Bid Tab X-ray: 6499-13-001

Apr 21, 2026 · Lubbock Sign up free
Set your company to personalize scores

FY26 Lubbock LRA

6499-13-001 · let Apr 21, 2026 · Lubbock, Lubbock · Material Maintenance Project

$318,990Low bid: VULCAN CONSTRUCTION MATERIALS, LLC+2.9% vs estimate $310,000
$7,990Left on the table2.5% gap to the second bid
2BiddersSpread 3% low to high
4Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1VULCAN CONSTRUCTION MATERIALS, LLC $318,9902.9% $7,990 0 0
2MARTIN MARIETTA MATERIALS, INC. $326,980+2.5%5.5% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.

Where the job was won

VULCAN CONSTRUCTION MATERIALS, LLC vs MARTIN MARIETTA MATERIALS, INC., biggest item swings
ItemQtyLow2ndMarket2nd minus low
8001-7010 LRA (TY I GR AA) (DEL) (ST2)500 TON $156.85$162.08$124.75 $2,615
8001-7009 LRA (TY I GR AA) (DEL) (ST1)500 TON $158.14$162.50$112.79 $2,180
8001-7108 LRA (TY II GR DS) (DEL) (ST2)500 TON $160.85$164.48$141.87 $1,815
8001-7107 LRA (TY II GR DS) (DEL) (ST1)500 TON $162.14$164.90$125.06 $1,380

Positive: the low bidder was cheaper on that item. These 4 items account for $7,990 of the $7,990 gap.