CR 412 AT COTTONWOOD CRK TRIB
0908-23-045 · let Apr 7, 2026 · Fisher, Abilene · Bridge Replacement
$3,158,064Low bid: SKYLINE BRIDGE LLC-31.0% vs estimate $4,574,023
$469,313Left on the table14.9% gap to the second bid
6BiddersSpread 54% low to high
223Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SKYLINE BRIDGE LLC | $3,158,064 | -31.0% | $469,313 | 3+$100,556 | 4-$601,588 | |
| 2 | DELGADO'S CONTRACTORS, LLC | $3,627,377 | +14.9% | -20.7% | $202,733 | 2+$85,330 | 3-$551,138 |
| 3 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $3,830,110 | +21.3% | -16.3% | $57,111 | 2+$83,360 | 1-$103,021 |
| 4 | TUCAN CONTRACTING, LLC | $3,887,221 | +23.1% | -15.0% | $285,326 | 0 | 3-$303,142 |
| 5 | COPPELL CONSTRUCTION CO., INC. | $4,172,547 | +32.1% | -8.8% | $679,974 | 4+$165,687 | 1-$82,070 |
| 6 | ALTUS CONSTRUCTION LLC | $4,852,521 | +53.7% | 6.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
SKYLINE BRIDGE LLC vs DELGADO'S CONTRACTORS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 420-7012 CL C CONC (ABUT) | 210 CY | $950.00 | $1,500.00 | $1,307.98 | $115,500 |
| 416-7005 DRILL SHAFT (30 IN) | 966 LF | $175.00 | $250.00 | $239.74 | $72,450 |
| 432-7048 RIPRAP (STONE PROTECTION)(36 IN) | 755 CY | $182.00 | $275.00 | $174.48 | $70,215 |
| 450-7008 RAIL (TY T223) | 1,188 LF | $108.00 | $160.00 | $141.07 | $61,776 |
| 422-7001 REINF CONC SLAB | 12,006 SF | $22.00 | $27.00 | $24.45 | $60,030 |
| 425-7026 PRESTR CONC BOX BEAM (4B20) | 713.96 LF | $400.00 | $325.00 | $285.37 | -$53,547 |
| 425-7030 PRESTR CONC BOX BEAM (4B34) | 380 LF | $455.00 | $325.00 | $353.67 | -$49,400 |
| 416-7006 DRILL SHAFT (36 IN) | 123 LF | $200.00 | $600.00 | $280.58 | $49,200 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 6 EA | $12,360.00 | $20,500.00 | $28,021.15 | $48,840 |
| 500-7001 MOBILIZATION | 1 LS | $225,000.00 | $195,000.00 | $523,850.32 | -$30,000 |
| 432-7002 RIPRAP (CONC)(5 IN) | 150 CY | $500.00 | $695.00 | $585.15 | $29,250 |
| 110-7002 EXCAV (CHANNEL) | 2,386 CY | $14.00 | $25.00 | $16.69 | $26,246 |
| 423-7015 RETAINING WALL (SPREAD FOOTING) | 570 SF | $145.00 | $100.00 | $107.44 | -$25,650 |
| 432-7042 RIPRAP (STONE PROTECTION)(15 IN) | 555 CY | $170.00 | $215.00 | $248.94 | $24,975 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 3,452 LF | $3.25 | $8.00 | $3.92 | $16,397 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 200 CY | $170.00 | $250.00 | $184.74 | $16,000 |
| 416-7002 DRILL SHAFT (18 IN) | 214 LF | $100.00 | $170.00 | $161.72 | $14,980 |
| 247-7067 FL BS (CMP IN PLC)(TY A GR 1-2) (8") | 5,757 SY | $20.00 | $22.50 | $21.46 | $14,393 |
| 552-7001 WIRE FENCE (TY A) | 1,907 LF | $18.50 | $25.00 | $22.53 | $12,396 |
| 425-7031 PRESTR CONC BOX BEAM (5B34) | 190 LF | $377.25 | $325.00 | $345.03 | -$9,928 |
Positive: the low bidder was cheaper on that item. These 20 items account for $464,123 of the $469,313 gap.
SKYLINE BRIDGE LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7010 CEM STABIL BKFL | 394 CY | $265.00 | $138.14 | 1.92x | $49,981 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 2,656 CY | $30.00 | $16.96 | 1.77x | $34,625 |
| 552-7003 WIRE FENCE (TY C) | 1,170 LF | $25.75 | $12.12 | 2.12x | $15,949 |
| 500-7001 MOBILIZATION | 1 LS | $225,000.00 | $523,850.32 | 0.43x | -$298,850 |
| 100-7002 PREPARING ROW | 22.97 STA | $1,025.00 | $6,072.92 | 0.17x | -$115,951 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 6 EA | $12,360.00 | $28,021.15 | 0.44x | -$93,967 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $3,850.00 | $11,585.04 | 0.33x | -$92,821 |
DELGADO'S CONTRACTORS, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7010 CEM STABIL BKFL | 394 CY | $255.00 | $138.14 | 1.85x | $46,041 |
| 416-7006 DRILL SHAFT (36 IN) | 123 LF | $600.00 | $280.58 | 2.14x | $39,289 |
| 500-7001 MOBILIZATION | 1 LS | $195,000.00 | $523,850.32 | 0.37x | -$328,850 |
| 100-7002 PREPARING ROW | 22.97 STA | $750.00 | $6,072.92 | 0.12x | -$122,267 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $3,250.00 | $11,585.04 | 0.28x | -$100,021 |
HODGES AND SON CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 3TUCAN CONTRACTING, LLC: unbalanced items
Placed 4COPPELL CONSTRUCTION CO., INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7010 CEM STABIL BKFL | 394 CY | $275.00 | $138.14 | 1.99x | $53,921 |
| 416-7006 DRILL SHAFT (36 IN) | 123 LF | $670.00 | $280.58 | 2.39x | $47,899 |
| 454-7001 TYPE A JOINT | 316 LF | $200.00 | $64.16 | 3.12x | $42,925 |
| 403-7001 TEMPORARY SPL SHORING | 306 SF | $94.00 | $25.56 | 3.68x | $20,942 |
| 100-7002 PREPARING ROW | 22.97 STA | $2,500.00 | $6,072.92 | 0.41x | -$82,070 |