Bid Tab X-ray: 0908-23-058

Apr 8, 2026 · Fisher Sign up free
Set your company to personalize scores

REPLACE BRIDGE CR 305 @ ALKALI CRK TRIB

0908-23-058 · let Apr 8, 2026 · Fisher, Abilene · Bridge Replacement

$1,880,830Low bid: TUCAN CONTRACTING, LLC-25.0% vs estimate $2,507,178
$30,081Left on the table1.6% gap to the second bid
7BiddersSpread 33% low to high
120Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1TUCAN CONTRACTING, LLC $1,880,830-25.0% $30,081 1+$11,426 5-$733,791
2DELGADO'S CONTRACTORS, LLC $1,910,911+1.6%-23.8% $5,009 5+$77,460 4-$698,148
3SKYLINE BRIDGE LLC $1,915,919+1.9%-23.6% $92,280 7+$168,052 5-$710,676
4HODGES AND SON CONSTRUCTION COMPANY, INC. $2,008,199+6.8%-19.9% $219,976 1+$10,206 4-$625,748
5J. H. STRAIN & SONS, INC. $2,228,175+18.5%-11.1% $190,018 3+$109,915 3-$498,172
6COPPELL CONSTRUCTION CO., INC. $2,418,193+28.6%-3.5% $89,507
7ALTUS CONSTRUCTION LLC $2,507,700+33.3%0.0%

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

TUCAN CONTRACTING, LLC vs DELGADO'S CONTRACTORS, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
450-7008 RAIL (TY T223)598 LF $209.00$120.00$141.07 -$53,222
425-7017 PRESTR CONC SLAB BEAM (5SB12)392.12 LF $221.79$315.00$242.93 $36,550
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING15 MO $1,100.00$3,000.00$11,585.04 $28,500
500-7001 MOBILIZATION1 LS $150,000.00$125,000.00$523,850.32 -$25,000
425-7019 PRESTR CONC SLAB BEAM (5SB15)247.5 LF $221.79$315.00$261.75 $23,069
100-7002 PREPARING ROW11.6 STA $2,750.00$1,000.00$6,072.92 -$20,300
416-7004 DRILL SHAFT (24 IN)474 LF $247.50$280.00$234.98 $15,405
247-7064 FL BS (CMP IN PLC)(TY A OR B GR 4)(6")2,892 SY $27.50$22.50$16.67 -$14,460
496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH)1 EA $11,000.00$25,000.00$136,676.66 $14,000
552-7003 WIRE FENCE (TY C)1,553 LF $16.50$25.00$12.12 $13,201
496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH)2 EA $8,800.00$15,000.00$28,021.15 $12,400
416-7005 DRILL SHAFT (30 IN)300 LF $341.00$310.00$239.74 -$9,300
506-7039 TEMP SEDMT CONT FENCE (INSTALL)1,661 LF $3.30$8.50$3.92 $8,637
420-7022 CL C CONC (CAP)36.8 CY $1,540.00$1,350.00$1,543.38 -$6,992
400-7010 CEM STABIL BKFL187 CY $220.00$255.00$138.14 $6,545
422-7007 REINF CONC SLAB (SLAB BEAM)3,380 SF $23.10$25.00$23.90 $6,422
420-7012 CL C CONC (ABUT)75.4 CY $1,430.00$1,350.00$1,307.98 -$6,032
316-7007 ASPH (AC-20-5TR)610 GAL $22.00$30.00$3.27 $4,880
422-7013 APPROACH SLAB49 CY $935.00$1,000.00$738.51 $3,185
420-7067 CL C CONC (MISC)15.2 CY $1,100.00$1,300.00$1,569.38 $3,040

Positive: the low bidder was cheaper on that item. These 20 items account for $40,528 of the $30,081 gap.

TUCAN CONTRACTING, LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
316-7007 ASPH (AC-20-5TR)610 GAL $22.00$3.276.73x$11,426
500-7001 MOBILIZATION1 LS $150,000.00$523,850.320.29x-$373,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING15 MO $1,100.00$11,585.040.09x-$157,276
496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH)1 EA $11,000.00$136,676.660.08x-$125,677
100-7002 PREPARING ROW11.6 STA $2,750.00$6,072.920.45x-$38,546
496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH)2 EA $8,800.00$28,021.150.31x-$38,442

DELGADO'S CONTRACTORS, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
400-7010 CEM STABIL BKFL187 CY $255.00$138.141.85x$21,852
552-7003 WIRE FENCE (TY C)1,553 LF $25.00$12.122.06x$20,005
316-7007 ASPH (AC-20-5TR)610 GAL $30.00$3.279.18x$16,306
316-7208 AGGR (TY-PB, GR-3)(SAC-B)7 CY $1,500.00$110.1813.61x$9,729
316-7211 AGGR (TY-PB, GR-4)(SAC-B)7 CY $1,500.00$133.0911.27x$9,568
500-7001 MOBILIZATION1 LS $125,000.00$523,850.320.24x-$398,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING15 MO $3,000.00$11,585.040.26x-$128,776
496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH)1 EA $25,000.00$136,676.660.18x-$111,677
100-7002 PREPARING ROW11.6 STA $1,000.00$6,072.920.16x-$58,846

SKYLINE BRIDGE LLC: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
247-7064 FL BS (CMP IN PLC)(TY A OR B GR 4)(6")2,892 SY $35.00$16.672.10x$53,003
400-7010 CEM STABIL BKFL187 CY $272.75$138.141.97x$25,171
316-7007 ASPH (AC-20-5TR)610 GAL $42.10$3.2712.88x$23,687
316-7208 AGGR (TY-PB, GR-3)(SAC-B)7 CY $2,970.00$110.1826.96x$20,019
316-7211 AGGR (TY-PB, GR-4)(SAC-B)7 CY $2,970.00$133.0922.32x$19,858
552-7010 WIRE FENCE (WATER GAP)165 LF $150.00$49.943.00x$16,511
164-7009 DRILL SEED (PERM_RURAL_SAND)2,220 SY $4.60$0.184424.95x$9,803
500-7001 MOBILIZATION1 LS $150,000.00$523,850.320.29x-$373,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING15 MO $2,800.00$11,585.040.24x-$131,776
496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH)1 EA $19,915.00$136,676.660.15x-$116,762
100-7002 PREPARING ROW11.6 STA $1,500.00$6,072.920.25x-$53,046
496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH)2 EA $10,400.00$28,021.150.37x-$35,242

HODGES AND SON CONSTRUCTION COMPANY, INC.: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
316-7007 ASPH (AC-20-5TR)610 GAL $20.00$3.276.12x$10,206
500-7001 MOBILIZATION1 LS $180,000.00$523,850.320.34x-$343,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING15 MO $2,000.00$11,585.040.17x-$143,776
496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH)1 EA $40,000.00$136,676.660.29x-$96,677
100-7002 PREPARING ROW11.6 STA $2,500.00$6,072.920.41x-$41,446

J. H. STRAIN & SONS, INC.: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
247-7064 FL BS (CMP IN PLC)(TY A OR B GR 4)(6")2,892 SY $33.00$16.671.98x$47,219
552-7003 WIRE FENCE (TY C)1,553 LF $33.00$12.122.72x$32,429
400-7010 CEM STABIL BKFL187 CY $300.00$138.142.17x$30,267
500-7001 MOBILIZATION1 LS $177,500.00$523,850.320.34x-$346,350
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING15 MO $5,000.00$11,585.040.43x-$98,776
100-7002 PREPARING ROW11.6 STA $1,500.00$6,072.920.25x-$53,046