CRP_FM0665_NUECES_HSIP
1052-02-098 · let Nov 4, 2026 · Nueces, Corpus Christi · Safety Improvement Projects
$3,833,265Low bid: J E CONSTRUCTION SERVICES, LLC-20.0% vs estimate $4,792,153
$3,958Left on the table0.1% gap to the second bid
5BiddersSpread 29% low to high
88Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | J E CONSTRUCTION SERVICES, LLC | $3,833,265 | -20.0% | $3,958 | 1+$20,827 | 2-$276,372 | |
| 2 | ANDERSON COLUMBIA CO., INC. | $3,837,222 | +0.1% | -19.9% | $779,579 | 2+$77,853 | 4-$499,304 |
| 3 | CK NEWBERRY, LLC | $4,616,801 | +20.4% | -3.7% | $200,600 | 3+$177,729 | 2-$262,232 |
| 4 | STX CIVIL | $4,817,402 | +25.7% | 0.5% | $125,914 | 4+$521,440 | 4-$540,640 |
| 5 | TEXAS MATERIALS GROUP, INC. | $4,943,316 | +29.0% | 3.2% | 5+$194,869 | 3-$347,151 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
J E CONSTRUCTION SERVICES, LLC vs ANDERSON COLUMBIA CO., INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 247-7348 FL BS (CIP)(TY A GR 1-2 OR 5) FINAL POS | 5,473 CY | $54.00 | $86.00 | $77.43 | $175,136 |
| 508-7001 CONSTRUCTING DETOURS | 14,413 SY | $59.00 | $49.00 | $83.58 | -$144,130 |
| 500-7001 MOBILIZATION | 1 LS | $327,944.00 | $236,600.00 | $523,850.32 | -$91,344 |
| 105-7123 REMOVE STAB BASE AND ASPH PAV (6"-20") | 7,459 SY | $8.00 | $17.50 | $9.85 | $70,861 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $1,670.00 | $6,620.00 | $11,585.04 | $69,300 |
| 341-7002 D-GR HMA TY-B SAC-B PG64-22 | 4,125 TON | $123.00 | $111.00 | $109.80 | -$49,500 |
| 260-7020 LIME TRT (SUBGRADE) (8") | 20,157 SY | $3.00 | $5.40 | $3.93 | $48,377 |
| 545-7018 CCA (INSTL)(N)(TL3)(WORK ZONE) | 6 EA | $8,661.00 | $2,360.00 | $7,875.52 | -$37,806 |
| 341-7050 D-GR HMA TY-D SAC-B PG70-22 | 3,622 TON | $132.00 | $122.00 | $116.75 | -$36,220 |
| 260-7005 LIME (COM OR QK)(SLURRY) | 400 TON | $314.00 | $395.00 | $295.18 | $32,400 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 3 EA | $3,511.00 | $13,800.00 | $9,253.78 | $30,867 |
| 662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD) | 47,949 LF | $1.00 | $0.4000 | $0.8371 | -$28,769 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 3,570 LF | $11.00 | $17.00 | $12.08 | $21,420 |
| 505-7003 TMA (MOBILE OPERATION) | 36 DAY | $587.00 | $10.00 | $229.60 | -$20,772 |
| 100-7002 PREPARING ROW | 28 STA | $1,160.00 | $430.00 | $6,072.92 | -$20,440 |
| 662-7068 WK ZN PAV MRK REMOV (W)6"(SLD) | 30,375 LF | $1.00 | $0.4000 | $0.8015 | -$18,225 |
| 467-7346 SET (TY II) (30 IN) (RCP) (4: 1) (C) | 9 EA | $4,514.00 | $2,810.00 | $3,015.98 | -$15,336 |
| 467-7345 SET (TY II) (30 IN) (RCP) (3: 1) (C) | 9 EA | $4,279.00 | $2,810.00 | $2,759.74 | -$13,221 |
| 354-7032 PLANE ASPH CONC PAV(0" TO 2") | 14,332 SY | $2.00 | $2.80 | $2.13 | $11,466 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 3,570 LF | $31.00 | $28.00 | $52.29 | -$10,710 |
Positive: the low bidder was cheaper on that item. These 20 items account for -$26,648 of the $3,958 gap.
J E CONSTRUCTION SERVICES, LLC: unbalanced items
Placed 1ANDERSON COLUMBIA CO., INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 105-7123 REMOVE STAB BASE AND ASPH PAV (6"-20") | 7,459 SY | $17.50 | $9.85 | 1.78x | $57,026 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 2,790 LF | $15.00 | $7.54 | 1.99x | $20,827 |
| 500-7001 MOBILIZATION | 1 LS | $236,600.00 | $523,850.32 | 0.45x | -$287,250 |
| 100-7002 PREPARING ROW | 28 STA | $430.00 | $6,072.92 | 0.07x | -$158,002 |
| 545-7018 CCA (INSTL)(N)(TL3)(WORK ZONE) | 6 EA | $2,360.00 | $7,875.52 | 0.30x | -$33,093 |
| 662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD) | 47,949 LF | $0.4000 | $0.8371 | 0.48x | -$20,959 |
CK NEWBERRY, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 3,570 LF | $35.00 | $12.08 | 2.90x | $81,812 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 5,427 CY | $26.00 | $13.19 | 1.97x | $69,510 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 2,790 LF | $17.00 | $7.54 | 2.26x | $26,407 |
| 100-7002 PREPARING ROW | 28 STA | $500.00 | $6,072.92 | 0.08x | -$156,042 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $4,000.00 | $11,585.04 | 0.35x | -$106,191 |
STX CIVIL: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7348 FL BS (CIP)(TY A GR 1-2 OR 5) FINAL POS | 5,473 CY | $135.76 | $77.43 | 1.75x | $319,264 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 3,570 LF | $92.58 | $52.29 | 1.77x | $143,840 |
| 505-7003 TMA (MOBILE OPERATION) | 36 DAY | $1,176.88 | $229.60 | 5.13x | $34,102 |
| 168-7001 VEGETATIVE WATERING | 521 TGL | $54.95 | $8.43 | 6.52x | $24,235 |
| 500-7001 MOBILIZATION | 1 LS | $246,612.00 | $523,850.32 | 0.47x | -$277,238 |
| 100-7002 PREPARING ROW | 28 STA | $697.50 | $6,072.92 | 0.11x | -$150,512 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $5,309.86 | $11,585.04 | 0.46x | -$87,853 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 3,570 LF | $5.07 | $12.08 | 0.42x | -$25,038 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 3 EA | $28,400.00 | $9,253.78 | 3.07x | $57,439 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 3,570 LF | $28.00 | $12.08 | 2.32x | $56,822 |
| 316-7212 AGGR (TY-PB, GR-4S OR 4)(SAC-B) | 305 CY | $220.00 | $125.13 | 1.76x | $28,936 |
| 505-7003 TMA (MOBILE OPERATION) | 36 DAY | $950.00 | $229.60 | 4.14x | $25,935 |
| 464-7007 RC PIPE (CL III)(30 IN) | 99 LF | $400.00 | $140.03 | 2.86x | $25,737 |
| 100-7002 PREPARING ROW | 28 STA | $969.00 | $6,072.92 | 0.16x | -$142,910 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $3,700.00 | $11,585.04 | 0.32x | -$110,391 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 3,570 LF | $26.00 | $52.29 | 0.50x | -$93,851 |