Bid Tab X-ray: 6506-32-001

Sep 30, 2026 · Nacogdoches Sign up free
Set your company to personalize scores

Nacogdoches Callout Mill & Inlay

6506-32-001 · let Sep 30, 2026 · Nacogdoches, Lufkin · Routine Maintenance Project - Sealed

$1,161,503Low bid: TEXAS MATERIALS GROUP, INC.+16.5% vs estimate $997,023
$637,880Left on the table54.9% gap to the second bid
2BiddersSpread 55% low to high
8Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1TEXAS MATERIALS GROUP, INC. $1,161,50316.5% $637,880 2+$146,068 0
2DREWERY CONSTRUCTION COMPANY, INCORPORATED $1,799,383+54.9%80.5% 6+$1,056,586 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.

Where the job was won

TEXAS MATERIALS GROUP, INC. vs DREWERY CONSTRUCTION COMPANY, INCORPORATED, biggest item swings
ItemQtyLow2ndMarket2nd minus low
344-7030 SP MIXES SP-C SAC-A PG76-224,000 TON $218.05$380.00$138.38 $647,800
354-7083 PLANE ASPH CONC PAV (0" TO 2-1/2")36,352 SY $6.40$4.20$2.98 -$79,974
505-7001 TMA (STATIONARY)50 DAY $203.45$675.00$217.57 $23,578
662-7065 WK ZN PAV MRK REMOV (W)6"(BRK)6,120 LF $1.25$4.00$1.02 $16,830
505-7003 TMA (MOBILE OPERATION)20 DAY $100.00$900.00$229.60 $16,000
662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD)4,720 LF $1.25$4.00$0.8371 $12,980
3007-7001 BONDING COURSE1,819 GAL $4.12$5.00$3.32 $1,601
500-7002 MOBILIZATION (CALLOUT)3 EA $7,811.29$7,500.00$600.85 -$934

Positive: the low bidder was cheaper on that item. These 8 items account for $637,880 of the $637,880 gap.

TEXAS MATERIALS GROUP, INC.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
354-7083 PLANE ASPH CONC PAV (0" TO 2-1/2")36,352 SY $6.40$2.982.15x$124,437
500-7002 MOBILIZATION (CALLOUT)3 EA $7,811.29$600.8513.00x$21,631

DREWERY CONSTRUCTION COMPANY, INCORPORATED: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
344-7030 SP MIXES SP-C SAC-A PG76-224,000 TON $380.00$138.382.75x$966,462
505-7001 TMA (STATIONARY)50 DAY $675.00$217.573.10x$22,871
500-7002 MOBILIZATION (CALLOUT)3 EA $7,500.00$600.8512.48x$20,697
662-7065 WK ZN PAV MRK REMOV (W)6"(BRK)6,120 LF $4.00$1.023.91x$18,218
662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD)4,720 LF $4.00$0.83714.78x$14,929
505-7003 TMA (MOBILE OPERATION)20 DAY $900.00$229.603.92x$13,408