SH 304 from Bastrop CL to 3.2 mi S of CL
0573-02-008 · let Sep 3, 2026 · Caldwell, Austin · Intersection & Operational Imprv
$5,111,478Low bid: HUNTER INDUSTRIES, LTD.-5.9% vs estimate $5,431,676
$370,395Left on the table7.2% gap to the second bid
8BiddersSpread 50% low to high
97Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HUNTER INDUSTRIES, LTD. | $5,111,478 | -5.9% | $370,395 | 0 | 1-$960,667 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $5,481,873 | +7.2% | 0.9% | $192,599 | 0 | 2-$1,012,739 |
| 3 | D&S CONCRETE CONTRACTORS LLC | $5,674,473 | +11.0% | 4.5% | $795,133 | 3+$333,657 | 5-$1,747,453 |
| 4 | JOE BLAND CONSTRUCTION LLC | $6,469,606 | +26.6% | 19.1% | $317,025 | 2+$307,786 | 2-$1,005,775 |
| 5 | AARON CONCRETE CONTRACTORS, LLC | $6,786,631 | +32.8% | 24.9% | $44,938 | 4+$249,764 | 3-$1,381,709 |
| 6 | DAN WILLIAMS COMPANY | $6,831,569 | +33.7% | 25.8% | $230,150 | ||
| 7 | STX CIVIL | $7,061,719 | +38.2% | 30.0% | $583,196 | ||
| 8 | CLARK CONSTRUCTION OF TEXAS, INC. | $7,644,915 | +49.6% | 40.7% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
HUNTER INDUSTRIES, LTD. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 247-7191 FL BS (CMP IN PLC)(TY D GR 5)(FNAL POS) | 13,819 CY | $59.83 | $74.00 | $62.11 | $195,815 |
| 500-7001 MOBILIZATION | 1 LS | $396,332.30 | $500,000.00 | $523,850.32 | $103,668 |
| 347-7002 TOM-C PG76-22 SAC-B | 4,863 TON | $116.71 | $97.00 | $130.62 | -$95,850 |
| 341-7056 D-GR HMA TY-D PG76-22 | 7,597 TON | $93.61 | $105.00 | $123.11 | $86,530 |
| 432-7002 RIPRAP (CONC)(5 IN) | 82 CY | $997.59 | $397.00 | $585.15 | -$49,248 |
| 467-7418 SET (TY II) (DES 1) (RCP) (6: 1) (P) | 50 EA | $1,260.11 | $2,240.00 | $1,799.60 | $48,995 |
| 530-7010 DRIVEWAYS (ACP) | 3,612 SY | $40.98 | $53.75 | $54.96 | $46,125 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 69,282 SY | $0.8700 | $1.25 | $1.43 | $26,327 |
| 168-7001 VEGETATIVE WATERING | 1,164 TGL | $22.75 | $2.00 | $8.43 | -$24,153 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $7,978.27 | $5,150.00 | $11,585.04 | -$22,626 |
| 464-7040 RC PIPE (ARCH)(CL III)(DES 1) | 688 LF | $236.27 | $203.50 | $201.47 | -$22,546 |
| 110-7001 EXCAV (ROADWAY) | 14,690 CY | $13.11 | $14.50 | $11.68 | $20,419 |
| 341-7030 D-GR HMA TY-C PG76-22 | 5,135 TON | $93.61 | $97.40 | $93.60 | $19,462 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 16 EA | $945.08 | $1,960.00 | $1,176.76 | $16,239 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 46 CY | $945.08 | $605.00 | $616.83 | -$15,644 |
| 105-7053 RMV (2"-8") TRT/UNTRT BASE & ASPH PAV | 12,084 SY | $3.00 | $4.25 | $3.40 | $15,105 |
| 530-7006 DRIVEWAYS (CONC) | 126 SY | $240.77 | $121.00 | $109.20 | -$15,091 |
| 467-7390 SET (TY II) (48 IN) (RCP) (4: 1) (C) | 2 EA | $6,300.55 | $13,400.00 | $9,736.49 | $14,199 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 9,687 CY | $13.11 | $14.50 | $16.96 | $13,465 |
| 496-7038 REMOVE STR (DRIVEWAY CULVERT) | 29 EA | $997.59 | $550.00 | $799.87 | -$12,980 |
Positive: the low bidder was cheaper on that item. These 20 items account for $348,210 of the $370,395 gap.
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 169 STA | $388.50 | $6,072.92 | 0.06x | -$960,667 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 2D&S CONCRETE CONTRACTORS LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7001 EXCAV (ROADWAY) | 14,690 CY | $24.00 | $11.68 | 2.05x | $180,948 |
| 467-7418 SET (TY II) (DES 1) (RCP) (6: 1) (P) | 50 EA | $3,500.00 | $1,799.60 | 1.94x | $85,020 |
| 105-7053 RMV (2"-8") TRT/UNTRT BASE & ASPH PAV | 12,084 SY | $9.00 | $3.40 | 2.65x | $67,689 |
| 100-7002 PREPARING ROW | 169 STA | $500.00 | $6,072.92 | 0.08x | -$941,824 |
| 247-7191 FL BS (CMP IN PLC)(TY D GR 5)(FNAL POS) | 13,819 CY | $27.00 | $62.11 | 0.43x | -$485,242 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 4,129 SY | $1.50 | $49.06 | 0.03x | -$196,395 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 69,282 SY | $0.4000 | $1.43 | 0.28x | -$71,312 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $5,000.00 | $11,585.04 | 0.43x | -$52,680 |
JOE BLAND CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 467-7418 SET (TY II) (DES 1) (RCP) (6: 1) (P) | 50 EA | $7,250.00 | $1,799.60 | 4.03x | $272,520 |
| 467-7434 SET (TY II) (DES 3) (RCP) (6: 1) (P) | 8 EA | $8,500.00 | $4,091.82 | 2.08x | $35,265 |
| 100-7002 PREPARING ROW | 169 STA | $750.00 | $6,072.92 | 0.12x | -$899,574 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 9,687 CY | $6.00 | $16.96 | 0.35x | -$106,201 |
AARON CONCRETE CONTRACTORS, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 160-7002 FURN & PLACE TOPSOIL (4") | 69,282 SY | $3.00 | $1.43 | 2.10x | $108,821 |
| 168-7001 VEGETATIVE WATERING | 1,164 TGL | $57.00 | $8.43 | 6.76x | $56,531 |
| 105-7053 RMV (2"-8") TRT/UNTRT BASE & ASPH PAV | 12,084 SY | $7.50 | $3.40 | 2.21x | $49,563 |
| 400-7010 CEM STABIL BKFL | 117 CY | $436.00 | $138.14 | 3.16x | $34,849 |
| 100-7002 PREPARING ROW | 169 STA | $229.00 | $6,072.92 | 0.04x | -$987,623 |
| 500-7001 MOBILIZATION | 1 LS | $200,332.00 | $523,850.32 | 0.38x | -$323,518 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $2,764.00 | $11,585.04 | 0.24x | -$70,568 |