Limestone Rock Asphalt 06 0926
6502-44-001 · let Sep 9, 2026 · Kaufman, Dallas · Material Maintenance Project
$108,418Low bid: MARTIN MARIETTA MATERIALS, INC.+15.6% vs estimate $93,820
$402Left on the table0.4% gap to the second bid
2BiddersSpread 0% low to high
2Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | MARTIN MARIETTA MATERIALS, INC. | $108,418 | 15.6% | $402 | 0 | 0 | |
| 2 | VULCAN CONSTRUCTION MATERIALS, LLC | $108,820 | +0.4% | 16.0% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
MARTIN MARIETTA MATERIALS, INC. vs VULCAN CONSTRUCTION MATERIALS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8001-7107 LRA (TY II GR DS) (DEL) (ST1) | 500 TON | $172.27 | $172.92 | $125.06 | $325 |
| 8001-7108 LRA (TY II GR DS) (DEL) (ST2) | 130 TON | $171.41 | $172.00 | $141.87 | $77 |
Positive: the low bidder was cheaper on that item. These 2 items account for $402 of the $402 gap.