REPLACE BRIDGE CR 305 @ ALKALI CRK TRIB
0908-23-058 · let Apr 8, 2026 · Fisher, Abilene · Bridge Replacement
$1,880,830Low bid: TUCAN CONTRACTING, LLC-25.0% vs estimate $2,507,178
$30,081Left on the table1.6% gap to the second bid
7BiddersSpread 33% low to high
120Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TUCAN CONTRACTING, LLC | $1,880,830 | -25.0% | $30,081 | 1+$11,426 | 5-$733,791 | |
| 2 | DELGADO'S CONTRACTORS, LLC | $1,910,911 | +1.6% | -23.8% | $5,009 | 5+$77,460 | 4-$698,148 |
| 3 | SKYLINE BRIDGE LLC | $1,915,919 | +1.9% | -23.6% | $92,280 | 7+$168,052 | 5-$710,676 |
| 4 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $2,008,199 | +6.8% | -19.9% | $219,976 | 1+$10,206 | 4-$625,748 |
| 5 | J. H. STRAIN & SONS, INC. | $2,228,175 | +18.5% | -11.1% | $190,018 | 3+$109,915 | 3-$498,172 |
| 6 | COPPELL CONSTRUCTION CO., INC. | $2,418,193 | +28.6% | -3.5% | $89,507 | ||
| 7 | ALTUS CONSTRUCTION LLC | $2,507,700 | +33.3% | 0.0% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
TUCAN CONTRACTING, LLC vs DELGADO'S CONTRACTORS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 450-7008 RAIL (TY T223) | 598 LF | $209.00 | $120.00 | $141.07 | -$53,222 |
| 425-7017 PRESTR CONC SLAB BEAM (5SB12) | 392.12 LF | $221.79 | $315.00 | $242.93 | $36,550 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $1,100.00 | $3,000.00 | $11,585.04 | $28,500 |
| 500-7001 MOBILIZATION | 1 LS | $150,000.00 | $125,000.00 | $523,850.32 | -$25,000 |
| 425-7019 PRESTR CONC SLAB BEAM (5SB15) | 247.5 LF | $221.79 | $315.00 | $261.75 | $23,069 |
| 100-7002 PREPARING ROW | 11.6 STA | $2,750.00 | $1,000.00 | $6,072.92 | -$20,300 |
| 416-7004 DRILL SHAFT (24 IN) | 474 LF | $247.50 | $280.00 | $234.98 | $15,405 |
| 247-7064 FL BS (CMP IN PLC)(TY A OR B GR 4)(6") | 2,892 SY | $27.50 | $22.50 | $16.67 | -$14,460 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $11,000.00 | $25,000.00 | $136,676.66 | $14,000 |
| 552-7003 WIRE FENCE (TY C) | 1,553 LF | $16.50 | $25.00 | $12.12 | $13,201 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 2 EA | $8,800.00 | $15,000.00 | $28,021.15 | $12,400 |
| 416-7005 DRILL SHAFT (30 IN) | 300 LF | $341.00 | $310.00 | $239.74 | -$9,300 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 1,661 LF | $3.30 | $8.50 | $3.92 | $8,637 |
| 420-7022 CL C CONC (CAP) | 36.8 CY | $1,540.00 | $1,350.00 | $1,543.38 | -$6,992 |
| 400-7010 CEM STABIL BKFL | 187 CY | $220.00 | $255.00 | $138.14 | $6,545 |
| 422-7007 REINF CONC SLAB (SLAB BEAM) | 3,380 SF | $23.10 | $25.00 | $23.90 | $6,422 |
| 420-7012 CL C CONC (ABUT) | 75.4 CY | $1,430.00 | $1,350.00 | $1,307.98 | -$6,032 |
| 316-7007 ASPH (AC-20-5TR) | 610 GAL | $22.00 | $30.00 | $3.27 | $4,880 |
| 422-7013 APPROACH SLAB | 49 CY | $935.00 | $1,000.00 | $738.51 | $3,185 |
| 420-7067 CL C CONC (MISC) | 15.2 CY | $1,100.00 | $1,300.00 | $1,569.38 | $3,040 |
Positive: the low bidder was cheaper on that item. These 20 items account for $40,528 of the $30,081 gap.
TUCAN CONTRACTING, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7007 ASPH (AC-20-5TR) | 610 GAL | $22.00 | $3.27 | 6.73x | $11,426 |
| 500-7001 MOBILIZATION | 1 LS | $150,000.00 | $523,850.32 | 0.29x | -$373,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $1,100.00 | $11,585.04 | 0.09x | -$157,276 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $11,000.00 | $136,676.66 | 0.08x | -$125,677 |
| 100-7002 PREPARING ROW | 11.6 STA | $2,750.00 | $6,072.92 | 0.45x | -$38,546 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 2 EA | $8,800.00 | $28,021.15 | 0.31x | -$38,442 |
DELGADO'S CONTRACTORS, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7010 CEM STABIL BKFL | 187 CY | $255.00 | $138.14 | 1.85x | $21,852 |
| 552-7003 WIRE FENCE (TY C) | 1,553 LF | $25.00 | $12.12 | 2.06x | $20,005 |
| 316-7007 ASPH (AC-20-5TR) | 610 GAL | $30.00 | $3.27 | 9.18x | $16,306 |
| 316-7208 AGGR (TY-PB, GR-3)(SAC-B) | 7 CY | $1,500.00 | $110.18 | 13.61x | $9,729 |
| 316-7211 AGGR (TY-PB, GR-4)(SAC-B) | 7 CY | $1,500.00 | $133.09 | 11.27x | $9,568 |
| 500-7001 MOBILIZATION | 1 LS | $125,000.00 | $523,850.32 | 0.24x | -$398,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $3,000.00 | $11,585.04 | 0.26x | -$128,776 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $25,000.00 | $136,676.66 | 0.18x | -$111,677 |
| 100-7002 PREPARING ROW | 11.6 STA | $1,000.00 | $6,072.92 | 0.16x | -$58,846 |
SKYLINE BRIDGE LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7064 FL BS (CMP IN PLC)(TY A OR B GR 4)(6") | 2,892 SY | $35.00 | $16.67 | 2.10x | $53,003 |
| 400-7010 CEM STABIL BKFL | 187 CY | $272.75 | $138.14 | 1.97x | $25,171 |
| 316-7007 ASPH (AC-20-5TR) | 610 GAL | $42.10 | $3.27 | 12.88x | $23,687 |
| 316-7208 AGGR (TY-PB, GR-3)(SAC-B) | 7 CY | $2,970.00 | $110.18 | 26.96x | $20,019 |
| 316-7211 AGGR (TY-PB, GR-4)(SAC-B) | 7 CY | $2,970.00 | $133.09 | 22.32x | $19,858 |
| 552-7010 WIRE FENCE (WATER GAP) | 165 LF | $150.00 | $49.94 | 3.00x | $16,511 |
| 164-7009 DRILL SEED (PERM_RURAL_SAND) | 2,220 SY | $4.60 | $0.1844 | 24.95x | $9,803 |
| 500-7001 MOBILIZATION | 1 LS | $150,000.00 | $523,850.32 | 0.29x | -$373,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $2,800.00 | $11,585.04 | 0.24x | -$131,776 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $19,915.00 | $136,676.66 | 0.15x | -$116,762 |
| 100-7002 PREPARING ROW | 11.6 STA | $1,500.00 | $6,072.92 | 0.25x | -$53,046 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 2 EA | $10,400.00 | $28,021.15 | 0.37x | -$35,242 |
HODGES AND SON CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7007 ASPH (AC-20-5TR) | 610 GAL | $20.00 | $3.27 | 6.12x | $10,206 |
| 500-7001 MOBILIZATION | 1 LS | $180,000.00 | $523,850.32 | 0.34x | -$343,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $2,000.00 | $11,585.04 | 0.17x | -$143,776 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $40,000.00 | $136,676.66 | 0.29x | -$96,677 |
| 100-7002 PREPARING ROW | 11.6 STA | $2,500.00 | $6,072.92 | 0.41x | -$41,446 |
J. H. STRAIN & SONS, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7064 FL BS (CMP IN PLC)(TY A OR B GR 4)(6") | 2,892 SY | $33.00 | $16.67 | 1.98x | $47,219 |
| 552-7003 WIRE FENCE (TY C) | 1,553 LF | $33.00 | $12.12 | 2.72x | $32,429 |
| 400-7010 CEM STABIL BKFL | 187 CY | $300.00 | $138.14 | 2.17x | $30,267 |
| 500-7001 MOBILIZATION | 1 LS | $177,500.00 | $523,850.32 | 0.34x | -$346,350 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $5,000.00 | $11,585.04 | 0.43x | -$98,776 |
| 100-7002 PREPARING ROW | 11.6 STA | $1,500.00 | $6,072.92 | 0.25x | -$53,046 |