LA PALOMA RD AT GALLINA SLOUGH
0922-48-004 · let Apr 7, 2026 · Zavala, Laredo · Bridge Replacement
$1,523,016Low bid: ACEE CONSTRUCTION LLC.-6.7% vs estimate $1,631,537
$68,641Left on the table4.5% gap to the second bid
5BiddersSpread 64% low to high
126Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ACEE CONSTRUCTION LLC. | $1,523,016 | -6.7% | $68,641 | 5+$77,763 | 4-$475,212 | |
| 2 | PRESIDIO CONTRACTING, LLC | $1,591,656 | +4.5% | -2.4% | $233,279 | 7+$124,799 | 3-$439,802 |
| 3 | J. CARROLL WEAVER, INC. | $1,824,936 | +19.8% | 11.9% | $32,231 | 7+$396,555 | 3-$451,479 |
| 4 | ACME BRIDGE COMPANY, INC. | $1,857,167 | +21.9% | 13.8% | $634,158 | 8+$325,821 | 4-$465,258 |
| 5 | CK NEWBERRY, LLC | $2,491,325 | +63.6% | 52.7% | 17+$775,025 | 1-$298,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ACEE CONSTRUCTION LLC. vs PRESIDIO CONTRACTING, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 4066-7001 PRECAST C-SPAN CULVERTS | 34 LF | $3,350.00 | $5,400.00 | $3,350.00 | $69,700 |
| 100-7002 PREPARING ROW | 7 STA | $2,250.00 | $9,615.00 | $6,072.92 | $51,555 |
| 420-7012 CL C CONC (ABUT) | 105.6 CY | $1,461.85 | $1,060.00 | $1,307.98 | -$42,435 |
| 330-7002 LRA PAV TY-I GR-A | 96 TON | $210.00 | $475.00 | $210.00 | $25,440 |
| 508-7004 CONSTRUCTING DETOURS (TY2) | 949 SY | $70.00 | $44.25 | $84.71 | -$24,437 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $12,500.00 | $6,500.00 | $9,253.78 | -$24,000 |
| 425-7019 PRESTR CONC SLAB BEAM (5SB15) | 197.5 LF | $429.05 | $322.00 | $261.75 | -$21,142 |
| 552-7003 WIRE FENCE (TY C) | 520 LF | $58.80 | $30.00 | $12.12 | -$14,976 |
| 341-7031 D-GR HMA TY-C SAC-A PG76-22 | 222.3 TON | $250.00 | $310.00 | $122.50 | $13,338 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $12,500.00 | $25,750.00 | $28,021.15 | $13,250 |
| 510-7003 ONE-WAY TRAF CONT (PORT TRAF SIG) | 5 MO | $7,644.00 | $5,140.00 | $4,980.23 | -$12,520 |
| 416-7004 DRILL SHAFT (24 IN) | 742 LF | $285.00 | $301.10 | $234.98 | $11,946 |
| 496-7007 REMOV STR (PIPE) | 216 LF | $17.35 | $72.00 | $23.96 | $11,804 |
| 110-7001 EXCAV (ROADWAY) | 341.996 CY | $25.00 | $58.15 | $11.68 | $11,337 |
| 110-7002 EXCAV (CHANNEL) | 310.4 CY | $25.00 | $59.60 | $16.69 | $10,740 |
| 422-7013 APPROACH SLAB | 38.5 CY | $1,195.80 | $932.00 | $738.51 | -$10,156 |
| 529-7004 CONC CURB (TY III) | 36 LF | $13.50 | $265.00 | $20.77 | $9,054 |
| 403-7001 TEMPORARY SPL SHORING | 600 SF | $18.00 | $7.00 | $25.56 | -$6,600 |
| 552-7010 WIRE FENCE (WATER GAP) | 40 LF | $269.50 | $105.00 | $49.94 | -$6,580 |
| 662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD) | 6,000 LF | $1.95 | $0.9000 | $0.8371 | -$6,300 |
Positive: the low bidder was cheaper on that item. These 20 items account for $59,018 of the $68,641 gap.
ACEE CONSTRUCTION LLC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7031 D-GR HMA TY-C SAC-A PG76-22 | 222.3 TON | $250.00 | $122.50 | 2.04x | $28,344 |
| 552-7003 WIRE FENCE (TY C) | 520 LF | $58.80 | $12.12 | 4.85x | $24,274 |
| 552-7010 WIRE FENCE (WATER GAP) | 40 LF | $269.50 | $49.94 | 5.40x | $8,783 |
| 666-7305 TY I HIGH PERF PM (Y)6"(SLD)(100MIL) | 2,000 LF | $4.75 | $0.5714 | 8.31x | $8,357 |
| 510-7001 ONE-WAY TRAF CONT (FLAGGER CONT) | 80 HR | $147.00 | $46.94 | 3.13x | $8,005 |
| 500-7001 MOBILIZATION | 1 LS | $152,000.00 | $523,850.32 | 0.29x | -$371,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $3,950.00 | $11,585.04 | 0.34x | -$61,080 |
| 100-7002 PREPARING ROW | 7 STA | $2,250.00 | $6,072.92 | 0.37x | -$26,760 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $12,500.00 | $28,021.15 | 0.45x | -$15,521 |
PRESIDIO CONTRACTING, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7031 D-GR HMA TY-C SAC-A PG76-22 | 222.3 TON | $310.00 | $122.50 | 2.53x | $41,682 |
| 330-7002 LRA PAV TY-I GR-A | 96 TON | $475.00 | $210.00 | 2.26x | $25,440 |
| 110-7001 EXCAV (ROADWAY) | 341.996 CY | $58.15 | $11.68 | 4.98x | $15,892 |
| 110-7002 EXCAV (CHANNEL) | 310.4 CY | $59.60 | $16.69 | 3.57x | $13,318 |
| 496-7007 REMOV STR (PIPE) | 216 LF | $72.00 | $23.96 | 3.00x | $10,376 |
| 552-7003 WIRE FENCE (TY C) | 520 LF | $30.00 | $12.12 | 2.48x | $9,298 |
| 529-7004 CONC CURB (TY III) | 36 LF | $265.00 | $20.77 | 12.76x | $8,792 |
| 500-7001 MOBILIZATION | 1 LS | $154,785.00 | $523,850.32 | 0.30x | -$369,065 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $4,135.00 | $11,585.04 | 0.36x | -$59,600 |
| 403-7001 TEMPORARY SPL SHORING | 600 SF | $7.00 | $25.56 | 0.27x | -$11,136 |
J. CARROLL WEAVER, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 416-7004 DRILL SHAFT (24 IN) | 742 LF | $428.82 | $234.98 | 1.82x | $143,832 |
| 4066-7001 PRECAST C-SPAN CULVERTS | 34 LF | $6,262.71 | $3,350.00 | 1.87x | $99,032 |
| 341-7031 D-GR HMA TY-C SAC-A PG76-22 | 222.3 TON | $366.75 | $122.50 | 2.99x | $54,298 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $73,514.57 | $28,021.15 | 2.62x | $45,493 |
| 422-7007 REINF CONC SLAB (SLAB BEAM) | 1,040 SF | $54.90 | $23.90 | 2.30x | $32,236 |
| 552-7010 WIRE FENCE (WATER GAP) | 40 LF | $333.00 | $49.94 | 6.67x | $11,323 |
| 110-7001 EXCAV (ROADWAY) | 341.996 CY | $41.92 | $11.68 | 3.59x | $10,341 |
| 500-7001 MOBILIZATION | 1 LS | $173,033.85 | $523,850.32 | 0.33x | -$350,816 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $2,775.00 | $11,585.04 | 0.24x | -$70,480 |
| 100-7002 PREPARING ROW | 7 STA | $1,761.13 | $6,072.92 | 0.29x | -$30,183 |
ACME BRIDGE COMPANY, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 4066-7001 PRECAST C-SPAN CULVERTS | 34 LF | $8,000.00 | $3,350.00 | 2.39x | $158,100 |
| 341-7031 D-GR HMA TY-C SAC-A PG76-22 | 222.3 TON | $298.00 | $122.50 | 2.43x | $39,015 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $18,000.00 | $9,253.78 | 1.95x | $34,985 |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 98 CY | $500.00 | $179.97 | 2.78x | $31,363 |
| 330-7002 LRA PAV TY-I GR-A | 96 TON | $459.00 | $210.00 | 2.19x | $23,904 |
| 132-7001 EMBANK (FNL)(OC)(TY A) | 484.403 CY | $60.00 | $22.62 | 2.65x | $18,108 |
| 110-7001 EXCAV (ROADWAY) | 341.996 CY | $44.00 | $11.68 | 3.77x | $11,053 |
| 512-7057 PORT CTB (REMOVE)(LOW PROF)(TY 1) | 360 LF | $37.00 | $11.18 | 3.31x | $9,294 |
| 500-7001 MOBILIZATION | 1 LS | $168,000.00 | $523,850.32 | 0.32x | -$355,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $2,000.00 | $11,585.04 | 0.17x | -$76,680 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $10,000.00 | $28,021.15 | 0.36x | -$18,021 |
| 403-7001 TEMPORARY SPL SHORING | 600 SF | $1.05 | $25.56 | 0.04x | -$14,706 |
CK NEWBERRY, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 416-7004 DRILL SHAFT (24 IN) | 742 LF | $500.00 | $234.98 | 2.13x | $196,648 |
| 4066-7001 PRECAST C-SPAN CULVERTS | 34 LF | $8,750.00 | $3,350.00 | 2.61x | $183,600 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $75,000.00 | $28,021.15 | 2.68x | $46,979 |
| 341-7031 D-GR HMA TY-C SAC-A PG76-22 | 222.3 TON | $300.00 | $122.50 | 2.45x | $39,459 |
| 110-7001 EXCAV (ROADWAY) | 341.996 CY | $125.00 | $11.68 | 10.70x | $38,754 |
| 247-7176 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) | 337 CY | $200.00 | $88.59 | 2.26x | $37,544 |
| 422-7007 REINF CONC SLAB (SLAB BEAM) | 1,040 SF | $60.00 | $23.90 | 2.51x | $37,540 |
| 422-7013 APPROACH SLAB | 38.5 CY | $1,500.00 | $738.51 | 2.03x | $29,318 |
| 110-7002 EXCAV (CHANNEL) | 310.4 CY | $100.00 | $16.69 | 5.99x | $25,858 |
| 510-7003 ONE-WAY TRAF CONT (PORT TRAF SIG) | 5 MO | $10,000.00 | $4,980.23 | 2.01x | $25,099 |
| 500-7001 MOBILIZATION | 1 LS | $225,000.00 | $523,850.32 | 0.43x | -$298,850 |