FM 2100: San Jacinto Canal to BU 90U
1062-04-063 · let Apr 7, 2026 · Harris, Houston · Overlay
$1,798,696Low bid: FORDE CONSTRUCTION COMPANY, INC.+13.9% vs estimate $1,578,950
$26,091Left on the table1.5% gap to the second bid
4BiddersSpread 8% low to high
69Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FORDE CONSTRUCTION COMPANY, INC. | $1,798,696 | 13.9% | $26,091 | 2+$150,299 | 1-$401,850 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $1,824,787 | +1.5% | 15.6% | $85,088 | 3+$136,206 | 1-$408,850 |
| 3 | ENVIRONMENTAL ALLIES, INC. | $1,909,875 | +6.2% | 21.0% | $38,684 | 4+$131,057 | 2-$445,174 |
| 4 | DURWOOD GREENE CONSTRUCTION CO. | $1,948,559 | +8.3% | 23.4% | 4+$317,892 | 2-$454,190 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
FORDE CONSTRUCTION COMPANY, INC. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 344-7064 SP MIXES SP-D SAC-A PG76-22 | 3,742 TON | $153.00 | $169.00 | $129.17 | $59,872 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $22,000.00 | $7,450.00 | $11,585.04 | -$58,200 |
| 3017-7001 CONTINUOUS GRINDING-CONCRETE PAVEMENT | 19,250 SY | $8.50 | $6.40 | $6.23 | -$40,425 |
| 351-7011 FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") | 1,766 SY | $110.00 | $132.00 | $98.88 | $38,852 |
| 354-7074 PLANE ASPH CONC PAV (1.5") | 45,357 SY | $3.75 | $3.00 | $1.35 | -$34,018 |
| 316-7245 AGGR (TY-PB OR PL, GR-4)(SAC-B) | 349 CY | $250.00 | $313.00 | $165.18 | $21,987 |
| 316-7067 ASPH (AC-20-5TR OR AC-20XP) | 16,328 GAL | $3.20 | $4.00 | $3.44 | $13,062 |
| 505-7001 TMA (STATIONARY) | 43 DAY | $200.00 | $450.00 | $217.57 | $10,750 |
| 500-7001 MOBILIZATION | 1 LS | $122,000.00 | $115,000.00 | $523,850.32 | -$7,000 |
| 361-7005 FULL - DEPTH REPAIR CRCP (10") | 17 CY | $1,250.00 | $1,635.00 | $1,202.68 | $6,545 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 4 EA | $3,800.00 | $2,350.00 | $3,190.07 | -$5,800 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 28 DAY | $250.00 | $50.00 | $87.82 | -$5,600 |
| 6006-7001 VIVDS PROSR SYS | 3 EA | $12,200.00 | $14,000.00 | $11,799.49 | $5,400 |
| 6006-7002 VIVDS CAM ASSY FXD LNS | 12 EA | $2,290.00 | $2,665.00 | $4,074.68 | $4,500 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 27 CY | $900.00 | $1,050.00 | $616.83 | $4,050 |
| 505-7003 TMA (MOBILE OPERATION) | 9 DAY | $200.00 | $650.00 | $229.60 | $4,050 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 2,544 EA | $2.10 | $0.5500 | $0.5715 | -$3,943 |
| 540-7018 MTL W - BEAM GD FEN (LOW FILL CULVERT) | 25 LF | $117.00 | $265.00 | $90.29 | $3,700 |
| 6006-7007 VIVDS CABLING | 2,220 LF | $3.80 | $2.35 | $2.85 | -$3,219 |
| 686-7004 INS TRF SIG PL AM (S)LUM ARM(10') | 4 EA | $1,700.00 | $2,400.00 | $1,070.00 | $2,800 |
Positive: the low bidder was cheaper on that item. These 20 items account for $17,363 of the $26,091 gap.
FORDE CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 1TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 354-7074 PLANE ASPH CONC PAV (1.5") | 45,357 SY | $3.00 | $1.35 | 2.21x | $74,621 |
| 316-7245 AGGR (TY-PB OR PL, GR-4)(SAC-B) | 349 CY | $313.00 | $165.18 | 1.89x | $51,590 |
| 505-7001 TMA (STATIONARY) | 43 DAY | $450.00 | $217.57 | 2.07x | $9,994 |
| 500-7001 MOBILIZATION | 1 LS | $115,000.00 | $523,850.32 | 0.22x | -$408,850 |
ENVIRONMENTAL ALLIES, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 354-7074 PLANE ASPH CONC PAV (1.5") | 45,357 SY | $2.50 | $1.35 | 1.85x | $51,943 |
| 316-7245 AGGR (TY-PB OR PL, GR-4)(SAC-B) | 349 CY | $290.00 | $165.18 | 1.76x | $43,563 |
| 662-7051 WK ZN PAV MRK REMOV (REFL) TY II-A-A | 8,906 EA | $6.60 | $3.75 | 1.76x | $25,349 |
| 662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) | 27,350 LF | $0.6500 | $0.2770 | 2.35x | $10,202 |
| 500-7001 MOBILIZATION | 1 LS | $102,000.00 | $523,850.32 | 0.19x | -$421,850 |
| 6006-7001 VIVDS PROSR SYS | 3 EA | $4,025.00 | $11,799.49 | 0.34x | -$23,323 |
DURWOOD GREENE CONSTRUCTION CO.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 3017-7001 CONTINUOUS GRINDING-CONCRETE PAVEMENT | 19,250 SY | $13.57 | $6.23 | 2.18x | $141,305 |
| 354-7074 PLANE ASPH CONC PAV (1.5") | 45,357 SY | $4.00 | $1.35 | 2.95x | $119,978 |
| 316-7245 AGGR (TY-PB OR PL, GR-4)(SAC-B) | 349 CY | $290.00 | $165.18 | 1.76x | $43,563 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 27 CY | $1,100.00 | $616.83 | 1.78x | $13,046 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $4,000.00 | $11,585.04 | 0.35x | -$30,340 |