Bid Tab X-ray: 0177-14-038

May 6, 2026 · Montgomery Sign up free
Set your company to personalize scores

SL 494, Via Principale to Royal Crossing

0177-14-038 · let May 6, 2026 · Montgomery, Houston · Overlay

$5,153,278Low bid: DURWOOD GREENE CONSTRUCTION CO.+9.3% vs estimate $4,713,675
$587,151Left on the table11.4% gap to the second bid
6BiddersSpread 25% low to high
66Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1DURWOOD GREENE CONSTRUCTION CO. $5,153,2789.3% $587,151 3+$129,811 2-$416,746
2ENVIRONMENTAL ALLIES, INC. $5,740,428+11.4%21.8% $97,021 2+$83,408 3-$417,913
3TEXAS MATERIALS GROUP, INC. $5,837,449+13.3%23.8% $18,961 2+$164,689 6-$407,967
4HAYDEN PAVING, INC. $5,856,410+13.6%24.2% $144,758 4+$182,383 1-$323,850
5FOUTSCO PAVING COMPANY, LLC $6,001,168+16.5%27.3% $461,584 3+$589,179 4-$308,244
6POSILLICO CIVIL, INC. $6,462,753+25.4%37.1%

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

DURWOOD GREENE CONSTRUCTION CO. vs ENVIRONMENTAL ALLIES, INC., biggest item swings
ItemQtyLow2ndMarket2nd minus low
351-7009 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")16,737 SY $40.00$73.00$77.78 $552,321
344-7052 SP MIXES SP-D SAC-A PG70-2214,556 TON $170.00$160.00$145.59 -$145,560
344-7077 TACK COAT30,817 GAL $3.00$5.00$3.25 $61,634
529-7026 CONC CURB (DOWEL)(SLOTTED)900 LF $65.00$6.50$49.51 -$52,650
134-7001 BACKFILL (TY A)332 STA $150.00$300.00$224.26 $49,800
505-7003 TMA (MOBILE OPERATION)150 DAY $150.00$475.00$229.60 $48,750
112-7002 SUBGR WIDEN (DC)26 STA $2,500.00$1,050.00$1,009.03 -$37,700
344-7001 SP MIXES SP-B PG64-221,725 TON $130.00$150.00$124.45 $34,500
354-7073 PLANE ASPH CONC PAV (0" TO 1.5")8,740 SY $7.00$3.75$3.19 -$28,405
500-7001 MOBILIZATION1 LS $200,000.00$224,545.66$523,850.32 $24,546
666-7309 ALL-WTHER PM TY I (W)6"(SLD)(100MIL)77,017 LF $0.7500$0.9500$0.6917 $15,403
105-7038 RMV (18") TRT/UNTRT BASE & ASPH PAV3,834 SY $10.00$14.00$8.86 $15,336
505-7001 TMA (STATIONARY)148 DAY $300.00$400.00$217.57 $14,800
100-7002 PREPARING ROW26 STA $2,500.00$3,000.00$6,072.92 $13,000
666-7315 ALL-WTHER PM TY I (Y)6"(SLD)(100MIL)64,160 LF $0.7500$0.9500$0.6819 $12,832
400-7010 CEM STABIL BKFL95 CY $1.00$125.00$138.14 $11,780
104-7005 REMOV CONC (MOWSTRIP)3,724 LF $25.00$22.00$9.49 -$11,172
305-7029 SLV, HAUL, & STKPL REL APH PV (9")3,834 SY $10.00$7.50$10.00 -$9,585
104-7016 REMOV CONC (CURB)900 LF $15.00$6.00$6.82 -$8,100
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING8 MO $7,000.00$8,000.00$11,585.04 $8,000

Positive: the low bidder was cheaper on that item. These 20 items account for $569,530 of the $587,151 gap.

DURWOOD GREENE CONSTRUCTION CO.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
104-7005 REMOV CONC (MOWSTRIP)3,724 LF $25.00$9.492.64x$57,770
112-7002 SUBGR WIDEN (DC)26 STA $2,500.00$1,009.032.48x$38,765
354-7073 PLANE ASPH CONC PAV (0" TO 1.5")8,740 SY $7.00$3.192.19x$33,276
500-7001 MOBILIZATION1 LS $200,000.00$523,850.320.38x-$323,850
100-7002 PREPARING ROW26 STA $2,500.00$6,072.920.41x-$92,896

ENVIRONMENTAL ALLIES, INC.: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
104-7005 REMOV CONC (MOWSTRIP)3,724 LF $22.00$9.492.32x$46,598
505-7003 TMA (MOBILE OPERATION)150 DAY $475.00$229.602.07x$36,810
500-7001 MOBILIZATION1 LS $224,545.66$523,850.320.43x-$299,305
100-7002 PREPARING ROW26 STA $3,000.00$6,072.920.49x-$79,896
529-7026 CONC CURB (DOWEL)(SLOTTED)900 LF $6.50$49.510.13x-$38,713

TEXAS MATERIALS GROUP, INC.: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
354-7073 PLANE ASPH CONC PAV (0" TO 1.5")8,740 SY $15.00$3.194.70x$103,196
104-7005 REMOV CONC (MOWSTRIP)3,724 LF $26.00$9.492.74x$61,494
100-7002 PREPARING ROW26 STA $1,250.00$6,072.920.21x-$125,396
344-7077 TACK COAT30,817 GAL $0.1100$3.250.03x-$96,698
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING8 MO $1,580.00$11,585.040.14x-$80,040
305-7029 SLV, HAUL, & STKPL REL APH PV (9")3,834 SY $0.1000$10.000.01x-$37,957
505-7003 TMA (MOBILE OPERATION)150 DAY $1.00$229.600.00x-$34,290
105-7038 RMV (18") TRT/UNTRT BASE & ASPH PAV3,834 SY $0.1000$8.860.01x-$33,587

HAYDEN PAVING, INC.: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
104-7005 REMOV CONC (MOWSTRIP)3,724 LF $28.00$9.492.95x$68,942
112-7002 SUBGR WIDEN (DC)26 STA $2,750.00$1,009.032.73x$45,265
104-7016 REMOV CONC (CURB)900 LF $50.00$6.827.34x$38,866
505-7003 TMA (MOBILE OPERATION)150 DAY $425.00$229.601.85x$29,310
500-7001 MOBILIZATION1 LS $200,000.00$523,850.320.38x-$323,850

FOUTSCO PAVING COMPANY, LLC: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING8 MO $75,000.00$11,585.046.47x$507,320
105-7038 RMV (18") TRT/UNTRT BASE & ASPH PAV3,834 SY $20.00$8.862.26x$42,710
104-7005 REMOV CONC (MOWSTRIP)3,724 LF $20.00$9.492.11x$39,150
100-7002 PREPARING ROW26 STA $500.00$6,072.920.08x-$144,896
344-7077 TACK COAT30,817 GAL $0.1000$3.250.03x-$97,006
505-7003 TMA (MOBILE OPERATION)150 DAY $1.00$229.600.00x-$34,290
505-7001 TMA (STATIONARY)148 DAY $1.00$217.570.00x-$32,053