IH 37: 0073-08-183; FOI
0073-08-183 · let May 6, 2026 · Bexar, San Antonio · Freeway Operational Improvements
$33,122,615Low bid: HUNTER INDUSTRIES, LTD.-3.5% vs estimate $34,315,721
$279,813Left on the table0.8% gap to the second bid
5BiddersSpread 6% low to high
385Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HUNTER INDUSTRIES, LTD. | $33,122,615 | -3.5% | $279,813 | 4+$3,159,791 | 2-$821,069 | |
| 2 | JORDAN FOSTER CONSTRUCTION, LLC | $33,402,427 | +0.8% | -2.7% | $913,249 | 7+$4,323,650 | 1-$275,689 |
| 3 | CAPITAL EXCAVATION COMPANY | $34,315,676 | +3.6% | 0.0% | $101,833 | 6+$4,188,233 | 3-$1,089,203 |
| 4 | URBAN INFRACONSTRUCTION LLC | $34,417,509 | +3.9% | 0.3% | $793,888 | 5+$3,637,790 | 0 |
| 5 | J3 COMPANY, LLC | $35,211,397 | +6.3% | 2.6% | 6+$4,524,179 | 1-$316,823 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
HUNTER INDUSTRIES, LTD. vs JORDAN FOSTER CONSTRUCTION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,749,227.15 | $3,306,840.41 | $523,850.32 | $557,613 |
| 403-7001 TEMPORARY SPL SHORING | 21,393 SF | $1.99 | $28.00 | $25.56 | $556,432 |
| 346-7001 STONE-MTRX-ASPH SMA-C SAC-A PG76-22 | 15,182 TON | $169.40 | $136.00 | $156.93 | -$507,079 |
| 341-7001 D-GR HMA TY-B PG64-22 | 21,800 TON | $101.20 | $83.00 | $97.82 | -$396,760 |
| 100-7002 PREPARING ROW | 112 STA | $4,070.00 | $7,455.89 | $6,072.92 | $379,220 |
| 423-7001 RETAINING WALL (MSE) | 31,007 SF | $53.50 | $65.00 | $74.07 | $356,581 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 27 MO | $8,382.88 | $20,500.00 | $11,585.04 | $327,162 |
| 420-7057 CL C CONC (SIGN COLUMN) | 467 CY | $1,800.00 | $1,350.00 | $1,584.19 | -$210,150 |
| 169-7010 SOIL RET BLKT(SL_MOD_CLAY_LONG_ROLL) | 149,838 SY | $2.75 | $1.50 | $2.71 | -$187,298 |
| 105-7018 RMV (18"-22") TRT/UNTRT BASE & ASPH PAV | 19,952 SY | $14.55 | $7.00 | $9.31 | -$150,638 |
| 505-7001 TMA (STATIONARY) | 710 DAY | $150.00 | $360.00 | $217.57 | $149,100 |
| 735-7001 DEBRIS REMOV-CNTR MED/MN LNS/RAMPS | 54 MI | $589.34 | $3,250.00 | $84.84 | $143,676 |
| 132-7039 EMBANK (FNL)(OC)(TY C2)(DS) | 7,348 CY | $65.12 | $46.00 | $44.90 | -$140,494 |
| 247-7192 FL BS(CIP)(TY D, GR 1-2 OR 5)(FNAL POS) | 8,341 CY | $68.84 | $85.00 | $41.72 | $134,791 |
| 344-7031 SP MIXES SP-C SAC-B PG76-22 | 9,610 TON | $113.30 | $100.00 | $97.84 | -$127,813 |
| 556-7008 PIPE UNDERDRAINS (TY 8) (6") | 6,448 LF | $41.51 | $22.00 | $32.77 | -$125,800 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 11,610 LF | $25.00 | $35.00 | $52.29 | $116,100 |
| 132-7009 EMBANK (FNL)(OC)(TY C2) | 13,729 CY | $37.02 | $29.00 | $8.97 | -$110,107 |
| 104-7008 REMOV CONC (MEDIANS) | 5,783 SY | $23.10 | $6.00 | $22.02 | -$98,889 |
| 618-7038 CONDT (PVC) (SCH 40) (3") (CONC ENCSE) | 15,330 LF | $21.00 | $15.00 | $14.52 | -$91,980 |
Positive: the low bidder was cheaper on that item. These 20 items account for $573,667 of the $279,813 gap.
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,749,227.15 | $523,850.32 | 5.25x | $2,225,377 |
| 132-7009 EMBANK (FNL)(OC)(TY C2) | 13,729 CY | $37.02 | $8.97 | 4.13x | $385,100 |
| 110-7001 EXCAV (ROADWAY) | 28,142 CY | $24.20 | $11.68 | 2.07x | $352,276 |
| 451-7024 RETROFIT RAIL (TY SSTR) | 1,126 LF | $350.00 | $175.01 | 2.00x | $197,038 |
| 403-7001 TEMPORARY SPL SHORING | 21,393 SF | $1.99 | $25.56 | 0.08x | -$504,246 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 11,610 LF | $25.00 | $52.29 | 0.48x | -$316,823 |
JORDAN FOSTER CONSTRUCTION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,306,840.41 | $523,850.32 | 6.31x | $2,782,990 |
| 247-7192 FL BS(CIP)(TY D, GR 1-2 OR 5)(FNAL POS) | 8,341 CY | $85.00 | $41.72 | 2.04x | $361,004 |
| 132-7009 EMBANK (FNL)(OC)(TY C2) | 13,729 CY | $29.00 | $8.97 | 3.23x | $274,993 |
| 110-7001 EXCAV (ROADWAY) | 28,142 CY | $21.00 | $11.68 | 1.80x | $262,222 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 27 MO | $20,500.00 | $11,585.04 | 1.77x | $240,704 |
| 451-7024 RETROFIT RAIL (TY SSTR) | 1,126 LF | $380.00 | $175.01 | 2.17x | $230,818 |
| 735-7001 DEBRIS REMOV-CNTR MED/MN LNS/RAMPS | 54 MI | $3,250.00 | $84.84 | 38.31x | $170,918 |
| 681-7001 TEMP TRAF SIGNALS | 8 EA | $28,000.00 | $62,461.14 | 0.45x | -$275,689 |
CAPITAL EXCAVATION COMPANY: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,775,000.00 | $523,850.32 | 5.30x | $2,251,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 27 MO | $38,000.00 | $11,585.04 | 3.28x | $713,204 |
| 132-7039 EMBANK (FNL)(OC)(TY C2)(DS) | 7,348 CY | $130.00 | $44.90 | 2.90x | $625,292 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 11,610 LF | $31.00 | $12.08 | 2.57x | $219,622 |
| 132-7009 EMBANK (FNL)(OC)(TY C2) | 13,729 CY | $23.00 | $8.97 | 2.56x | $192,619 |
| 132-7008 EMBANK (FNL)(DC)(TY C1) | 5,090 CY | $54.00 | $17.39 | 3.11x | $186,346 |
| 403-7001 TEMPORARY SPL SHORING | 21,393 SF | $1.70 | $25.56 | 0.07x | -$510,450 |
| 100-7002 PREPARING ROW | 112 STA | $2,800.00 | $6,072.92 | 0.46x | -$366,567 |
| 169-7010 SOIL RET BLKT(SL_MOD_CLAY_LONG_ROLL) | 149,838 SY | $1.29 | $2.71 | 0.48x | -$212,186 |
URBAN INFRACONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,578,955.00 | $523,850.32 | 4.92x | $2,055,105 |
| 132-7009 EMBANK (FNL)(OC)(TY C2) | 13,729 CY | $45.00 | $8.97 | 5.02x | $494,657 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 27 MO | $29,387.95 | $11,585.04 | 2.54x | $480,679 |
| 529-7001 CONC CURB (TY I) | 12,202 LF | $44.62 | $13.68 | 3.26x | $377,538 |
| 505-7001 TMA (STATIONARY) | 710 DAY | $541.25 | $217.57 | 2.49x | $229,812 |
J3 COMPANY, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,000,000.00 | $523,850.32 | 5.73x | $2,476,150 |
| 110-7001 EXCAV (ROADWAY) | 28,142 CY | $30.00 | $11.68 | 2.57x | $515,500 |
| 132-7039 EMBANK (FNL)(OC)(TY C2)(DS) | 7,348 CY | $115.00 | $44.90 | 2.56x | $515,072 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 27 MO | $28,000.00 | $11,585.04 | 2.42x | $443,204 |
| 132-7009 EMBANK (FNL)(OC)(TY C2) | 13,729 CY | $35.00 | $8.97 | 3.90x | $357,367 |
| 132-7008 EMBANK (FNL)(DC)(TY C1) | 5,090 CY | $60.00 | $17.39 | 3.45x | $216,886 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 11,610 LF | $25.00 | $52.29 | 0.48x | -$316,823 |