OVERLAY_SH302_SH158_SL338
0572-01-076 · let May 6, 2026 · Ector, Odessa · Overlay
$9,284,543Low bid: JONES BROS. DIRT & PAVING CONTRACTORS, INC.-12.3% vs estimate $10,581,432
$1,854,213Left on the table20.0% gap to the second bid
5BiddersSpread 40% low to high
33Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | JONES BROS. DIRT & PAVING CONTRACTORS, INC. | $9,284,543 | -12.3% | $1,854,213 | 1+$84,382 | 1-$368,850 | |
| 2 | RAGLE CONSTRUCTION, INC. | $11,138,757 | +20.0% | 5.3% | $7,872 | 4+$1,114,152 | 0 |
| 3 | REECE ALBERT, INC. | $11,146,629 | +20.1% | 5.3% | $569,071 | 1+$160,203 | 1-$311,142 |
| 4 | RK HALL, LLC | $11,715,700 | +26.2% | 10.7% | $1,241,666 | 1+$149,227 | 0 |
| 5 | FNF CONSTRUCTION, INC. | $12,957,366 | +39.6% | 22.5% | 4+$2,238,364 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
JONES BROS. DIRT & PAVING CONTRACTORS, INC. vs RAGLE CONSTRUCTION, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $155,000.00 | $1,000,000.00 | $523,850.32 | $845,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $15,000.00 | $60,000.00 | $11,585.04 | $405,000 |
| 347-7001 TOM-C PG76-22 SAC-A | 33,665 TON | $148.00 | $160.00 | $169.86 | $403,980 |
| 247-7069 FL BS (CMP IN PLC)(TY A GR 4) (8") | 20,118 SY | $22.27 | $12.00 | $17.87 | -$206,612 |
| 3007-7001 BONDING COURSE | 58,547 GAL | $2.55 | $5.50 | $3.32 | $172,714 |
| 505-7003 TMA (MOBILE OPERATION) | 175 DAY | $8.50 | $400.00 | $229.60 | $68,513 |
| 344-7005 SP MIXES SP-B SAC-B PG70-22 | 4,369 TON | $125.00 | $140.00 | $94.47 | $65,535 |
| 112-7001 SUBGR WIDEN (OC) | 122 STA | $1,150.00 | $1,600.00 | $458.34 | $54,900 |
| 505-7001 TMA (STATIONARY) | 175 DAY | $82.50 | $300.00 | $217.57 | $38,063 |
| 315-7004 FOG SEAL (CSS-1H) | 29,662 GAL | $3.95 | $5.20 | $4.02 | $37,078 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 265,812 LF | $0.1900 | $0.0700 | $0.2040 | -$31,897 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $19,250.00 | $25,000.00 | $9,253.78 | $23,000 |
| 6025-7001 TMSP RADAR SPEED CONTROL MONITOR | 4 EA | $6,500.00 | $9,500.00 | $8,404.45 | $12,000 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 132,906 LF | $0.7000 | $0.6400 | $0.4757 | -$7,974 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 132,906 LF | $0.6900 | $0.6300 | $0.4986 | -$7,974 |
| 662-7008 WK ZN PAV MRK NON-REMOV (W)6"(SLD) | 265,812 LF | $0.1800 | $0.1600 | $0.2750 | -$5,316 |
| 662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) | 265,812 LF | $0.1800 | $0.1600 | $0.2770 | -$5,316 |
| 506-7046 BIODEG EROSN CONT LOGS (REMOVE) | 1,030 LF | $4.00 | $1.00 | $1.29 | -$3,090 |
| 644-7001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) | 28 EA | $886.60 | $806.00 | $696.14 | -$2,257 |
| 658-7078 REMOVE DELIN & OBJECT MARKER ASSMS | 140 EA | $10.00 | $25.00 | $23.28 | $2,100 |
Positive: the low bidder was cheaper on that item. These 20 items account for $1,857,444 of the $1,854,213 gap.
JONES BROS. DIRT & PAVING CONTRACTORS, INC.: unbalanced items
Placed 1RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,000,000.00 | $523,850.32 | 1.91x | $476,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $60,000.00 | $11,585.04 | 5.18x | $435,735 |
| 112-7001 SUBGR WIDEN (OC) | 122 STA | $1,600.00 | $458.34 | 3.49x | $139,282 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $25,000.00 | $9,253.78 | 2.70x | $62,985 |
REECE ALBERT, INC.: unbalanced items
Placed 3RK HALL, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 112-7001 SUBGR WIDEN (OC) | 122 STA | $1,681.51 | $458.34 | 3.67x | $149,227 |
FNF CONSTRUCTION, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 344-7005 SP MIXES SP-B SAC-B PG70-22 | 4,369 TON | $286.00 | $94.47 | 3.03x | $836,798 |
| 500-7001 MOBILIZATION | 1 LS | $1,294,600.00 | $523,850.32 | 2.47x | $770,750 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $54,000.00 | $11,585.04 | 4.66x | $381,735 |
| 112-7001 SUBGR WIDEN (OC) | 122 STA | $2,500.00 | $458.34 | 5.45x | $249,082 |