US 69_N of FM 841 to W of FM 1475-IOI
0200-01-093 · let Oct 7, 2026 · Angelina, Lufkin · Intersection & Operational Imprv
$31,796,270Low bid: LONGVIEW BRIDGE AND ROAD, LTD.-9.5% vs estimate $35,140,814
$1,482,945Left on the table4.7% gap to the second bid
7BiddersSpread 54% low to high
179Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | LONGVIEW BRIDGE AND ROAD, LTD. | $31,796,270 | -9.5% | $1,482,945 | 2+$1,694,793 | 3-$2,312,776 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $33,279,215 | +4.7% | -5.3% | $4,193,730 | 3+$2,574,930 | 2-$2,039,488 |
| 3 | A. L. HELMCAMP, INC. | $37,472,944 | +17.9% | 6.6% | $1,885,405 | 4+$4,270,027 | 0 |
| 4 | R CONSTRUCTION CIVIL, LLC | $39,358,349 | +23.8% | 12.0% | $1,398,832 | 7+$5,136,679 | 1-$446,914 |
| 5 | POSILLICO CIVIL, INC. | $40,757,181 | +28.2% | 16.0% | $6,084,560 | 3+$3,596,993 | 2-$1,481,931 |
| 6 | RAGLE CONSTRUCTION, INC. | $46,841,741 | +47.3% | 33.3% | $2,131,871 | ||
| 7 | DURWOOD GREENE CONSTRUCTION CO. | $48,973,611 | +54.0% | 39.4% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
LONGVIEW BRIDGE AND ROAD, LTD. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 132-7006 EMBANK (FNL)(DC)(TY C) | 32,049 CY | $10.00 | $26.70 | $13.19 | $535,218 |
| 500-7001 MOBILIZATION | 1 LS | $2,000,000.00 | $2,485,000.00 | $523,850.32 | $485,000 |
| 344-7084 SP MIXES SP-B PG70-22(LEVEL-UP) | 37,687 TON | $150.00 | $141.87 | $150.00 | -$306,395 |
| 512-7086 PTB (MOVE)(SSCB OR CSB)(TY1)OR(STL) | 19,040 LF | $3.00 | $18.91 | $9.41 | $302,926 |
| 316-7088 ASPH (AC-15P OR CRS-2P) | 495 TON | $1,000.00 | $1,438.00 | $1,008.86 | $216,810 |
| 512-7088 PTB (REMOVE)(SSCB OR CSB)(TY1)OR(STL) | 7,470 LF | $4.50 | $32.26 | $17.41 | $207,367 |
| 161-7002 COMPOST MANUF TOPSOIL (4") | 128,372 SY | $3.65 | $2.12 | $1.95 | -$196,409 |
| 512-7085 PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL) | 7,470 LF | $14.00 | $40.03 | $38.28 | $194,444 |
| 344-7030 SP MIXES SP-C SAC-A PG76-22 | 26,423 TON | $163.00 | $156.09 | $138.38 | -$182,583 |
| 425-7018 PRESTR CONC SLAB BEAM (4SB15) | 1,188 LF | $300.00 | $158.75 | $233.81 | -$167,805 |
| 462-7012 CONC BOX CULV (6 FT X 4 FT) | 1,380 LF | $480.00 | $599.90 | $553.42 | $165,462 |
| 425-7019 PRESTR CONC SLAB BEAM (5SB15) | 4,752 LF | $280.00 | $250.50 | $261.75 | -$140,184 |
| 344-7004 SP MIXES SP-B PG70-22 | 32,716 TON | $145.00 | $140.95 | $147.51 | -$132,500 |
| 403-7001 TEMPORARY SPL SHORING | 8,126 SF | $20.00 | $35.10 | $25.56 | $122,703 |
| 168-7001 VEGETATIVE WATERING | 8,929.2 TGL | $10.50 | $0.0100 | $8.43 | -$93,667 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 6 EA | $10,000.00 | $25,000.00 | $9,253.78 | $90,000 |
| 104-7001 REMOV CONC (PAV) | 2,374 SY | $23.00 | $55.50 | $11.85 | $77,155 |
| 275-7015 CEMENT TRT (SUBGRADE)(12") | 42,275 SY | $2.00 | $3.76 | $2.55 | $74,404 |
| 100-7002 PREPARING ROW | 305.45 STA | $1,000.00 | $1,240.00 | $6,072.92 | $73,308 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 3,010 CY | $185.00 | $161.25 | $190.61 | -$71,488 |
Positive: the low bidder was cheaper on that item. These 20 items account for $1,253,767 of the $1,482,945 gap.
LONGVIEW BRIDGE AND ROAD, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,000,000.00 | $523,850.32 | 3.82x | $1,476,150 |
| 161-7002 COMPOST MANUF TOPSOIL (4") | 128,372 SY | $3.65 | $1.95 | 1.87x | $218,643 |
| 100-7002 PREPARING ROW | 305.45 STA | $1,000.00 | $6,072.92 | 0.16x | -$1,549,524 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 62 MO | $2,200.00 | $11,585.04 | 0.19x | -$581,873 |
| 512-7085 PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL) | 7,470 LF | $14.00 | $38.28 | 0.37x | -$181,380 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,485,000.00 | $523,850.32 | 4.74x | $1,961,150 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 32,049 CY | $26.70 | $13.19 | 2.02x | $432,921 |
| 512-7086 PTB (MOVE)(SSCB OR CSB)(TY1)OR(STL) | 19,040 LF | $18.91 | $9.41 | 2.01x | $180,859 |
| 100-7002 PREPARING ROW | 305.45 STA | $1,240.00 | $6,072.92 | 0.20x | -$1,476,216 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 62 MO | $2,500.00 | $11,585.04 | 0.22x | -$563,273 |
A. L. HELMCAMP, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,700,000.00 | $523,850.32 | 7.06x | $3,176,150 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 32,049 CY | $28.00 | $13.19 | 2.12x | $474,585 |
| 512-7085 PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL) | 7,470 LF | $84.00 | $38.28 | 2.19x | $341,520 |
| 512-7086 PTB (MOVE)(SSCB OR CSB)(TY1)OR(STL) | 19,040 LF | $24.00 | $9.41 | 2.55x | $277,773 |
R CONSTRUCTION CIVIL, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,850,000.00 | $523,850.32 | 7.35x | $3,326,150 |
| 416-7004 DRILL SHAFT (24 IN) | 2,700 LF | $430.00 | $234.98 | 1.83x | $526,564 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 32,049 CY | $24.00 | $13.19 | 1.82x | $346,389 |
| 134-7002 BACKFILL (TY B) | 305.45 STA | $1,100.00 | $206.94 | 5.32x | $272,785 |
| 168-7001 VEGETATIVE WATERING | 8,929.2 TGL | $35.00 | $8.43 | 4.15x | $237,216 |
| 512-7085 PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL) | 7,470 LF | $67.00 | $38.28 | 1.75x | $214,530 |
| 110-7001 EXCAV (ROADWAY) | 18,824 CY | $23.00 | $11.68 | 1.97x | $213,046 |
| 316-7088 ASPH (AC-15P OR CRS-2P) | 495 TON | $106.00 | $1,008.86 | 0.11x | -$446,914 |
POSILLICO CIVIL, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,500,000.00 | $523,850.32 | 6.68x | $2,976,150 |
| 512-7085 PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL) | 7,470 LF | $80.00 | $38.28 | 2.09x | $311,640 |
| 316-7268 AGGR (TY E OR L, PE OR PL GR 4) | 2,053 CY | $323.00 | $172.39 | 1.87x | $309,203 |
| 100-7002 PREPARING ROW | 305.45 STA | $2,700.00 | $6,072.92 | 0.44x | -$1,030,259 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 62 MO | $4,300.00 | $11,585.04 | 0.37x | -$451,673 |