SL 494, Via Principale to Royal Crossing
0177-14-038 · let May 6, 2026 · Montgomery, Houston · Overlay
$5,153,278Low bid: DURWOOD GREENE CONSTRUCTION CO.+9.3% vs estimate $4,713,675
$587,151Left on the table11.4% gap to the second bid
6BiddersSpread 25% low to high
66Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | DURWOOD GREENE CONSTRUCTION CO. | $5,153,278 | 9.3% | $587,151 | 3+$129,811 | 2-$416,746 | |
| 2 | ENVIRONMENTAL ALLIES, INC. | $5,740,428 | +11.4% | 21.8% | $97,021 | 2+$83,408 | 3-$417,913 |
| 3 | TEXAS MATERIALS GROUP, INC. | $5,837,449 | +13.3% | 23.8% | $18,961 | 2+$164,689 | 6-$407,967 |
| 4 | HAYDEN PAVING, INC. | $5,856,410 | +13.6% | 24.2% | $144,758 | 4+$182,383 | 1-$323,850 |
| 5 | FOUTSCO PAVING COMPANY, LLC | $6,001,168 | +16.5% | 27.3% | $461,584 | 3+$589,179 | 4-$308,244 |
| 6 | POSILLICO CIVIL, INC. | $6,462,753 | +25.4% | 37.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
DURWOOD GREENE CONSTRUCTION CO. vs ENVIRONMENTAL ALLIES, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 351-7009 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") | 16,737 SY | $40.00 | $73.00 | $77.78 | $552,321 |
| 344-7052 SP MIXES SP-D SAC-A PG70-22 | 14,556 TON | $170.00 | $160.00 | $145.59 | -$145,560 |
| 344-7077 TACK COAT | 30,817 GAL | $3.00 | $5.00 | $3.25 | $61,634 |
| 529-7026 CONC CURB (DOWEL)(SLOTTED) | 900 LF | $65.00 | $6.50 | $49.51 | -$52,650 |
| 134-7001 BACKFILL (TY A) | 332 STA | $150.00 | $300.00 | $224.26 | $49,800 |
| 505-7003 TMA (MOBILE OPERATION) | 150 DAY | $150.00 | $475.00 | $229.60 | $48,750 |
| 112-7002 SUBGR WIDEN (DC) | 26 STA | $2,500.00 | $1,050.00 | $1,009.03 | -$37,700 |
| 344-7001 SP MIXES SP-B PG64-22 | 1,725 TON | $130.00 | $150.00 | $124.45 | $34,500 |
| 354-7073 PLANE ASPH CONC PAV (0" TO 1.5") | 8,740 SY | $7.00 | $3.75 | $3.19 | -$28,405 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $224,545.66 | $523,850.32 | $24,546 |
| 666-7309 ALL-WTHER PM TY I (W)6"(SLD)(100MIL) | 77,017 LF | $0.7500 | $0.9500 | $0.6917 | $15,403 |
| 105-7038 RMV (18") TRT/UNTRT BASE & ASPH PAV | 3,834 SY | $10.00 | $14.00 | $8.86 | $15,336 |
| 505-7001 TMA (STATIONARY) | 148 DAY | $300.00 | $400.00 | $217.57 | $14,800 |
| 100-7002 PREPARING ROW | 26 STA | $2,500.00 | $3,000.00 | $6,072.92 | $13,000 |
| 666-7315 ALL-WTHER PM TY I (Y)6"(SLD)(100MIL) | 64,160 LF | $0.7500 | $0.9500 | $0.6819 | $12,832 |
| 400-7010 CEM STABIL BKFL | 95 CY | $1.00 | $125.00 | $138.14 | $11,780 |
| 104-7005 REMOV CONC (MOWSTRIP) | 3,724 LF | $25.00 | $22.00 | $9.49 | -$11,172 |
| 305-7029 SLV, HAUL, & STKPL REL APH PV (9") | 3,834 SY | $10.00 | $7.50 | $10.00 | -$9,585 |
| 104-7016 REMOV CONC (CURB) | 900 LF | $15.00 | $6.00 | $6.82 | -$8,100 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $7,000.00 | $8,000.00 | $11,585.04 | $8,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $569,530 of the $587,151 gap.
DURWOOD GREENE CONSTRUCTION CO.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 104-7005 REMOV CONC (MOWSTRIP) | 3,724 LF | $25.00 | $9.49 | 2.64x | $57,770 |
| 112-7002 SUBGR WIDEN (DC) | 26 STA | $2,500.00 | $1,009.03 | 2.48x | $38,765 |
| 354-7073 PLANE ASPH CONC PAV (0" TO 1.5") | 8,740 SY | $7.00 | $3.19 | 2.19x | $33,276 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
| 100-7002 PREPARING ROW | 26 STA | $2,500.00 | $6,072.92 | 0.41x | -$92,896 |
ENVIRONMENTAL ALLIES, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 104-7005 REMOV CONC (MOWSTRIP) | 3,724 LF | $22.00 | $9.49 | 2.32x | $46,598 |
| 505-7003 TMA (MOBILE OPERATION) | 150 DAY | $475.00 | $229.60 | 2.07x | $36,810 |
| 500-7001 MOBILIZATION | 1 LS | $224,545.66 | $523,850.32 | 0.43x | -$299,305 |
| 100-7002 PREPARING ROW | 26 STA | $3,000.00 | $6,072.92 | 0.49x | -$79,896 |
| 529-7026 CONC CURB (DOWEL)(SLOTTED) | 900 LF | $6.50 | $49.51 | 0.13x | -$38,713 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 354-7073 PLANE ASPH CONC PAV (0" TO 1.5") | 8,740 SY | $15.00 | $3.19 | 4.70x | $103,196 |
| 104-7005 REMOV CONC (MOWSTRIP) | 3,724 LF | $26.00 | $9.49 | 2.74x | $61,494 |
| 100-7002 PREPARING ROW | 26 STA | $1,250.00 | $6,072.92 | 0.21x | -$125,396 |
| 344-7077 TACK COAT | 30,817 GAL | $0.1100 | $3.25 | 0.03x | -$96,698 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $1,580.00 | $11,585.04 | 0.14x | -$80,040 |
| 305-7029 SLV, HAUL, & STKPL REL APH PV (9") | 3,834 SY | $0.1000 | $10.00 | 0.01x | -$37,957 |
| 505-7003 TMA (MOBILE OPERATION) | 150 DAY | $1.00 | $229.60 | 0.00x | -$34,290 |
| 105-7038 RMV (18") TRT/UNTRT BASE & ASPH PAV | 3,834 SY | $0.1000 | $8.86 | 0.01x | -$33,587 |
HAYDEN PAVING, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 104-7005 REMOV CONC (MOWSTRIP) | 3,724 LF | $28.00 | $9.49 | 2.95x | $68,942 |
| 112-7002 SUBGR WIDEN (DC) | 26 STA | $2,750.00 | $1,009.03 | 2.73x | $45,265 |
| 104-7016 REMOV CONC (CURB) | 900 LF | $50.00 | $6.82 | 7.34x | $38,866 |
| 505-7003 TMA (MOBILE OPERATION) | 150 DAY | $425.00 | $229.60 | 1.85x | $29,310 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
FOUTSCO PAVING COMPANY, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $75,000.00 | $11,585.04 | 6.47x | $507,320 |
| 105-7038 RMV (18") TRT/UNTRT BASE & ASPH PAV | 3,834 SY | $20.00 | $8.86 | 2.26x | $42,710 |
| 104-7005 REMOV CONC (MOWSTRIP) | 3,724 LF | $20.00 | $9.49 | 2.11x | $39,150 |
| 100-7002 PREPARING ROW | 26 STA | $500.00 | $6,072.92 | 0.08x | -$144,896 |
| 344-7077 TACK COAT | 30,817 GAL | $0.1000 | $3.25 | 0.03x | -$97,006 |
| 505-7003 TMA (MOBILE OPERATION) | 150 DAY | $1.00 | $229.60 | 0.00x | -$34,290 |
| 505-7001 TMA (STATIONARY) | 148 DAY | $1.00 | $217.57 | 0.00x | -$32,053 |