA CO., INC. | $17,197,678 | +46.0% | 6.2% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
DEAN WORD COMPANY, LTD. vs HUNTER INDUSTRIES, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 512-7033 PORT CTB (MOVE)(LOW PROF)(TY 1) | 37,260 LF | $3.15 | $11.00 | $8.08 | $292,491 |
| 500-7001 MOBILIZATION | 1 LS | $650,000.00 | $834,428.27 | $523,850.32 | $184,428 |
| 105-7007 RMV (7"-11") TRT/UNTRT BASE & ASPH PAV | 59,324 SY | $2.70 | $5.39 | $7.66 | $159,582 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 6,460 LF | $10.75 | $35.00 | $43.56 | $156,655 |
| 508-7001 CONSTRUCTING DETOURS | 15,089 SY | $94.90 | $85.97 | $83.58 | -$134,745 |
| 6089-7001 RESIDENTIAL DRIVEWAY TEMP SIGNAL SYSTEM | 12 MO | $4,987.30 | $16,073.82 | $6,943.78 | $133,038 |
| 260-7020 LIME TRT (SUBGRADE) (8") | 93,122 SY | $4.25 | $2.86 | $3.93 | -$129,440 |
| 100-7002 PREPARING ROW | 308 STA | $800.00 | $388.08 | $6,072.92 | -$126,871 |
| 530-7010 DRIVEWAYS (ACP) | 7,314 SY | $23.95 | $39.06 | $54.96 | $110,515 |
| 290-7021 EMUL TRT (NEW BASE) (6") | 89,283 SY | $4.50 | $3.30 | $4.50 | -$107,140 |
| 466-7147 WINGWALL (FW - 0) (HW=5 FT) | 4 EA | $27,966.80 | $8,593.36 | $18,162.70 | -$77,494 |
| 530-7002 INTERSECTIONS (ACP) | 5,686 SY | $25.90 | $39.06 | $50.74 | $74,828 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $5,601.00 | $10,840.50 | $11,585.04 | $73,353 |
| 510-7002 ONE-WAY TRAF CONT (PILOT CAR) | 240 HR | $376.90 | $99.00 | $98.78 | -$66,696 |
| 168-7001 VEGETATIVE WATERING | 3,431 TGL | $1.50 | $20.72 | $8.43 | $65,944 |
| 738-7005 CLEAN / SWEEP - CENTER MEDIAN - AREA(1) | 14 CYC | $696.20 | $5,000.00 | $2,445.81 | $60,253 |
| 467-7292 SET (TY II) (12 IN) (RCP) (6: 1) (P) | 86 EA | $1,434.35 | $746.85 | $1,205.57 | -$59,125 |
| 260-7001 LIME (COM OR QK)(SLURRY) OR QK(DRY) | 1,853 TON | $355.35 | $326.35 | $345.77 | -$53,737 |
| 112-7001 SUBGR WIDEN (OC) | 59 STA | $1,612.10 | $725.94 | $458.34 | -$52,283 |
| 344-7031 SP MIXES SP-C SAC-B PG76-22 | 13,308 TON | $95.40 | $91.52 | $97.84 | -$51,635 |
Positive: the low bidder was cheaper on that item. These 20 items account for $451,921 of the $126,020 gap.
DEAN WORD COMPANY, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 112-7001 SUBGR WIDEN (OC) | 59 STA | $1,612.10 | $458.34 | 3.52x | $68,072 |
| 510-7002 ONE-WAY TRAF CONT (PILOT CAR) | 240 HR | $376.90 | $98.78 | 3.82x | $66,749 |
| 510-7003 ONE-WAY TRAF CONT (PORT TRAF SIG) | 12 MO | $10,021.55 | $4,980.23 | 2.01x | $60,496 |
| 100-7002 PREPARING ROW | 308 STA | $800.00 | $6,072.92 | 0.13x | -$1,624,060 |
| 105-7007 RMV (7"-11") TRT/UNTRT BASE & ASPH PAV | 59,324 SY | $2.70 | $7.66 | 0.35x | -$294,277 |
| 530-7010 DRIVEWAYS (ACP) | 7,314 SY | $23.95 | $54.96 | 0.44x | -$226,774 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 6,460 LF | $10.75 | $43.56 | 0.25x | -$211,958 |
| 512-7033 PORT CTB (MOVE)(LOW PROF)(TY 1) | 37,260 LF | $3.15 | $8.08 | 0.39x | -$183,785 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $5,601.00 | $11,585.04 | 0.48x | -$83,777 |
| 530-7018 TURNOUTS (ACP) | 1,292 SY | $18.40 | $82.59 | 0.22x | -$82,939 |
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 2SALINAS CONSTRUCTION TECHNOLOGIES, LTD.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 6089-7001 RESIDENTIAL DRIVEWAY TEMP SIGNAL SYSTEM | 12 MO | $16,103.10 | $6,943.78 | 2.32x | $109,912 |
| 510-7003 ONE-WAY TRAF CONT (PORT TRAF SIG) | 12 MO | $12,499.78 | $4,980.23 | 2.51x | $90,235 |
| 100-7002 PREPARING ROW | 308 STA | $202.15 | $6,072.92 | 0.03x | -$1,808,198 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $4,243.23 | $11,585.04 | 0.37x | -$102,785 |
D & D CONTRACTORS, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 6089-7001 RESIDENTIAL DRIVEWAY TEMP SIGNAL SYSTEM | 12 MO | $18,134.26 | $6,943.78 | 2.61x | $134,286 |
| 510-7003 ONE-WAY TRAF CONT (PORT TRAF SIG) | 12 MO | $14,290.08 | $4,980.23 | 2.87x | $111,718 |
| 316-7175 AGGR (TY-B, GR-5)(SAC-B) | 653 CY | $225.00 | $88.19 | 2.55x | $89,334 |
| 100-7002 PREPARING ROW | 308 STA | $139.15 | $6,072.92 | 0.02x | -$1,827,602 |
| 530-7010 DRIVEWAYS (ACP) | 7,314 SY | $14.00 | $54.96 | 0.25x | -$299,549 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $4,369.97 | $11,585.04 | 0.38x | -$101,011 |
| 530-7018 TURNOUTS (ACP) | 1,292 SY | $22.00 | $82.59 | 0.27x | -$78,288 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $985,654.00 | $523,850.32 | 1.88x | $461,804 |
| 6089-7001 RESIDENTIAL DRIVEWAY TEMP SIGNAL SYSTEM | 12 MO | $32,000.00 | $6,943.78 | 4.61x | $300,675 |
| 510-7003 ONE-WAY TRAF CONT (PORT TRAF SIG) | 12 MO | $15,300.00 | $4,980.23 | 3.07x | $123,837 |
| 168-7001 VEGETATIVE WATERING | 3,431 TGL | $30.00 | $8.43 | 3.56x | $73,994 |
| 100-7002 PREPARING ROW | 308 STA | $140.00 | $6,072.92 | 0.02x | -$1,827,340 |