Bid Tab X-ray: 0073-08-183

May 6, 2026 · Bexar Sign up free
Set your company to personalize scores

IH 37: 0073-08-183; FOI

0073-08-183 · let May 6, 2026 · Bexar, San Antonio · Freeway Operational Improvements

$33,122,615Low bid: HUNTER INDUSTRIES, LTD.-3.5% vs estimate $34,315,721
$279,813Left on the table0.8% gap to the second bid
5BiddersSpread 6% low to high
385Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1HUNTER INDUSTRIES, LTD. $33,122,615-3.5% $279,813 4+$3,159,791 2-$821,069
2JORDAN FOSTER CONSTRUCTION, LLC $33,402,427+0.8%-2.7% $913,249 7+$4,323,650 1-$275,689
3CAPITAL EXCAVATION COMPANY $34,315,676+3.6%0.0% $101,833 6+$4,188,233 3-$1,089,203
4URBAN INFRACONSTRUCTION LLC $34,417,509+3.9%0.3% $793,888 5+$3,637,790 0
5J3 COMPANY, LLC $35,211,397+6.3%2.6% 6+$4,524,179 1-$316,823

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

HUNTER INDUSTRIES, LTD. vs JORDAN FOSTER CONSTRUCTION, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
500-7001 MOBILIZATION1 LS $2,749,227.15$3,306,840.41$523,850.32 $557,613
403-7001 TEMPORARY SPL SHORING21,393 SF $1.99$28.00$25.56 $556,432
346-7001 STONE-MTRX-ASPH SMA-C SAC-A PG76-2215,182 TON $169.40$136.00$156.93 -$507,079
341-7001 D-GR HMA TY-B PG64-2221,800 TON $101.20$83.00$97.82 -$396,760
100-7002 PREPARING ROW112 STA $4,070.00$7,455.89$6,072.92 $379,220
423-7001 RETAINING WALL (MSE)31,007 SF $53.50$65.00$74.07 $356,581
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING27 MO $8,382.88$20,500.00$11,585.04 $327,162
420-7057 CL C CONC (SIGN COLUMN)467 CY $1,800.00$1,350.00$1,584.19 -$210,150
169-7010 SOIL RET BLKT(SL_MOD_CLAY_LONG_ROLL)149,838 SY $2.75$1.50$2.71 -$187,298
105-7018 RMV (18"-22") TRT/UNTRT BASE & ASPH PAV19,952 SY $14.55$7.00$9.31 -$150,638
505-7001 TMA (STATIONARY)710 DAY $150.00$360.00$217.57 $149,100
735-7001 DEBRIS REMOV-CNTR MED/MN LNS/RAMPS54 MI $589.34$3,250.00$84.84 $143,676
132-7039 EMBANK (FNL)(OC)(TY C2)(DS)7,348 CY $65.12$46.00$44.90 -$140,494
247-7192 FL BS(CIP)(TY D, GR 1-2 OR 5)(FNAL POS)8,341 CY $68.84$85.00$41.72 $134,791
344-7031 SP MIXES SP-C SAC-B PG76-229,610 TON $113.30$100.00$97.84 -$127,813
556-7008 PIPE UNDERDRAINS (TY 8) (6")6,448 LF $41.51$22.00$32.77 -$125,800
512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)11,610 LF $25.00$35.00$52.29 $116,100
132-7009 EMBANK (FNL)(OC)(TY C2)13,729 CY $37.02$29.00$8.97 -$110,107
104-7008 REMOV CONC (MEDIANS)5,783 SY $23.10$6.00$22.02 -$98,889
618-7038 CONDT (PVC) (SCH 40) (3") (CONC ENCSE)15,330 LF $21.00$15.00$14.52 -$91,980

Positive: the low bidder was cheaper on that item. These 20 items account for $573,667 of the $279,813 gap.

HUNTER INDUSTRIES, LTD.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $2,749,227.15$523,850.325.25x$2,225,377
132-7009 EMBANK (FNL)(OC)(TY C2)13,729 CY $37.02$8.974.13x$385,100
110-7001 EXCAV (ROADWAY)28,142 CY $24.20$11.682.07x$352,276
451-7024 RETROFIT RAIL (TY SSTR)1,126 LF $350.00$175.012.00x$197,038
403-7001 TEMPORARY SPL SHORING21,393 SF $1.99$25.560.08x-$504,246
512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)11,610 LF $25.00$52.290.48x-$316,823

JORDAN FOSTER CONSTRUCTION, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $3,306,840.41$523,850.326.31x$2,782,990
247-7192 FL BS(CIP)(TY D, GR 1-2 OR 5)(FNAL POS)8,341 CY $85.00$41.722.04x$361,004
132-7009 EMBANK (FNL)(OC)(TY C2)13,729 CY $29.00$8.973.23x$274,993
110-7001 EXCAV (ROADWAY)28,142 CY $21.00$11.681.80x$262,222
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING27 MO $20,500.00$11,585.041.77x$240,704
451-7024 RETROFIT RAIL (TY SSTR)1,126 LF $380.00$175.012.17x$230,818
735-7001 DEBRIS REMOV-CNTR MED/MN LNS/RAMPS54 MI $3,250.00$84.8438.31x$170,918
681-7001 TEMP TRAF SIGNALS8 EA $28,000.00$62,461.140.45x-$275,689

CAPITAL EXCAVATION COMPANY: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $2,775,000.00$523,850.325.30x$2,251,150
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING27 MO $38,000.00$11,585.043.28x$713,204
132-7039 EMBANK (FNL)(OC)(TY C2)(DS)7,348 CY $130.00$44.902.90x$625,292
512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1)11,610 LF $31.00$12.082.57x$219,622
132-7009 EMBANK (FNL)(OC)(TY C2)13,729 CY $23.00$8.972.56x$192,619
132-7008 EMBANK (FNL)(DC)(TY C1)5,090 CY $54.00$17.393.11x$186,346
403-7001 TEMPORARY SPL SHORING21,393 SF $1.70$25.560.07x-$510,450
100-7002 PREPARING ROW112 STA $2,800.00$6,072.920.46x-$366,567
169-7010 SOIL RET BLKT(SL_MOD_CLAY_LONG_ROLL)149,838 SY $1.29$2.710.48x-$212,186

URBAN INFRACONSTRUCTION LLC: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $2,578,955.00$523,850.324.92x$2,055,105
132-7009 EMBANK (FNL)(OC)(TY C2)13,729 CY $45.00$8.975.02x$494,657
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING27 MO $29,387.95$11,585.042.54x$480,679
529-7001 CONC CURB (TY I)12,202 LF $44.62$13.683.26x$377,538
505-7001 TMA (STATIONARY)710 DAY $541.25$217.572.49x$229,812

J3 COMPANY, LLC: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $3,000,000.00$523,850.325.73x$2,476,150
110-7001 EXCAV (ROADWAY)28,142 CY $30.00$11.682.57x$515,500
132-7039 EMBANK (FNL)(OC)(TY C2)(DS)7,348 CY $115.00$44.902.56x$515,072
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING27 MO $28,000.00$11,585.042.42x$443,204
132-7009 EMBANK (FNL)(OC)(TY C2)13,729 CY $35.00$8.973.90x$357,367
132-7008 EMBANK (FNL)(DC)(TY C1)5,090 CY $60.00$17.393.45x$216,886
512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)11,610 LF $25.00$52.290.48x-$316,823