6501-37-001 LRA
6501-37-001 · let Apr 28, 2026 · Midland, Odessa · Material Maintenance Project
$167,752Low bid: VULCAN CONSTRUCTION MATERIALS, LLC-9.6% vs estimate $185,600
$2,023Left on the table1.2% gap to the second bid
2BiddersSpread 1% low to high
10Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | VULCAN CONSTRUCTION MATERIALS, LLC | $167,752 | -9.6% | $2,023 | 0 | 0 | |
| 2 | MARTIN MARIETTA MATERIALS, INC. | $169,774 | +1.2% | -8.5% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
VULCAN CONSTRUCTION MATERIALS, LLC vs MARTIN MARIETTA MATERIALS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8001-7011 LRA (TY I GR AA) (DEL) (ST3) | 250 TON | $138.79 | $141.89 | $127.41 | $775 |
| 8001-7010 LRA (TY I GR AA) (DEL) (ST2) | 100 TON | $130.39 | $133.66 | $124.75 | $327 |
| 8001-7012 LRA (TY I GR AA) (DEL) (ST4) | 100 TON | $137.11 | $140.24 | $124.59 | $313 |
| 8001-7009 LRA (TY I GR AA) (DEL) (ST1) | 100 TON | $149.50 | $151.77 | $112.79 | $227 |
| 8001-7096 LRA (TY II GR CS) (DEL) (ST4) | 200 TON | $139.11 | $140.24 | $123.65 | $226 |
| 8001-7038 LRA (TY I GR B) (DEL) (ST2) | 100 TON | $132.39 | $133.66 | $153.94 | $127 |
| 8001-7107 LRA (TY II GR DS) (DEL) (ST1) | 50 TON | $152.50 | $151.77 | $125.06 | -$36 |
| 8001-7037 LRA (TY I GR B) (DEL) (ST1) | 100 TON | $151.50 | $151.77 | $152.70 | $27 |
| 8001-7108 LRA (TY II GR DS) (DEL) (ST2) | 100 TON | $133.39 | $133.66 | $141.87 | $27 |
| 8001-7109 LRA (TY II GR DS) (DEL) (ST3) | 100 TON | $141.79 | $141.89 | $132.08 | $10 |
Positive: the low bidder was cheaper on that item. These 10 items account for $2,023 of the $2,023 gap.